BLD-Aging Inspection | 4/28/2020 | 4/28/2020 | 4/28/2020 | | PASS |
Tell Riley
|
|
|
|
BLD-Foundation | 12/13/2019 | 12/16/2019 | 12/16/2019 | A | PART |
Tell Riley
|
|
|
Dane Phone #: ###-####//blankets onsite--covered all weekend//workers are heating steel// forms are warm//will cover after pour//
|
BLD-Foundation | 12/12/2019 | 12/13/2019 | 12/13/2019 | P | CANC |
Tell Riley
|
|
|
Dane - foundation wall Phone #: ###-####
|
BLD-Footing | 12/10/2019 | 12/11/2019 | 12/11/2019 | A | PASS |
Tell Riley
|
|
|
10am pouring - Dane Phone #: ###-####//temps ok//bar installed per plans//setbacks set by surveyor//
|
BLD-Footing | 12/9/2019 | 12/10/2019 | 12/10/2019 | A | FAIL |
Tell Riley
|
|
|
Dane Phone #: ###-####//no blankets onsite,ground temps below freezing//
|
Issue PAID IN FULL permit | | | 12/3/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/3/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 11/20/2019 | | |
|
|
|
|
Plan assigned to (JG) | 10/15/2019 | 10/15/2019 | 11/20/2019 | | PASS |
Javier Guzman
|
|
|
2nd rev comp, 11/18 Northview Apartment (Foundation & Utilities)
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/20/2019 | | DONE |
|
|
|
ALL MET
NEED
RP
Met
GC (updated version)
Revised Certificate of Value
|
Routing Off Site - STRUCTURAL | 11/14/2019 | | 11/20/2019 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by AHJ Engineers
|
Routing - PLANNING | 11/14/2019 | | 11/19/2019 | | PASS |
Celine Acord
|
|
|
Per Celine Accord ok to sign off in Tidemark (email dated 11/19/19)
|
Routing - FIRE | 11/14/2019 | 11/14/2019 | 11/15/2019 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Route to Impact Fee Review | 11/13/2019 | 11/16/2019 | 11/14/2019 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing PW Sewer Design | 11/14/2019 | | 11/14/2019 | | PASS |
DeAnn Brown
|
|
|
|
Routing - PLAN CHECK | 11/14/2019 | | 11/14/2019 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 11/13/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 10/15/2019 | | 11/13/2019 | | PASS |
Javier Guzman
|
|
|
Foundation Only
|
Routing Off Site - STRUCTURAL | 10/15/2019 | | 11/13/2019 | | FAIL |
Javier Guzman
|
|
|
failed in ePlan by AHJ Engineers
|
Routing - FIRE | 10/15/2019 | 10/15/2019 | 10/28/2019 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing - MECHANICAL | 10/15/2019 | | 10/22/2019 | | PASS |
Troy James
|
|
|
Approved for foundation only.
|
Routing PW Grading-Hillside | 10/15/2019 | | 10/22/2019 | | CANC |
Melissa Jannusch
|
|
|
No hillside review needed
|
Routing - Design Review | 10/15/2019 | | 10/18/2019 | | PASS |
Katelyn Menuge
|
|
|
Foundation and Utilities okay. Redlined parking striping and requirement for parking blocks or 6 inch curbing.
|
Routing - PLANNING | 10/15/2019 | | 10/18/2019 | | FAIL |
Celine Acord
|
|
|
24 bike parking spaces are required, 25% need to be covered per Code. Striping of parking spaces needs to be compliant with Code. XREF PUD18-00022
|
Routing - PLUMBING | 10/15/2019 | | 10/16/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing PW Sewer Design | 10/15/2019 | | 10/16/2019 | | FAIL |
DeAnn Brown
|
|
|
Update sheet C5.1 to reflect configuration of new sewer service taps that were installed on 8-8-19 and the original sewer service tap that was plugged on 8-8-19. Add note to locate existing services and connect. See changemarks.
|
Routing PW Environmental | 10/15/2019 | | 10/16/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Solid Waste | 10/15/2019 | | 10/15/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Drainage | 10/15/2019 | | 10/15/2019 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Street Lights | 10/15/2019 | | 10/15/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing - Addressing | 10/15/2019 | | 10/15/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/15/2019 | | 10/15/2019 | | PASS |
Morgan Webb
|
|
|
NO ASSESSMENT DUE. CONNECTION FEES WILL BE DUE UPON BUILDOUT PERMIT.
|
Routing - Erosion and Sediment | 10/15/2019 | | 10/15/2019 | | PASS |
Michael Zawacki
|
|
|
Please refer to ESC19-00034 for main site esc permit
|
Intake Approval | | | 10/14/2019 | | PASS |
|
|
|
|
Intake Approval | | | 10/9/2019 | | FAIL |
Javier Guzman
|
|
|
For prescreen review provide and upload the following:
• Uploaded engineering calculations are required to be stamped, signed and dated by an Idaho licensed engineer
• Per checklist the uploaded Verification of Legal Lot or Parcel Form needs to be Signed and approved by PDS Planning Staff.
• Per checklist Include on site plan A1.1 Site Plan Clearly marked “Fire Department Access Roadways”
• Per checklist clearly mark on site plan A1.1 Site Plan location of Fire Hydrants
• Per ePlan submittal standards the reserve the bottom right corner on the drawing plans for the City electronic stamps. Leave a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block on plan sheet L1, A101, A103, A205, A401, A404, A405, S0.00. see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
|
Application received | | | 10/8/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 8 2019 9:35AM
|