PubWorks Occupancy Approval | 7/28/2020 | 7/28/2020 | 7/28/2020 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 7/22/2020 | 7/23/2020 | 7/23/2020 | P | PASS |
Tony Young
|
|
|
Please call Jared 15 minutes prior at ###-#### Phone #: ###-#### Inspection requested via web by Jared Waggoner// ok per 450
|
DOC - Permit Finaled | 7/23/2020 | 7/23/2020 | 7/23/2020 | P | PASS |
Tony Young
|
|
|
|
BLD-Concrete | 11/7/2019 | 11/8/2019 | 11/8/2019 | P | PASS |
Tell Riley
|
|
|
East mechanical pad, west and north aprons Phone #: ###-#### Inspection requested via web by Jared Waggoner//ok per plans and engineering//maintain clearances on rebar in turned down footings//pending specials//
|
BLD-Foundation | 10/21/2019 | 10/22/2019 | 10/22/2019 | P | PASS |
Mike Jordan
|
|
|
Please call Jared at ###-#### 15 minutes ahead for access, east side Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
Permit Ready to Issue | | | 10/21/2019 | | DONE |
|
|
|
MET
NEED
GC FORM
REVISED VALUE
|
Issue PAID IN FULL permit | | | 10/21/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/21/2019 | | DONE |
|
|
|
|
Plan assigned to (BJM) | 9/27/2019 | 10/2/2019 | 10/18/2019 | | DONE |
Brian McGowan
|
|
|
10/22- 1st Review Complete- 502 FiberPipe Antenna on W. Emerald
|
Routing - PLANNING | 10/2/2019 | | 10/18/2019 | | PASS |
Celine Acord
|
|
|
No Current Planning Review
|
Routing - PLAN CHECK | 10/18/2019 | | 10/18/2019 | | PASS |
Brian McGowan
|
|
|
|
Routing PW Drainage | 10/18/2019 | | 10/18/2019 | | PASS |
Brian Murphy
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/18/2019 | | DONE |
Brian McGowan
|
|
|
|
Route to Impact Fee Review | 10/16/2019 | 10/19/2019 | 10/17/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - Design Review | 10/9/2019 | | 10/17/2019 | | PASS |
KayCee Babb
|
|
|
Per DRH19-00428, to comply with all conditions of approval for screening.
|
Plan Reviewer's activity | | | 10/17/2019 | | DONE |
Brian McGowan
|
|
|
Called Jason to let him know nothing was uploaded with the resubmittal. He will either email me the documents or have Brian Murphy fail it so I can send it back.
|
Plan Reviewer's activity | | | 10/16/2019 | | DONE |
Brian McGowan
|
|
|
Out Sourced Engineering not required as per Carl Madsen.
Fire Review not required as per Carl Madsen (remove from Tidemark and ePlan).
|
1st review completed | | | 10/16/2019 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 10/2/2019 | | 10/16/2019 | | FAIL |
Brian McGowan
|
|
|
Need Form # 310 for Special Inspections
|
Routing - PLUMBING | 10/2/2019 | | 10/9/2019 | | PASS |
Daryl Spivey
|
|
|
No plumbing review required
|
Routing PW Drainage | 10/2/2019 | | 10/8/2019 | | FAIL |
Brian Murphy
|
|
|
NEED STAMPED LETTER MORE GRADES ONSITE4
|
Routing - Erosion and Sediment | 10/2/2019 | | 10/7/2019 | | PASS |
Michael Zawacki
|
|
|
Work is in existing paved area.
|
Routing - Design Review | 10/2/2019 | | 10/2/2019 | | FAIL |
KayCee Babb
|
|
|
Design Review approval is required. DRH19-00428 is still under review.
|
Routing - MECHANICAL | 10/2/2019 | | 10/2/2019 | | PASS |
Troy James
|
|
|
|
Routing - Addressing | 10/2/2019 | | 10/2/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/2/2019 | | 10/2/2019 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 9/27/2019 | | PASS |
Michael Hanson
|
|
|
|
Application received | | | 9/25/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 25 2019 2:54PM
|
First Notice | 7/23/2020 | 7/23/2020 | | | |
Tony Young
|
|
|
|