BLD-Concrete | 2/6/2020 | 2/10/2020 | 2/10/2020 | P | CANC |
Dave Hannah
|
|
|
LVL 2 slab on deck pour - area "B" Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign offs
|
BLD-Concrete | 2/7/2020 | 2/10/2020 | 2/10/2020 | A | PEND |
Dave Hannah
|
|
|
Columns to be poured @ South half of pour "A". Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign offs
|
BLD-Footing | 2/7/2020 | 2/10/2020 | 2/10/2020 | A | PEND |
Dave Hannah
|
|
|
Apartment footings @ SW quadrant. Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign offs
|
BLD-Concrete | 2/6/2020 | 2/7/2020 | 2/10/2020 | A | PEND |
Dave Hannah
|
|
|
Column pour @ lvl 2 deck - area "A" - and shear wall @ lvl 2 deck, West shear wall. Phone #: ###-#### Inspection requested via web by Garrett Camp ok after spec inspection sign offs
|
BLD-Concrete | 1/30/2020 | 1/30/2020 | 2/3/2020 | P | DONE |
Dave Hannah
|
|
|
Inspection of slab on deck pour with PT Phone #: ###-#### Inspection requested via web by Garrett Camp
|
BLD-Concrete | 1/8/2020 | 1/8/2020 | 1/13/2020 | P | PASS |
Dave Hannah
|
|
|
Slab on grade reinforcement Thanks Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Concrete | 1/3/2020 | 1/3/2020 | 1/6/2020 | P | PEND |
Dave Hannah
|
|
|
SOG - ramp to mini ramp. Grids P4 - P9 Phone #: ###-#### Inspection requested via web by Garrett Camp
|
BLD-Concrete | 12/31/2019 | 1/2/2020 | 1/2/2020 | A | PASS |
Dave Hannah
|
|
|
Need inspection on shear wall from PC - PD along P1. Columns at grid intersections PD.8/P1; PE/P1; and PB.6/P1. Foot between P3.2 - P4 along PA. Phone #: ###-#### Inspection requested via web by Garrett Camp
|
BLD-Concrete | 12/30/2019 | 12/31/2019 | 12/31/2019 | A | PASS |
Dave Hannah
|
|
|
Columns @ NW and SW corners of level 1. Total of 10. Phone #: ###-#### Inspection requested via web by Garrett Camp
|
BLD-Foundation | 12/23/2019 | 12/23/2019 | 12/24/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Foundation | 12/19/2019 | 12/20/2019 | 12/23/2019 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Foundation | 12/11/2019 | 12/11/2019 | 12/11/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Foundation | 12/6/2019 | 12/6/2019 | 12/6/2019 | P | PART |
Brandon Shaw
|
|
|
Pending Special Inspection...
|
BLD-Foundation | 12/3/2019 | 12/3/2019 | 12/3/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Footing | 11/25/2019 | 11/25/2019 | 11/26/2019 | P | PASS |
Dave Hannah
|
|
|
Footings, Foundation. Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Footing | 11/21/2019 | 11/21/2019 | 11/22/2019 | P | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Jim Williams
|
BLD-Footing | 11/4/2019 | 11/5/2019 | 11/5/2019 | A | DONE |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by Jim Williams
|
CHANGE STATUS TO (ISS) | | | 11/4/2019 | | DONE |
|
|
|
plan mod
|
Inspection Record Card- Bld | | | 11/4/2019 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 10/10/2019 | 10/10/2019 | 10/31/2019 | | PASS |
Carl Westfall
|
|
|
(1st done) 07/05/19 Park place foundation
|
Routing Off Site - STRUCTURAL | 10/30/2019 | | 10/31/2019 | | PASS |
Carl Westfall
|
|
|
Howie Henrikson (Jacobs) Jared Bauder (CH2M Hill)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/31/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/31/2019 | | DONE |
|
|
|
DO NOT ISS plan mod approved
|
Routing - PLAN CHECK | 10/29/2019 | | 10/30/2019 | | PASS |
Carl Westfall
|
|
|
Pending approval by structural
|
Plan resubmittals received | | | 10/29/2019 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 10/22/2019 | | 10/23/2019 | | FAIL |
Carl Westfall
|
|
|
Jared Bauder (CH2M Hill)
|
Plan resubmittals requested | | | 10/23/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/21/2019 | | 10/22/2019 | | PASS |
Carl Westfall
|
|
|
Pending approval by structural
|
Plan resubmittals received | | | 10/21/2019 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/17/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/11/2019 | | 10/17/2019 | | FAIL |
Carl Westfall
|
|
|
Structural has not approved
|
Routing Off Site - STRUCTURAL | 10/11/2019 | | 10/16/2019 | | FAIL |
Carl Westfall
|
|
|
Jared Bauder (CH2M Hill)
|
Route to Impact Fee Review | 10/10/2019 | 10/13/2019 | 10/11/2019 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Plan Modification Accepted | | | 10/10/2019 | | DONE |
|
|
|
plan mod accepted by Angie B. -changes doundation design with geo piers-sheets gt1.0,gt1.1, gt1.2, gt1.3, gt1.4. gt1.5, gt2.0, ram aggregate piers, strc calcs, foundation design, signed-assinged to Carl W- no extra valuation to be added to this foundation permit
|
Issue PAID IN FULL permit | | | 10/9/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/9/2019 | | DONE |
|
|
|
|
Plan assigned to (CJW) | 10/1/2019 | 10/1/2019 | 10/8/2019 | | PASS |
Carl Westfall
|
|
|
Park place footings and foundations
|
Routing - PLAN CHECK | 10/1/2019 | | 10/8/2019 | | PASS |
Carl Westfall
|
|
|
Footings and foundations only
|
1st review completed | | | 10/8/2019 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/8/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/8/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/8/2019 | | DONE |
|
|
|
Already in the documents
NEED
GC
Revised Certificate of Value
|
Routing Off Site - STRUCTURAL | 10/4/2019 | | 10/4/2019 | | PASS |
Angela Brosious
|
|
|
Structural reviewed and approved under BLD19-01478.
|
Routing - PLANNING | 10/1/2019 | | 10/1/2019 | | PASS |
David Moser
|
|
|
|
Intake Approval | | | 10/1/2019 | | PASS |
|
|
|
|
Application received | | 10/1/2019 | | | |
|
|
|
|