Permit Information
Permit NumberBLD19-03957
StatusIssued
Name STRANG DAVIN
Site Address 1202 W HOWARD ST
Project NameStrang ADU
Customer NumberCAA18-00218
ePlanReviewYes
Description
MODIFICATION TO SIMULATED PERFORMANCE ALTERNATIVE FOR ENERGY CODE COMPLIANCE, PROOF OF ACHIEVING A BLOWER DOOR TEST OF <1@ach50 REQUIRED BEFORE APPROVAL TO COVER. 4/23/20 **jab** Permit to convert an existing 21'x28'6" two story outbuilding to a 598sq' ADU over a 598sq' shop with a half bath. Heating/cooling via mini-split - Energy Code via alt-Prescriptive. All work per plans, notations, attachments, local codes & ordinances. Separate electrical, plumbing & mechanical permits required. **JAB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Energy code compliance5/20/20205/21/20205/21/2020APASS
DetailsJim Storey
screened // Davin Phone #: ###-####
BLD-Framing/Rough-in4/27/20204/28/20204/28/2020APASS
DetailsJim Storey
Davin **cleared** Phone #: ###-####
CHANGE STATUS TO (ISS)  4/27/2020 DONE
Plan assigned to (JAB) Josh4/22/20204/22/20204/23/2020 PASS
DetailsJosh Bogle
Plan Modification Accepted  4/23/2020 DONE
Floor plan and ES changes proposed.

Originally submitted as paper, please stamp all ePlanReview files when approved
Routing - PLAN CHECK4/23/2020 4/23/2020 PASS
DetailsJosh Bogle
1hr Plan Review
Permit Ready to Issue  4/23/2020 DONE
**DO NOT REISSUE - PLAN MOD**
BLD-Framing/Rough-in2/24/20202/25/20202/25/2020APART
DetailsJim Storey
Davin Phone #: ###-#### hard wire sd/ support floor joist at stair at access opening/ insulate attic spaces at vault. ok to insulate.
Routing Walk-In (BLD)1/28/20201/28/20201/28/2020PPASS
DetailsJosh Bogle
discussed possible engineering changes
BLD-Footing12/3/201912/3/201912/3/2019PPASS
DetailsJim Storey
Annie Phone #: ###-####
Route to Impact Fee Review11/14/201911/17/201911/15/2019 PASS
DetailsTravis P Black
Initial residential review of new SFD permits requested for now.
Route to Impact Fee Review11/14/201911/19/201911/14/2019 PASS
DetailsTravis P Black
Issue PAID IN FULL permit  11/14/2019 DONE
Routing Walk-In (BLD)11/13/201911/13/201911/13/2019PDONE
DetailsJosh Bogle
Plan assigned to (JAB) Josh10/22/201910/22/201911/13/2019 PASS
DetailsJosh Bogle
10/28 ADU, paper - 1st done
Routing - PLAN CHECK11/13/2019 11/13/2019 PASS
DetailsJosh Bogle
Inspection Record Card- Bld  11/13/2019 DONE
DetailsJosh Bogle
Case Summary (BLD)  11/13/2019 DONE
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  11/13/2019 DONE
DetailsJosh Bogle
ESC no - Energy yes
Permit Ready to Issue  11/13/2019 DONE
Plan resubmittals received  11/12/2019 DONE
2 large sets of plans- Floor plans and Structural plans- Taken to Josh
Routing - MECHANICAL10/23/2019 10/25/2019 PASS
DetailsChad Schwendiman
Ductless System
Routing - Addressing10/3/2019 10/23/2019 PASS
DetailsDoug Chausow
ADU address: 1202 W Howard St
Routing - PUBLIC WORKS10/3/2019 10/23/2019 PASS
DetailsMorgan Webb
Routing Walk-In (BLD)10/22/201910/22/201910/22/2019APASS
DetailsJosh Bogle
took in for level two review
Routing Walk-In (BLD)10/3/201910/3/201910/3/2019AFAIL
DetailsJosh Bogle
documentation problems - applicant will resubmit after redrawing
1st review completed  10/3/2019 FAIL
DetailsJosh Bogle
Plans ACCEPTED BY PLAN TECH  10/3/2019 DONE
Intake Approval  10/3/2019 PASS
Recd Pcfee & Taken To Pln CK  10/3/2019 DONE
Routing - PLAN CHECK  10/3/2019 FAIL
DetailsJosh Bogle
Routing - PLANNING10/3/2019 10/3/2019 PASS
DetailsSue Cummings
per CAA19-00218
Application received 10/3/2019