BLD-Footing | 10/16/2019 | 10/17/2019 | 10/17/2019 | P | PASS |
Tony Young
|
|
|
RYAN Phone #: ###-####,, pool rebar ok
|
PubWorks Subgrade Approval | 10/15/2019 | 10/15/2019 | 10/15/2019 | | DONE |
Melissa Jannusch
|
|
|
*POOL* A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
OVERRIDE | | | 10/3/2019 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/3/2019 | | DONE |
|
|
|
|
Telephone call | | | 10/3/2019 | | DONE |
|
|
|
spoke with Ryan informing permit is ready and fee amount due
|
Issue PAID IN FULL permit | | | 10/3/2019 | | DONE |
|
|
|
|
1st review completed | | | 10/3/2019 | | DONE |
Rob Patrick
|
|
|
|
Case Summary (BLD) | | | 10/3/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/3/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 10/3/2019 | | DONE |
|
|
|
|
Plan assigned to (RDP) | 9/19/2019 | | 10/3/2019 | | DONE |
Rob Patrick
|
|
|
10/02 Pool L2 PAPER...09-26-19 Delivered to Melissa for review
|
Routing - PLAN CHECK | 9/23/2019 | | 10/3/2019 | | PASS |
Rob Patrick
|
|
|
|
Routing - PUBLIC WORKS | 9/19/2019 | | 10/1/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Grading-Hillside | 10/1/2019 | | 10/1/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Plan Reviewer's activity | | | 9/26/2019 | | |
|
|
|
Delivered entire package to Melissa for her review
|
Routing - Erosion and Sediment | 9/19/2019 | | 9/23/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified RP.
|
Routing - PLANNING | 9/19/2019 | | 9/20/2019 | | PASS |
Sue Cummings
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 9/19/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/19/2019 | | DONE |
|
|
|
no intake fee taken- 426 application
|
Intake Approval | | | 9/19/2019 | | PASS |
|
|
|
|
Meeting | | | 9/19/2019 | | DONE |
|
|
|
taken to planning intake basket
|
Application received | | 9/19/2019 | | | |
|
|
|
|