BLD-Final | 4/10/2020 | 4/13/2020 | 4/13/2020 | P | PASS |
Tony Young
|
|
|
Vinnie - Screened for Covid 19 symptoms Phone #: ###-####
|
DOC - Permit Finaled | 4/13/2020 | 4/13/2020 | 4/13/2020 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Blower Door Test Results | 4/13/2020 | 4/13/2020 | 4/13/2020 | P | DONE |
Tony Young
|
|
|
Vinnie - Screened for Covid 19 symptoms Phone #: ###-####// 3,92
|
BLD-Wall cover | 3/2/2020 | 3/3/2020 | 3/3/2020 | A | PASS |
Jim Storey
|
|
|
Vinnie Phone #: ###-#### soffit per plan 1 layer gyp.
|
BLD-Energy code compliance | 2/28/2020 | 3/2/2020 | 3/2/2020 | A | PASS |
Jim Storey
|
|
|
Vinny Phone #: ###-####
|
BLD-Framing/Rough-in | 2/27/2020 | 2/27/2020 | 2/27/2020 | P | PART |
Jim Storey
|
|
|
Vinnie Phone #: ###-#### ok to insulate.
|
BLD-Energy code compliance | 2/25/2020 | 2/26/2020 | 2/26/2020 | A | PART |
Jim Storey
|
|
|
Vinnie Phone #: ###-#### airseal ok
|
BLD-Framing/Rough-in | 2/25/2020 | 2/26/2020 | 2/26/2020 | A | PART |
Jim Storey
|
|
|
Vinnie Phone #: ###-#### c/n posted
|
BLD-Framing/Rough-in | 2/24/2020 | 2/25/2020 | 2/25/2020 | A | NR |
Dave Hannah
|
|
|
Vinnie Phone #: ###-#### needs mec rough in and ceiling and floor truss engineering on site
|
BLD-Energy code compliance | 2/24/2020 | 2/25/2020 | 2/25/2020 | A | PART |
Dave Hannah
|
|
|
Vinnie Phone #: ###-#### air seal package ok
|
BLD-Wall Bracing | 2/12/2020 | 2/13/2020 | 2/13/2020 | A | PASS |
Jim Storey
|
|
|
Vinnie Phone #: ###-####
|
BLD-Foundation | 12/24/2019 | 12/26/2019 | 12/26/2019 | P | PASS |
Tell Riley
|
|
|
Jerry Phone #: ###-####//per plans//
|
BLD-Footing | 12/23/2019 | 12/24/2019 | 12/24/2019 | A | PASS |
Brandon Shaw
|
|
|
Frost protection is required...
|
BLD-Footing | 12/20/2019 | 12/23/2019 | 12/23/2019 | P | NR |
Brandon Shaw
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/13/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/13/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/13/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 12/5/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 11/12/2019 | 11/12/2019 | 12/5/2019 | | DONE |
Jenny Nelson
|
|
|
Need full size plans. 1st complete, failed planning, need shear calcs
|
Routing - PLAN CHECK | 12/5/2019 | | 12/5/2019 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/5/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 12/5/2019 | | DONE |
|
|
|
met
|
Routing - PLANNING | 12/3/2019 | | 12/4/2019 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PLAN CHECK | 12/3/2019 | | 12/3/2019 | | FAIL |
Jenny Nelson
|
|
|
Need full size plans
|
Plan assigned to (RDP) | 10/2/2019 | 10/2/2019 | 11/12/2019 | | DEFR |
Rob Patrick
|
|
|
10/15 sfd L1 ePlan
|
Routing - PLAN CHECK | 10/2/2019 | | 11/12/2019 | | FAIL |
Jenny Nelson
|
|
|
Shear wall calcs
|
1st review completed | | | 11/12/2019 | | DONE |
Jenny Nelson
|
|
|
|
Route to Impact Fee Review | 10/2/2019 | 10/5/2019 | 10/3/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 10/2/2019 | | 10/3/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 10/2/2019 | | 10/2/2019 | | FAIL |
Katelyn Menuge
|
|
|
Update window on elevations to match floor plans.
|
Routing - Addressing | 10/2/2019 | | 10/2/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/2/2019 | | 10/2/2019 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/2/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/2/2019 | | DONE |
|
|
|
|
Intake Approval | | | 10/2/2019 | | PASS |
|
|
|
|
Intake Approval | | | 9/30/2019 | | FAIL |
|
|
|
Please upload a Manual J with the correct address listed.
|
Application received | | | 9/24/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 24 2019 3:08PM
|