(FIBERPIPE ANTENNA) (DRH19-00428) SPECIAL INSPECTIONS REQUIRED- SOILS AND CONCRETE. Permit to construct a 9.2 Antenna and Foundation. Scope of work to include; Site modifications, under ground utility work and preparation to construct a concrete slab on grade for the antenna and equipment; installation of antenna and equipment as per engineering and specifications. All work shall comply with the approved plans, Engineering, DRH19-00428 and all applicable codes. To comply with ACI 301 ***BJM***
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Occupancy Approval7/28/20207/28/20207/28/2020 DONE
DetailsTiffany Lowery
BLD-Final7/22/20207/23/20207/23/2020PPASS
DetailsTony Young
Please call Jared 15 minutes prior at ###-#### Phone #: ###-#### Inspection requested via web by Jared Waggoner// ok per 450
DOC - Permit Finaled7/23/20207/23/20207/23/2020PPASS
DetailsTony Young
BLD-Concrete11/7/201911/8/201911/8/2019PPASS
DetailsTell Riley
East mechanical pad, west and north aprons Phone #: ###-#### Inspection requested via web by Jared Waggoner//ok per plans and engineering//maintain clearances on rebar in turned down footings//pending specials//
BLD-Foundation10/21/201910/22/201910/22/2019PPASS
DetailsMike Jordan
Please call Jared at ###-#### 15 minutes ahead for access, east side Phone #: ###-#### Inspection requested via web by Jared Waggoner
Permit Ready to Issue  10/21/2019 DONE
MET
NEED
GC FORM
REVISED VALUE
Issue PAID IN FULL permit  10/21/2019 DONE
Inspection Record Card- Bld  10/21/2019 DONE
Plan assigned to (BJM)9/27/201910/2/201910/18/2019 DONE
DetailsBrian McGowan
10/22- 1st Review Complete- 502 FiberPipe Antenna on W. Emerald
Routing - PLANNING10/2/2019 10/18/2019 PASS
DetailsCeline Acord
No Current Planning Review
Routing - PLAN CHECK10/18/2019 10/18/2019 PASS
DetailsBrian McGowan
Routing PW Drainage10/18/2019 10/18/2019 PASS
DetailsBrian Murphy
PLANS/APPL TAKEN TO FRONT DESK  10/18/2019 DONE
DetailsBrian McGowan
Route to Impact Fee Review10/16/201910/19/201910/17/2019 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - Design Review10/9/2019 10/17/2019 PASS
DetailsKayCee Babb
Per DRH19-00428, to comply with all conditions of approval for screening.
Plan Reviewer's activity  10/17/2019 DONE
DetailsBrian McGowan
Called Jason to let him know nothing was uploaded with the resubmittal. He will either email me the documents or have Brian Murphy fail it so I can send it back.
Plan Reviewer's activity  10/16/2019 DONE
DetailsBrian McGowan
Out Sourced Engineering not required as per Carl Madsen.
Fire Review not required as per Carl Madsen (remove from Tidemark and ePlan).
1st review completed  10/16/2019 FAIL
DetailsBrian McGowan
Routing - PLAN CHECK10/2/2019 10/16/2019 FAIL
DetailsBrian McGowan
Need Form # 310 for Special Inspections
Routing - PLUMBING10/2/2019 10/9/2019 PASS
DetailsDaryl Spivey
No plumbing review required
Routing PW Drainage10/2/2019 10/8/2019 FAIL
DetailsBrian Murphy
NEED STAMPED LETTER MORE GRADES ONSITE4
Routing - Erosion and Sediment10/2/2019 10/7/2019 PASS
DetailsMichael Zawacki
Work is in existing paved area.
Routing - Design Review10/2/2019 10/2/2019 FAIL
DetailsKayCee Babb
Design Review approval is required. DRH19-00428 is still under review.
Routing - MECHANICAL10/2/2019 10/2/2019 PASS
DetailsTroy James
Routing - Addressing10/2/2019 10/2/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS10/2/2019 10/2/2019 PASS
DetailsMorgan Webb
Intake Approval  9/27/2019 PASS
DetailsMichael Hanson
Application received  9/25/2019 DONE
Application submitted via PDS Online on Sep 25 2019 2:54PM
First Notice7/23/20207/23/2020   
DetailsTony Young