BLD-Ceiling Grid Inspection | 8/11/2020 | 8/12/2020 | 8/12/2020 | A | PASS |
Mike Jordan
|
|
|
Jason */Screened*/ Phone #: ###-####. Phase 2.
|
BLD-Framing/Rough-in | 6/30/2020 | 7/1/2020 | 7/1/2020 | A | PASS |
Jim Storey
|
|
|
screened // Cameron Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 6/30/2020 | | DONE |
|
|
|
plan mod
|
Permit Ready to Issue | | | 6/22/2020 | | DONE |
|
|
|
PLAN MOD Met
|
Plan Modification Accepted | | | 6/5/2020 | | DONE |
|
|
|
deferred submittal
|
Plan assigned to (M_H) | 6/5/2020 | | 6/5/2020 | | DONE |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 6/5/2020 | | 6/5/2020 | | PASS |
Michael Hanson
|
|
|
VERIFIED SKYLIGHTS MET THE REQUIRED U-VALUE AND SHGC REQUIREMENTS PER 2015 IECC TABLE C402.4.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/5/2020 | | DONE |
Michael Hanson
|
|
|
|
FIRE-Final Inspection | 5/19/2020 | 5/19/2020 | 5/19/2020 | P | PART |
Troy Cobbley
|
|
|
Life safety passed for phase 2, west side of the building.
Jason *screened* Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 5/14/2020 | 5/14/2020 | 5/14/2020 | P | PASS |
Mike Jordan
|
|
|
Screened- Jason Phone #: ###-####. Phase 1 grid ok.
|
Routing - MECHANICAL | 5/11/2020 | | 5/11/2020 | | PASS |
Chad Schwendiman
|
|
|
|
Telephone call | | | 5/8/2020 | | DONE |
|
|
|
Sent email to Willis, permit is ready pending fees paid
|
CHANGE STATUS TO (ISS) | | | 5/8/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/7/2020 | | DONE |
|
|
|
MET - updated 306 for plan mod
|
Plan assigned to (M_H) | 4/22/2020 | | 5/5/2020 | | DONE |
Michael Hanson
|
|
|
1st review plan mod complete 05/08 Plan Mod - AAA Boise
|
Routing Off Site - STRUCTURAL | 4/29/2020 | | 5/5/2020 | | PASS |
Michael Hanson
|
|
|
D. Haugland @ AHJ engineering
|
Routing - PLAN CHECK | 4/22/2020 | | 4/22/2020 | | PASS |
Michael Hanson
|
|
|
Plan Mod #1
|
Routing Off Site - STRUCTURAL | 4/8/2020 | | 4/21/2020 | | PASS |
Michael Hanson
|
|
|
Per D. Haugland @ AHJ engineering.
|
BLD-Ceiling Grid Inspection | 4/20/2020 | 4/20/2020 | 4/20/2020 | P | NR |
Mike Jordan
|
|
|
SCREENED // JASON Phone #: ###-####. Mech rough in inspection has failed.
|
BLD-Ceiling Grid Inspection | 4/16/2020 | 4/16/2020 | 4/16/2020 | P | NR |
Mike Jordan
|
|
|
Jason - no one is at the job site willing to do virtual Phone #: ###-####. Needs mech rough in inspection first.
|
Routing - Design Review | 4/8/2020 | | 4/8/2020 | | PASS |
KayCee Babb
|
|
|
Approval to replace fiberglass roofing with metal panel roofing and skylights. No other alterations are approved through this plan mod.
|
BLD-Ceiling Grid Inspection | 4/7/2020 | 4/7/2020 | 4/7/2020 | P | NR |
Mike Jordan
|
|
|
screened willing to do video/phot // Jason Phone #: ###-####
|
Plan Modification Accepted | | | 4/1/2020 | | DONE |
|
|
|
**NEED 306** Willis DeWitt submitted a plan mod
|
Plan assigned to (M_H) | 4/1/2020 | | 4/1/2020 | | DONE |
Gemma Flores
|
|
|
plan mod: Replacing the permitted translucent fiberglass sandwich panel roof structure in the lobby with a metal deck and skylight roof assembly. Sheets to be uploaded: G0.01, S0.01, S2.01, A1.03, A2.10, A3.01, A5.01, A5.07, A5.08, A6.10, A6.11, A6.12, and 6.13
|
BLD-Framing/Rough-in | 3/9/2020 | 3/9/2020 | 3/9/2020 | P | PART |
Mike Jordan
|
|
|
Jason Phone #: ###-####. Interior steel stud framed walls and soffits for phase 1 construction. Pending electrical rough in inspection.
|
BLD-Framing/Rough-in | 3/5/2020 | 3/6/2020 | 3/6/2020 | A | PART |
Mike Jordan
|
|
|
Jason Phone #: ###-####. Interior steel stud framed walls and soffits in open office area phase 1. Needs electrical rough in inspection. Also needs to add missing screws in framing.
|
Meeting | | | 1/7/2020 | | DONE |
|
|
|
Emailed a reminder to the GC to please print and sign their name on the building permit and send it back.
|
Issue PAID IN FULL permit | | | 1/3/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/3/2020 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 12/30/2019 | | 12/30/2019 | | PASS |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 12/30/2019 | | DONE |
|
|
|
all met: willis@woofterarchitecture.com
Need
GC Form
Revised Cert of Value
|
Plan assigned to (M_H) | 11/19/2019 | | 12/30/2019 | | DONE |
Michael Hanson
|
|
|
2nd review completed - 12/13 #520 L3 ePlan - AAA Boise
|
Routing - PLAN CHECK | 12/23/2019 | | 12/23/2019 | | FAIL |
Michael Hanson
|
|
|
See building plan review report for corrections required.
|
Route to Impact Fee Review | 12/12/2019 | 12/15/2019 | 12/12/2019 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 11/19/2019 | 11/19/2019 | 12/12/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 12/12/2019 | | DONE |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 11/19/2019 | | 12/11/2019 | | FAIL |
Michael Hanson
|
|
|
See building plan review report for corrections required.
|
Routing - Addressing | 11/19/2019 | | 11/20/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/19/2019 | | 11/19/2019 | | PASS |
Morgan Webb
|
|
|
WEST BOISE SEWER DISTRICT
|
Routing - Design Review | 11/19/2019 | | 11/19/2019 | | PASS |
KayCee Babb
|
|
|
Per CZC19-00262
|
Intake Approval | | | 11/18/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 11/5/2019 | | FAIL |
Brian McGowan
|
|
|
Many of the uploaded drawings do not provide the required space in the lower right hand corner for the City Approval Stamp as required.
Please resubmit sheets as needed to provide the required space.
|
Intake Approval | | | 10/4/2019 | | FAIL |
Brian McGowan
|
|
|
Please address or provide the following for your Prescreen to be approved:
1. Plan Sheets must be uploaded separately.
2. Mechanical, Electrical and Plumbing cannot be deferred without written approval from the Chief Inspector of that division.
3. Sheet A1.03 Keynote #3 mentions the manufacturer to verify and engineer structural framing sizes. All structural changes must be submitted with the drawings. Please include details, calculations and designs that are stamped and signed by a licensed Idaho Engineer.
|
Application received | | | 10/3/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 3 2019 6:37PM
|