BLD-Final | 3/24/2020 | 3/25/2020 | 3/25/2020 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Cindi Lee
|
DOC - Permit Finaled | 3/25/2020 | 3/25/2020 | 3/25/2020 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 3/18/2020 | 3/20/2020 | 3/20/2020 | P | NR |
Mike Jordan
|
|
|
Cindy Phone #: ###-####. Needs mech final, plumbing final has failed.
|
BLD-Framing/Rough-in | 1/2/2020 | 1/3/2020 | 1/3/2020 | P | PASS |
Mike Jordan
|
|
|
Cindy Phone #: ###-####
|
BLD-Framing/Rough-in | 12/30/2019 | 12/31/2019 | 12/31/2019 | A | PART |
Mike Jordan
|
|
|
Cindy Phone #: ###-####. Needs to remove sheetrock at furred walls to complete fireblocking.
|
Routing Walk-In (Zoning) | 9/19/2019 | 9/19/2019 | 9/19/2019 | P | PASS |
Stephanie Leonard
|
|
|
|
Routing Walk-In (BLD) | 9/19/2019 | 9/19/2019 | 9/19/2019 | P | DONE |
Rob Patrick
|
|
|
|
Plan assigned to (RDP) | 9/19/2019 | 9/19/2019 | 9/19/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/19/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 9/19/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 9/19/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/19/2019 | | 9/19/2019 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 9/19/2019 | | DONE |
Rob Patrick
|
|
|
|
Inspection Record Card- Bld | | | 9/19/2019 | | DONE |
Rob Patrick
|
|
|
|
Case Summary (BLD) | | | 9/19/2019 | | DONE |
Rob Patrick
|
|
|
|
Application received | | 9/19/2019 | | | |
|
|
|
|