Permit Information
Permit NumberBLD19-03698
StatusFinaled
Name ONE & DONE REMODELING LLC
Site Address 6566 S FEDERAL WAY
Project NameForever Nails Salon
Customer Number 
ePlanReviewYes
Description
(FOREVER NAILS SALON – INTERIOR TENANT IMPROVEMENT) (11-27-19 PLAN MODIFICATION TO CHANGE PLUMBING PIPE SIZES AND ROUTING.) This building has a fire sprinkler system. To remodel an existing 1,154 square foot tenant space located within an existing 8,125 square foot strip mall building for a new nail salon tenant. This tenant space was formerly occupied by “General Nutrition Center”. Two new sinks, 3 manicure tables, 2 nail polish stations, and 6 pedicure chairs will be provided. Work is to include saw cutting the concrete slab on grade floor to accommodate new under slab plumbing, patching the concrete floor slab, and new tile flooring. An electrical washer and a dryer will also be installed. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/10/20201/10/20201/10/2020PPASS
DetailsJim Storey
John Phone #: ###-####
FIRE-Final Inspection1/9/20201/10/20201/10/2020APASS
DetailsJim Page
Previously noted have been corrected, no fire sprinkler modifications, no fire alarm modificaitons, fire exitnguisher is placed with current inspection tag. Final life fire safety inspection for area of work complete, signatures provided on permit sign off card.

john Phone #: ###-####
Permanent Occupancy  1/10/2020 DONE
FIRE-Final Inspection1/8/20201/9/20201/9/2020AFAIL
DetailsJim Page
Provide annual inspection for fire extinguisher. Install ceiling tiles that are missing, ceiling tiles must be in place or upright fire sprinkler protection will be required, a seperate permit will be required if fire sprinkler system needs modified. Provide signage at main entry reading "Door to remain unlocked while building is occupied".

John Phone #: ###-####
Plan assigned to (CJW)11/22/201911/22/201911/27/2019 PASS
DetailsCarl Westfall
plan mod - Forever Nails - Routed to staff.
Plan Reviewer's activity  11/27/2019 PASS
Plan mod approved
Permit Ready to Issue  11/27/2019 DONE
PLAN MOD
Print Occupancy Form  11/27/2019 DONE
CHANGE STATUS TO (ISS)  11/27/2019 DONE
Routing - PLUMBING11/25/2019 11/26/2019 PASS
DetailsDan Ediger
Install 3 in. end of line clean out.
Routing PW Sewer Rating11/25/2019 11/25/2019 PASS
DetailsMorgan Webb
SAME FIXTURE COUNT.
Routing - PLAN CHECK11/25/2019 11/25/2019 PASS
DetailsCarl Westfall
Plan mod approved
Routing - PLAN CHECK11/22/2019 11/25/2019 PASS
DetailsCarl Westfall
Plan mod plan intake review
Plan Modification Accepted  11/22/2019 DONE
plan mod to submit plumbing change
Issue PAID IN FULL permit  11/1/2019 DONE
Emailed permits to be signed to- onedoneremodeling@gmail.com
Eplan needs to be released
Print Occupancy Form  11/1/2019 DONE
Plan assigned to (CJW)9/26/201910/21/201910/29/2019 PASS
DetailsCarl Westfall
(1st done) 10/14/19 (L-3 - 15 days) (eplan - 6 sheets) Forever Nails (routed to staff)
PLANS/APPL TAKEN TO FRONT DESK  10/29/2019 DONE
Please call the tenant owner Duc Nyguen at ###-#### when the permit is ready to issue.
Permit Ready to Issue  10/29/2019 DONE
ALL MET (onedoneremodeling@gmail.com)
NEED
GC
Revised Certificate of Value

Telephone call  10/29/2019 DONE
called Duc Nyguen and informed him that we need a 302 and 306 form
and the if he is going to be his own GC he will need a letter from the parcel owner giving him authority to do the work, he was also inform that the GC for the trades need will need to be license
Routing - PLAN CHECK10/25/2019 10/28/2019 PASS
DetailsCarl Westfall
Routed drawings
Routing - MECHANICAL10/28/2019 10/28/2019 PASS
DetailsTroy James
Plan resubmittals received  10/24/2019 DONE
Route to Impact Fee Review10/22/201910/25/201910/23/2019 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  10/22/2019 DONE
Plan resubmittals requested  10/22/2019 DONE
Routing - PLAN CHECK9/26/2019 10/22/2019 PASS
DetailsCarl Westfall
Routing - FIRE9/26/20199/26/201910/21/2019 PASS
DetailsErika Akin
Attached comments to case
Routing - MECHANICAL9/26/2019 10/2/2019 FAIL
DetailsTroy James
See eplan
Routing - PLANNING9/26/2019 9/30/2019 PASS
DetailsDavid Moser
Routing - Addressing9/26/2019 9/30/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS9/26/2019 9/30/2019 PASS
DetailsMorgan Webb
Routing - PLUMBING9/26/2019 9/27/2019 PASS
DetailsDan Ediger
Per plans and ISPC
Intake Approval  9/24/2019 PASS
Plan Reviewer's activity  9/20/2019 PASS
Plan intake review approved
Application received  9/19/2019 DONE
Application submitted via PDS Online on Sep 19 2019 9:36AM