BLD-Conference | 11/8/2019 | 11/15/2019 | 11/15/2019 | A | CANC |
Tell Riley
|
|
|
no one onsite//no contact information//talke with concrete guys next door they were unsure of conference//
|
BLD-Foundation | 11/7/2019 | 11/8/2019 | 11/8/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 11/6/2019 | 11/7/2019 | 11/7/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
Issue PAID IN FULL permit | | | 10/30/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/30/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/30/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 10/29/2019 | | |
|
|
|
|
Plan assigned to (RDP) | 9/30/2019 | 9/30/2019 | 10/29/2019 | | DONE |
Rob Patrick
|
|
|
10/11 sfd L1 ePlan...10/29 Failed
|
Routing - PLAN CHECK | 9/30/2019 | | 10/29/2019 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 10/29/2019 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/29/2019 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 10/29/2019 | | DONE |
|
|
|
MET
|
Routing - MECHANICAL | 9/30/2019 | | 10/2/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 9/30/2019 | 10/3/2019 | 10/1/2019 | | PASS |
Shannon Cade
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 9/30/2019 | | 10/1/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 9/30/2019 | | 10/1/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 9/30/2019 | | 10/1/2019 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 9/30/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 30 2019 2:08PM
|
Plans ACCEPTED BY PLAN TECH | | | 9/30/2019 | | DONE |
|
|
|
|
Intake Approval | | | 9/30/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/30/2019 | | DONE |
|
|
|
|