Permit Information
Permit NumberBLD19-03694
StatusIssued
Name WRIGHT BROTHERS THE BLDG CO EAGLE
Site Address 3033 W ELDER ST
Project NameWells Fargo - Fuel Tank
Customer Number 
ePlanReviewYes
Description
(WELLS FARGO - FUEL TANK) This is a scope of work permit, a certificate of completion is to be issued upon final inspection approval. Permit to excavate and remove an existing 10,000 gallon diesel fuel tank and replace with a new 750 gallon above ground diesel fuel tank on a new concrete pad with new underground piping to existing fuel riser in building. The tank to be fastened to the concrete slab by (4) anchor bolts. Approval is contingent on adhering to the approved plans, engineering, local codes and ordinances. MDH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/16/20207/17/20207/17/2020ANR
DetailsJim Storey
Josh *screened* Phone #: ###-#### plm and fire need signed off// nuts need tightened.
Plan Reviewer's activity  7/17/2020 DONE
DetailsMichael Hanson
Removed plumbing inspection sign off requirement per Dan Ediger and Carl Madsen. DEQ is to inspect.
Inspection Record Card- Bld  6/30/2020 DONE
BLD-Final6/25/20206/26/20206/26/2020ADEFR
DetailsJim Storey
Nicol....... screened Phone #: ###-#### planreview and plm sup. revising permit and communicating with permitees
Plan Reviewer's activity  6/25/2020 DONE
DetailsMichael Hanson
Added plumbing inspection sign off requirements.
Print Occupancy Form  6/25/2020 DONE
BLD-Foundation11/6/201911/6/201911/6/2019PPASS
DetailsJim Storey
rebar // Nicol Phone #: ###-####
Permit Ready to Issue  11/6/2019 DONE
Issue PAID IN FULL permit  11/6/2019 DONE
Routing - FIRE11/5/201911/5/201911/5/2019 PASS
DetailsMark Stumbaugh
PLANS/APPL TAKEN TO FRONT DESK  11/5/2019 DONE
DetailsMark Stumbaugh
Meeting  11/5/2019 DONE
waiting to hear back from tisha, unable to batch stamp an item
Plan assigned to (M_H)10/11/2019 11/5/2019 DONE
DetailsMichael Hanson
3rd review completed - 10/16 #518 L1 ePlan - Wells Fargo - Fuel Tank
Routing - PLAN CHECK11/5/2019 11/5/2019 PASS
DetailsMichael Hanson
Routing - FIRE11/4/201911/4/201911/4/2019 FAIL
DetailsMark Stumbaugh
Routing - PLAN CHECK11/4/2019 11/4/2019 FAIL
DetailsMichael Hanson
Plans need updated to reflect new fuel tank location. Engineering is updating frost depth and anchor bolt information.
Route to Impact Fee Review10/16/201910/19/201910/17/2019 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  10/16/2019 DONE
DetailsMichael Hanson
Routing - PLAN CHECK10/11/2019 10/16/2019 FAIL
DetailsMichael Hanson
See changemarks in ePlan for corrections required.
Routing - FIRE10/11/201910/11/201910/15/2019 FAIL
DetailsErika Akin
10/16 L1 Wells Fargo - Fuel Tank ePlan
Routing PW Drainage10/11/2019 10/15/2019 PASS
DetailsBrian Murphy
O and M of utility treaching small above ground tank
Routing - MECHANICAL10/11/2019 10/15/2019 PASS
DetailsTroy James
No mechanical work.
Routing - PUBLIC WORKS10/11/2019 10/11/2019 PASS
DetailsMorgan Webb
Routing - Design Review10/11/2019 10/11/2019 PASS
DetailsJosh Wilson
Intake Approval  10/10/2019 PASS
DetailsJavier Guzman
Intake Approval  9/27/2019 FAIL
DetailsBrian McGowan
1. No engineering calculations were provided. Please upload them. (Provide form #310 if Special Inspections are required.)
2. Please indicate how the tank is attached to the slab.
Intake Approval  9/25/2019 FAIL
DetailsBrian McGowan
Please address or provide the following for your Prescreen to be approved:
1. Planning and Zoning Letters of Approval.
2. Sheet C1.0 does not provide the required area for the City Approval Stamp in the lower right corner.
3. Please list the City of Boise Current Codes on the Cover Sheet.
4. No engineering calculations were provided. Please upload them. (Provide form #310 if Special Inspections are required.)
Intake Approval  9/19/2019 FAIL
DetailsBrian McGowan
No Submittal Checklist was uploaded and no Drawings were uploaded.
Application received  9/18/2019 DONE
Application submitted via PDS Online on Sep 18 2019 4:48PM