Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD19-03880
StatusFinaled
Name AURIC SOLAR
Site Address 2104 N WESTGATE DR
Project Name177780 - Gibbons PV
Customer Number 
ePlanReviewYes
Description
Permit for 630sq' of roof-mounted, grid-tied Photo-voltaic panels with micro-inverters; 36 panels in 4 arrays panel. No work needed to the existing roof trusses per engineer’s roof evaluation. All racking, modules, and other listed equipment must be installed by a certified installer. All work per plans, engineering, manufacturer’s specs, & local code. Separate electrical permit required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final10/25/201910/25/201910/25/2019PPASS
DetailsTell Riley
Tell, if you would text homeowner @ ###-#### when your arrive on site, he will put the dogs away so that you can access backyard. Thanks. If any questions regarding project, pls contact Bryce (Foreman) @ ###-####. Thanks again, Rob Inspection requested via web by Rob Maes//installed per approved plans//
DOC - Permit Finaled10/25/201910/25/201910/25/2019PPASS
DetailsTell Riley
BLD-Final10/23/201910/24/201910/24/2019PNR
DetailsTell Riley
Pls contact Bryce (Foreman) @ ###-#### or Barry (Electrician) @ ###-#### one hr prior or if you have any questions. Thank you. Inspection requested via web by Rob Maes//need to see plans for setbacks on roof eaves and valleys//knocked on door no one home//
Permit Ready to Issue  10/8/2019 DONE
met
Issue PAID IN FULL permit  10/8/2019 DONE
Plan assigned to (JAB) Josh9/30/20199/30/201910/7/2019 PASS
DetailsJosh Bogle
10/04 PV, ePlan
Routing - PLAN CHECK9/30/2019 10/7/2019 PASS
DetailsJosh Bogle
1st review completed  10/7/2019 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  10/7/2019 DONE
DetailsJosh Bogle
ESC no - Energy no
Application received  9/30/2019 DONE
Application submitted via PDS Online on Sep 30 2019 12:54PM
Intake Approval  9/30/2019 PASS
Recd Pcfee & Taken To Pln CK  9/30/2019 DONE
no fees taken at intake
Routing - PLANNING9/30/2019 9/30/2019 PASS
DetailsSue Cummings