BLD-Final | 4/30/2020 | 5/1/2020 | 5/1/2020 | A | PASS |
Tony Young
|
|
|
Final can be done at anytime. Thanks! Phone #: ###-#### Inspection requested via web by rich prasch
|
DOC - Permit Finaled | 5/1/2020 | 5/1/2020 | 5/1/2020 | P | PASS |
Tony Young
|
|
|
|
BLD-Footing | 11/21/2019 | 11/22/2019 | 11/22/2019 | A | PASS |
Tony Young
|
|
|
Installer ~ Jimmy Phone #: ###-#### Inspection requested via web by rich prasch
|
BLD-Footing | 11/19/2019 | 11/20/2019 | 11/20/2019 | A | FAIL |
Jim Storey
|
|
|
Footing inspection can be done at anytime tomorrow. Subgrade was completed and accepted by Melissa. Jimmy will be doing the installation and his cell number is ###-####. Thanks! Phone #: ###-#### Inspection requested via web by rich prasch/// need compaction report for fill.
|
PubWorks Subgrade Approval | 11/19/2019 | 11/19/2019 | 11/19/2019 | | DONE |
Melissa Jannusch
|
|
|
PATIO
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Plan assigned to (JAB) Josh | 10/3/2019 | 10/3/2019 | 10/10/2019 | | PASS |
Josh Bogle
|
|
|
10/09 pergola, ePlan - 1st done
|
Routing - Erosion and Sediment | 10/10/2019 | | 10/10/2019 | | PASS |
Michael Zawacki
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/10/2019 | | DONE |
Josh Bogle
|
|
|
ESc no - Energy no
|
Permit Ready to Issue | | | 10/10/2019 | | DONE |
|
|
|
met
|
Issue PAID IN FULL permit | | | 10/10/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/10/2019 | | DONE |
|
|
|
|
1st review completed | | | 10/9/2019 | | FAIL |
Josh Bogle
|
|
|
|
Plan Reviewer's activity | | | 10/9/2019 | | DONE |
Josh Bogle
|
|
|
returned to ESC for re-review
|
Routing - PLAN CHECK | 10/3/2019 | | 10/9/2019 | | PASS |
Josh Bogle
|
|
|
|
Routing - Erosion and Sediment | 10/3/2019 | | 10/7/2019 | | FAIL |
Michael Zawacki
|
|
|
Talked with Josh, only footings, was some confusion on my end with scope of work.
|
Routing PW Grading-Hillside | 10/4/2019 | | 10/4/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
|
Routing - PUBLIC WORKS | 10/3/2019 | | 10/4/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 10/3/2019 | | 10/3/2019 | | PASS |
Sue Cummings
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/3/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/3/2019 | | DONE |
|
|
|
no intake fee taken, 406
|
Intake Approval | | | 10/3/2019 | | PASS |
|
|
|
|
Application received | | | 10/2/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 2 2019 12:50PM
|