BLD-Aging Inspection | 4/28/2020 | 4/28/2020 | 4/28/2020 | | PASS |
Mike Jordan
|
|
|
Needs to pivk up c.o.
|
BLD-Final | 12/15/2019 | 12/16/2019 | 12/16/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Neil CANNADY. Ok for perm occ.
|
FIRE-Final Inspection | 12/15/2019 | 12/16/2019 | 12/16/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Phone #: ###-#### Inspection requested via web by Neil CANNADY
|
BLD-Framing/Rough-in | 12/9/2019 | 12/10/2019 | 12/10/2019 | P | PASS |
Mike Jordan
|
|
|
Plumbing inspection was scheduled for 12/9 so I need framing inspection. Phone #: ###-#### Inspection requested via web by Neil CANNADY
|
Issue PAID IN FULL permit | | | 11/22/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/22/2019 | | DONE |
|
|
|
|
(F) Reprint permit | | | 11/22/2019 | | DONE |
|
|
|
|
Route to Impact Fee Review | 11/20/2019 | 11/23/2019 | 11/21/2019 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Permit Ready to Issue | | | 11/21/2019 | | DONE |
|
|
|
Need
GC Form
Revised Cert of Value
|
Plan assigned to (CJW) | 10/15/2019 | 11/8/2019 | 11/20/2019 | | PASS |
Carl Westfall
|
|
|
11/01/19 (L-3 - 15 days) (eplan - 4 sheets) Idaho Independent Living Council
|
1st review completed | | | 11/20/2019 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/20/2019 | | DONE |
|
|
|
|
Routing - FIRE | 10/15/2019 | 10/15/2019 | 11/8/2019 | | PASS |
Erika Akin
|
|
|
No comments attached. Inspector to field verify life safety.
|
Routing - PLAN CHECK | 10/15/2019 | | 10/20/2019 | | PASS |
Carl Westfall
|
|
|
|
Routing - PLANNING | 10/15/2019 | | 10/17/2019 | | PASS |
Karla Nelson
|
|
|
|
Routing - Addressing | 10/15/2019 | | 10/15/2019 | | PASS |
Doug Chausow
|
|
|
Updated parcel number.
|
Routing - PUBLIC WORKS | 10/15/2019 | | 10/15/2019 | | PASS |
Morgan Webb
|
|
|
NO NEW FEES. CREDIT FOR DEMO.
|
Intake Approval | | | 10/14/2019 | | PASS |
|
|
|
|
Intake Approval | | | 10/10/2019 | | FAIL |
Javier Guzman
|
|
|
For prescreen review provide and upload the following:
• Some keynotes on plan sheet A1.0 do not reference the correct items listed and some keynotes are not listed (for example right of the main door keynote #21 not listed and office doors keynote #13 states they are outlets), revise and match keynotes shown to correspond with listed keynotes.
• The uploaded COMcheck on plan sheet A1.2 references the 2009 IECC which is not used, revise the COMcheck so that it references the 2015 IECC
|
Application received | | | 10/8/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 8 2019 4:21PM
|