BLD-Foundation | 7/10/2020 | 7/13/2020 | 7/13/2020 | A | PASS |
Mike Jordan
|
|
|
screened - stem wall / Jerrid Phone #: ###-####. East stemwall.
|
BLD-Foundation | 7/8/2020 | 7/8/2020 | 7/8/2020 | P | PART |
Brandon Shaw
|
|
|
Pending Special Inspection...
|
Issue PAID IN FULL permit | | | 7/6/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/6/2020 | | DONE |
|
|
|
|
Telephone call | | | 6/12/2020 | | DONE |
|
|
|
emailed owner and cc'd contractor to let them know the fees have to be paid on the 03###-####2
|
Extend Review Timeline | | | 6/1/2020 | | DONE |
|
|
|
1st approved 180 day extension per joe. see documents
|
Telephone call | | | 5/28/2020 | | DONE |
|
|
|
sent jeff email about expired permits and may still request an extension
|
Permit Ready to Issue | | | 5/20/2020 | | DONE |
|
|
|
all met
NEED
ACHD inspections y/n
METNEED
ACHD: have receipt, just need doc that states whether inspections are required or not
MET Griffin Moeser
RP
GC
REVISED VALUE
met- Need GC
GC
REVISED VALUE
|
Routing PW Street Lights | 3/6/2020 | | 5/19/2020 | | PASS |
Tom Marshall
|
|
|
Per BLD19-03569
|
Routing - PLAN CHECK | 5/19/2020 | | 5/19/2020 | | PASS |
Michael Hanson
|
|
|
Per BLD19-03569
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/19/2020 | | DONE |
Michael Hanson
|
|
|
|
Plan assigned to (M_H) | 10/11/2019 | | 5/19/2020 | | DONE |
Michael Hanson
|
|
|
2nd review completed - 11/07 #502 L3 ePlan - Barber Valley Storage
|
Routing PW Drainage | 3/6/2020 | | 5/15/2020 | | PASS |
Brian Murphy
|
|
|
|
Routing - Design Review | 5/12/2020 | | 5/12/2020 | | PASS |
Katelyn Menuge
|
|
|
Redlined retaining wall plus fence cannot not exceed 6 feet in height- C3 & C4
|
Routing PW Sewer Design | 3/6/2020 | | 3/6/2020 | | PASS |
DeAnn Brown
|
|
|
|
Routing - Design Review | 3/6/2020 | | 3/6/2020 | | FAIL |
Katelyn Menuge
|
|
|
Need updates to site plan, photometric plan, easements for awnings, current planning requirements.
|
Routing - PLANNING | 3/3/2020 | | 3/3/2020 | | FAIL |
David Moser
|
|
|
1) Need to submit a copy of the 17 foot easment from harris Ranch for Future Road street improvements.
2) Need to submit a copy of the approval/comment letter from harris ranch Review Board on the final design.
3) Provide sidewalk easement for sidewalk along Wise Way on private property
4) Provide cross access easement with property to the north for the emergency gate
|
Route to Impact Fee Review | 11/7/2019 | 11/10/2019 | 11/12/2019 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 10/11/2019 | | 11/7/2019 | | FAIL |
Michael Hanson
|
|
|
See main permit BLD19-03569.
|
Routing Off Site - STRUCTURAL | 10/11/2019 | | 11/7/2019 | | FAIL |
Michael Hanson
|
|
|
See main permit BLD19-03569.
|
Routing PW Drainage | 10/14/2019 | | 11/7/2019 | | FAIL |
Brian Murphy
|
|
|
See main permit BLD19-03569.
|
Routing PW Street Lights | 10/14/2019 | | 11/7/2019 | | FAIL |
Tom Marshall
|
|
|
See main permit BLD19-03569.
|
Routing - Erosion and Sediment | 10/11/2019 | | 11/7/2019 | | PASS |
Michael Zawacki
|
|
|
See main permit BLD19-03569.
|
Routing PW Solid Waste | 10/14/2019 | | 11/7/2019 | | PASS |
Evan Carpenter
|
|
|
See main permit BLD19-03569.
|
1st review completed | | | 11/7/2019 | | FAIL |
Michael Hanson
|
|
|
See main permit BLD19-03569.
|
Routing - FIRE | 10/11/2019 | 10/11/2019 | 11/6/2019 | | FAIL |
Mark Stumbaugh
|
|
|
See review comments for BLD19-03569
11/14 (502) Barber Valley Storage, ePlan
|
Routing PW Sewer Design | 10/14/2019 | | 10/16/2019 | | FAIL |
DeAnn Brown
|
|
|
Sheet labeled and submitted as DWG_C3_BVSS_GD&U is actually sheet C2 the horizontal control plan. Please resubmit and include sheet C3 (grading, drainage, and utilities).
|
Routing - Design Review | 10/11/2019 | | 10/16/2019 | | FAIL |
Katelyn Menuge
|
|
|
Upload Idaho Power approval, photometric plan, lighting plan for inside the storefront corridors and a plan for what will be placed in these areas, HRRB comments on final design and any written waivers by the HRRB per DR conditions. Awnings extending over property lines shall be placed within easements. See current planning comments for additional required documents.
|
Routing - Addressing | 10/11/2019 | | 10/14/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/11/2019 | | 10/14/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 10/11/2019 | | 10/11/2019 | | FAIL |
David Moser
|
|
|
* Need to submit a Staff Level Floodplain Review since the site is located in the 100 year floodplain as per the new FEMA maps.
* Need to submit a copy of the 17 foot easment from harris Ranch for Future Road street improvements. Also need approval/comment letter from harris ranch Review Board on the final design.
*provide sidewalk easement for sidewalk along Wise Way on private property
* Provide cross access easement with property to the north for the emergency gate* Need to submit a Staff Level Floodplain Review since the site is located in the 100 year floodplain as per the new FEMA maps.
* Need to submit a copy of the 17 foot easment from harris Ranch for Future Road street improvements. Also need approval/comment letter from harris ranch Review Board on the final design.
*Provide sidewalk easement for sidewalk along Wise Way on private property
* Provide cross access easement with property to the north for the emergency gate
|
Intake Approval | | | 10/4/2019 | | PASS |
|
|
|
|
Application received | | 10/1/2019 | | | |
|
|
|
|