BLD-Final | 12/17/2019 | 12/18/2019 | 12/18/2019 | A | DONE |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by Sarah Schuller
|
DOC - Permit Finaled | 12/18/2019 | 12/18/2019 | 12/18/2019 | P | PASS |
Tony Young
|
|
|
done
|
Issue PAID IN FULL permit | | | 12/2/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/2/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 11/6/2019 | 11/6/2019 | 11/27/2019 | | PASS |
Josh Bogle
|
|
|
11/12 PV, ePlan - 1st done
|
Routing - PLAN CHECK | 11/27/2019 | | 11/27/2019 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/27/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 11/27/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 11/18/2019 | | 11/18/2019 | | FAIL |
Josh Bogle
|
|
|
engineering doesn't seem to address the carport
|
Routing - PLAN CHECK | 11/6/2019 | | 11/8/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLANNING | 11/6/2019 | | 11/8/2019 | | PASS |
Ted Vanegas
|
|
|
|
1st review completed | | | 11/8/2019 | | FAIL |
Josh Bogle
|
|
|
|
Intake Approval | | | 11/6/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/6/2019 | | DONE |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/6/2019 | | DONE |
|
|
|
|
Intake Approval | | | 10/25/2019 | | FAIL |
|
|
|
You may not apply for this building permit until after the appeals period has lapsed. You may apply for this permit on November 5, 2019.
|
Intake Approval | | | 10/15/2019 | | FAIL |
|
|
|
2nd prescreen: Planning and Zoning case DRH19-00462 needs to be reviewed and approved AND the appeals period must expire before you can resubmit for this building permit.
|
Application received | | | 10/9/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 9 2019 2:54PM
|
Intake Approval | | | 10/9/2019 | | FAIL |
|
|
|
Please contact planning and zoning prior to resubmitting for this building permit. This parcel is in the Historic area and will you will need to speak with a planner. ###-####
|