BLD-Final | 2/19/2020 | 2/19/2020 | 2/19/2020 | P | PASS |
Dave Hannah
|
|
|
Brandon Phone #: ###-####
|
Zoning Approval | 2/19/2020 | 2/19/2020 | 2/19/2020 | | PASS |
KayCee Babb
|
|
|
Per DRH19-00284 and plans approved through Building permit. Any future exterior alterations or temporary uses shall require additional review.
|
FIRE-Final Inspection | 2/14/2020 | 2/14/2020 | 2/14/2020 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Brandon Phone #: ###-####
|
BLD-Final | 2/13/2020 | 2/14/2020 | 2/14/2020 | A | NR |
Jim Storey
|
|
|
call with questions- Brandon Phone #: ###-#### need p&z and fire sign offs
|
BLD-Framing/Rough-in | 2/10/2020 | 2/11/2020 | 2/11/2020 | P | PASS |
Dave Hannah
|
|
|
call 1 hr ahead // Brandon Phone #: ###-####
|
Plan Reviewer's activity | | | 1/13/2020 | | DONE |
Michael Hanson
|
|
|
Removed requirement for special inspections. New patio design does not have post installed epoxy or welding.
|
Inspection Record Card- Bld | | | 1/10/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/10/2020 | | DONE |
|
|
|
|
Telephone call | | | 1/7/2020 | | DONE |
|
|
|
called Carrie asking her for the 302 and 306 from the GC. She said that she believes the owner is hiring a GC and has forwarded my email to them to get the forms signed by the right people.
|
Route to Impact Fee Review | 1/3/2020 | 1/6/2020 | 1/6/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 1/6/2020 | | DONE |
|
|
|
all met:
ACHD
GC Form
Revised Cert of Value
(double check impact fees activity is signed off)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/3/2020 | | DONE |
Michael Hanson
|
|
|
|
Routing Off Site - STRUCTURAL | 1/3/2020 | | 1/3/2020 | | PASS |
Michael Hanson
|
|
|
Per ePlan approval
|
Plan assigned to (M_H) | 10/4/2019 | | 1/3/2020 | | DONE |
Michael Hanson
|
|
|
2nd review completed - 10/10 #518 L2 ePlan - Patio Addition
|
Routing - PLAN CHECK | 12/26/2019 | | 12/26/2019 | | PASS |
Michael Hanson
|
|
|
|
Routing PW Solid Waste | 12/19/2019 | | 12/20/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Street Lights | 12/19/2019 | | 12/20/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing Off Site - STRUCTURAL | 12/18/2019 | | 12/20/2019 | | FAIL |
Michael Hanson
|
|
|
See changemark in ePlan for corrections required.
|
Routing PW Drainage | 12/19/2019 | | 12/19/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - Design Review | 12/18/2019 | | 12/18/2019 | | PASS |
KayCee Babb
|
|
|
To comply with all conditions of approval of DRH19-00284, as revised November 20, 2019. Conditions of approval include, but are not limited to: Existing patio enclosure on site, using corrugated metal and wood, shall be removed from the site or documentation of Design Review approval submitted to Staff; Site is not approved for outdoor storage of shipping containers. All shipping containers shall be removed from the site.
|
Routing - PLANNING | 12/18/2019 | | 12/18/2019 | | PASS |
David Moser
|
|
|
|
Plan Reviewer's activity | | | 12/4/2019 | | DONE |
Michael Hanson
|
|
|
Emailed applicant for status. They have completely redesigned and they are discussing with DR before resubmitting.
|
Routing Off Site - STRUCTURAL | 10/4/2019 | | 10/18/2019 | | FAIL |
Michael Hanson
|
|
|
Per ePlan corrections required by D. Haugland @ AHJ
|
1st review completed | | | 10/18/2019 | | DONE |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 10/10/2019 | | 10/10/2019 | | FAIL |
Michael Hanson
|
|
|
|
Routing PW Solid Waste | 10/4/2019 | | 10/8/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Street Lights | 10/4/2019 | | 10/7/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Drainage | 10/4/2019 | | 10/4/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing - Design Review | 10/4/2019 | | 10/4/2019 | | PASS |
KayCee Babb
|
|
|
To comply with all conditions of approval of DRH19-00284, as revised Aug. 20, 2019. Conditions of approval include, but are not limited to: Existing patio enclosure on site, using corrugated metal and wood, shall be removed from the site or documentation of Design Review approval submitted to Staff; Site is not approved for outdoor storage of shipping containers. All shipping containers shall be removed from the site.
|
Routing - PUBLIC WORKS | 10/4/2019 | | 10/4/2019 | | PASS |
Morgan Webb
|
|
|
|
Plan Reviewer's activity | | | 9/30/2019 | | DONE |
Michael Hanson
|
|
|
***APPLICANT DID NOT PROVIDE COMPLETED #310 COVERSHEET (MISSING OWNERS SIGNATURE) I APPROVED THE PRESCREEN AS I DIDN'T WANT TO HOLD UP THE REVIEW FOR A SINGLE SIGNATURE. THE #310 SHALL BE UPDATED WITH ALL FIELDS COMPLETED PRIOR TO ISSUING PERMIT. MDH 09-30-2019
|
Intake Approval | | | 9/26/2019 | | FAIL |
Michael Hanson
|
|
|
09/26
#310 form must be completed in it's entirety and upload all 10 pages. There is epoxy being used and so a special inspection is required and must be indicated on pg. 2 and pg. 3 table 2 the #310 form.
---------------------
Please provide the 310 special inspection form for welding and post installed anchors.
Please provide documentation for shade material demonstrating compliance with Section 3105.
Update the steel beam and footing calculations to show IBC 2015 instead of IBC 2012.
|
Intake Approval | | | 9/24/2019 | | FAIL |
Michael Hanson
|
|
|
|
Application received | | | 9/19/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 19 2019 11:01AM
|