Permanent Occupancy | | | 5/4/2020 | | DONE |
|
|
|
|
BLD-Final | 4/30/2020 | 5/1/2020 | 5/1/2020 | P | PASS |
Jim Storey
|
|
|
Screened-Paul Phone #: ###-####
|
BLD-Final | 4/20/2020 | 4/22/2020 | 4/22/2020 | P | NR |
Jim Storey
|
|
|
Paul Phone #: ###-#### need ele
|
FIRE-Final Inspection | 4/20/2020 | 4/22/2020 | 4/22/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Paul Phone #: ###-####
|
Plan Reviewer's activity | | | 4/22/2020 | | DONE |
Michael Hanson
|
|
|
Changed the public works inspection from a "Y" to "N" per the approval comment from Morgan Webb "no new plumbing".
|
FIRE-Final Inspection | 4/13/2020 | 4/14/2020 | 4/14/2020 | P | FAIL |
Jim Page
|
|
|
Ansul systems that was protecting the de-commissioned paint booth will need to be removed, a demo FIR permit is required for removal of the fire system. Provide single action door hardware on main entry as discussed, door hardware in place would not operate when locked. Provide fire extinguishers with current inspection tags and place as discussed. Provide maximum occupancy placard as shown on city approved drawings. Provide code compliant addressing on the fire access side of the building as discussed.
*screened* Check Ansul system, please call ahead for access - Paul Phone #: ###-####
|
BLD-Framing/Rough-in | 3/25/2020 | 3/27/2020 | 3/27/2020 | P | PASS |
Jim Storey
|
|
|
Paul Phone #: ###-#### fire wall complet
|
BLD-Framing/Rough-in | 3/23/2020 | 3/24/2020 | 3/24/2020 | P | PASS |
Jim Storey
|
|
|
Paul Phone #: ###-#### interior gyp ok parapet ok .
|
BLD-Conference | 3/3/2020 | 3/3/2020 | 3/3/2020 | P | DONE |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 2/19/2020 | 2/21/2020 | 2/21/2020 | A | NR |
Jim Storey
|
|
|
Paul Phone #: ###-####
|
Plan Reviewer's activity | | | 1/27/2020 | | DONE |
Michael Hanson
|
|
|
Contacted Christy Little at ACHD and verified no impact fees would be required due to the CZC, age, and continued use of the building.
|
Issue PAID IN FULL permit | | | 1/27/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 1/27/2020 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/7/2020 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 1/7/2020 | | DONE |
|
|
|
Need
ACHD
GC Form
Revised Cert of Value
|
Routing - FIRE | 12/19/2019 | | 1/6/2020 | | PASS |
Mark Stumbaugh
|
|
|
Resubmittal Capital City Auto
|
Routing - PLAN CHECK | 12/23/2019 | | 12/23/2019 | | PASS |
Michael Hanson
|
|
|
|
Plan assigned to (M_H) | 11/6/2019 | | 12/23/2019 | | DONE |
Michael Hanson
|
|
|
1st review completed - 11/28 #520 L3 ePlan - Capital city auto
|
Routing - Design Review | 12/20/2019 | | 12/20/2019 | | PASS |
KayCee Babb
|
|
|
Per CZC19-00271, as revised 11-26-19 and 12-20-19.
|
Plan Reviewer's activity | | | 12/19/2019 | | DONE |
Michael Hanson
|
|
|
Provided occupancy reduction request template on 12/12/2019
|
Routing - MECHANICAL | 12/12/2019 | | 12/12/2019 | | PASS |
Troy James
|
|
|
Letter provided by owner stating that the existing spray booth will not be used. Therefore no mechanical work is being performed under this permit.
|
Route to Impact Fee Review | 12/5/2019 | 12/8/2019 | 12/6/2019 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - MECHANICAL | 12/2/2019 | | 12/5/2019 | | FAIL |
Troy James
|
|
|
Emailed corrections to applicant
|
1st review completed | | | 12/5/2019 | | DONE |
Michael Hanson
|
|
|
|
Routing - FIRE | 11/6/2019 | 11/6/2019 | 12/2/2019 | | FAIL |
Mark Stumbaugh
|
|
|
11/28 Capital City Auto L3
|
Routing - PLAN CHECK | 11/6/2019 | | 12/2/2019 | | FAIL |
Michael Hanson
|
|
|
See changemarks in ePlan for corrections required.
|
Routing - PLANNING | 11/6/2019 | | 11/14/2019 | | PASS |
David Moser
|
|
|
see CZC19-00271
|
Routing PW Environmental | 11/12/2019 | | 11/12/2019 | | PASS |
Rick Christenson
|
|
|
|
Routing - PUBLIC WORKS | 11/6/2019 | | 11/12/2019 | | PASS |
Morgan Webb
|
|
|
NO NEW PLUMBING
|
Routing - Addressing | 11/6/2019 | | 11/7/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - Design Review | 11/6/2019 | | 11/7/2019 | | FAIL |
KayCee Babb
|
|
|
Comply with all conditions of approval of CZC19-00271.
|
Plan Reviewer's activity | | | 11/1/2019 | | DONE |
Javier Guzman
|
|
|
Carl M was ok with this being a 520
|
Intake Approval | | | 11/1/2019 | | PASS |
|
|
|
|
Intake Approval | | | 10/10/2019 | | FAIL |
Javier Guzman
|
|
|
For prescreen review provide and upload the following:
• Without having any permits or past C of O for the building addition will require a 502 application as if it were a new building. Provide and upload a completed 502 checklist along with any items requested by the 502 checklist.
• Structural design of the building can be a stamped letter from an Idaho licensed engineer or provide full structural design calculations from an Idaho licensed engineer
|
Application received | | | 10/8/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 8 2019 4:15PM
|