BLD-Final | 4/16/2020 | 4/17/2020 | 4/17/2020 | A | PASS |
Mike Jordan
|
|
|
shop // kurt Phone #: ###-####
|
DOC - Permit Finaled | 4/17/2020 | 4/17/2020 | 4/17/2020 | P | PASS |
Mike Jordan
|
|
|
Noted that the home owner will need to apply for a seperate building permit to construct the restroom when ready.
|
BLD-Conference | 2/7/2020 | 2/7/2020 | 2/7/2020 | P | DONE |
Mike Jordan
|
|
|
Spoke with home owner, he will submit plans mod for half bath.
|
DOC - Permit Finaled | 2/7/2020 | 2/7/2020 | 2/7/2020 | P | PASS |
Mike Jordan
|
|
|
(This activity was added in error so we have changed the case status back to Issued.)
|
BLD-Conference | 2/6/2020 | 2/7/2020 | 2/7/2020 | A | DONE |
Mike Jordan
|
|
|
Inpsection set up by permit tech. Tisha talked to Buss Mechanical for plumbing permit pulled for bathroom in shop PLM20-00285. No plumbing or bathroom is approved. Please verify if full or half bathroom is being built plan modification is required.
|
BLD-Framing/Rough-in | 1/21/2020 | 1/21/2020 | 1/21/2020 | P | PASS |
Mike Jordan
|
|
|
Curt Phone #: ###-####. Lean to ok.
|
BLD-Framing/Rough-in | 1/8/2020 | 1/9/2020 | 1/9/2020 | A | PART |
Mike Jordan
|
|
|
CURT Phone #: ###-####. Main structure ok. lean to portion not completed.
|
BLD-Footing | 12/17/2019 | 12/18/2019 | 12/18/2019 | A | PASS |
Mike Jordan
|
|
|
Curt Phone #: ###-####
|
Routing Walk-In (Zoning) | 10/1/2019 | 10/1/2019 | 10/1/2019 | P | PASS |
Ethan Mansfield
|
|
|
CZC19-00211 approved by EOM
|
Routing Walk-In (BLD) | 10/1/2019 | 10/1/2019 | 10/1/2019 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 10/1/2019 | | 10/1/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 10/1/2019 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 10/1/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 10/1/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 10/1/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/1/2019 | | DONE |
|
|
|
|
Application received | | 10/1/2019 | | | |
|
|
|
|