BLD-Final | 6/23/2020 | 6/24/2020 | 6/24/2020 | A | PASS |
Tony Young
|
|
|
Garage code is 1977. Thanks! Phone #: ###-#### Inspection requested via web by Craig Hammett
|
DOC - Permit Finaled | 6/24/2020 | 6/24/2020 | 6/24/2020 | P | PASS |
Tony Young
|
|
|
|
BLD-Blower Door Test Results | 6/24/2020 | 6/24/2020 | 6/24/2020 | P | DONE |
Tony Young
|
|
|
Garage code is 1977. Thanks! Phone #: ###-#### Inspection requested via web by Craig Hammett// 3,79
|
BLD-Energy code compliance | 4/7/2020 | 4/8/2020 | 4/8/2020 | A | PART |
Tony Young
|
|
|
*screened* - Craig Phone #: ###-####// contractor to verify the access for attic blow in
|
BLD-Framing/Rough-in | 4/7/2020 | 4/8/2020 | 4/8/2020 | A | PASS |
Tony Young
|
|
|
*screened* - Craig Phone #: ###-####
|
BLD-Framing/Rough-in | 4/2/2020 | 4/3/2020 | 4/3/2020 | A | FAIL |
Tony Young
|
|
|
Craig Phone #: ###-####,, c/n posted,, straps, point loads,, overbuild bearing, double king studs, etc,, ok to insulate if needed
|
BLD-Wall Bracing | 3/13/2020 | 3/13/2020 | 3/13/2020 | P | PART |
Tell Riley
|
|
|
Shear // Craig Phone #: ###-####//ok when nailing added and blocking added//
|
BLD-Wall Bracing | 3/11/2020 | 3/12/2020 | 3/12/2020 | A | NR |
Mike Jordan
|
|
|
Greg Phone #: ###-####
|
BLD-Foundation | 2/2/2020 | 2/3/2020 | 2/3/2020 | A | DONE |
Tony Young
|
|
|
Foundation wall inspection. Thank you! Phone #: ###-#### Inspection requested via web by Craig Hammett// already poured
|
BLD-Footing | 1/29/2020 | 1/30/2020 | 1/30/2020 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
Issue PAID IN FULL permit | | | 1/16/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/16/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 11/15/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 11/15/2019 | | DONE |
|
|
|
|
Plan assigned to (D_S) Debbie | 11/13/2019 | 11/13/2019 | 11/14/2019 | | DONE |
Debbie Sanine
|
|
|
|
1st review completed | | | 11/14/2019 | | DONE |
Debbie Sanine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/14/2019 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 10/2/2019 | | 11/14/2019 | | PASS |
Debbie Sanine
|
|
|
Per review with JJN
|
Plan assigned to (RDP) | 10/2/2019 | 10/2/2019 | 11/13/2019 | | DEFR |
Rob Patrick
|
|
|
10/15 sfd L1 ePlan
|
Route to Impact Fee Review | 10/2/2019 | 10/5/2019 | 10/3/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 10/2/2019 | | 10/3/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 10/2/2019 | | 10/2/2019 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 10/2/2019 | | 10/2/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/2/2019 | | 10/2/2019 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/2/2019 | | DONE |
|
|
|
|
Intake Approval | | | 10/2/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/2/2019 | | DONE |
|
|
|
|
Application received | | | 9/30/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 30 2019 4:04PM
|