Print Statement | | | 8/13/2020 | | DONE |
|
|
|
plan mod fee
|
Routing - MECHANICAL | 6/17/2020 | | 6/17/2020 | | PASS |
Troy James
|
|
|
Removed supply and return from flex room which is now pantry.
|
BLD-Energy code compliance | 6/16/2020 | 6/16/2020 | 6/16/2020 | P | PEND |
Dave Hannah
|
|
|
Forest *screened* Phone #: ###-#### ok to cover after mec rough in c/n items signed off
|
BLD-Framing/Rough-in | 6/8/2020 | 6/8/2020 | 6/9/2020 | P | PART |
Dave Hannah
|
|
|
Screened-Forest Phone #: ###-#### ok to insulate needs to add truss bracing
|
Plan Modification Accepted | | | 6/8/2020 | | DONE |
|
|
|
Ashley from Quality requested plan mod workflow started for Manual J.
|
BLD-Wall Bracing | 5/21/2020 | 5/22/2020 | 5/22/2020 | A | PASS |
Dave Hannah
|
|
|
Screened- Daniel- Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 5/21/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 4/24/2020 | | |
|
|
|
|
Plan assigned to (J_N) | 3/10/2020 | 3/10/2020 | 4/24/2020 | | DONE |
Jenny Nelson
|
|
|
1st complete 03/16 plan mod #1 -submitting a modified house plan that will have a bonus room above the garage that is accessed by a staircase from the living room area. We will be removing the office from the plan to make room for the stairs. Will inform HVAC contractor of plan change to update the manual J
|
Routing - PLANNING | 4/24/2020 | | 4/24/2020 | | PASS |
Sue Cummings
|
|
|
Pass per ePlan pass on 4/24/20 for planning review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/24/2020 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 4/24/2020 | | DONE |
|
|
|
**DO NOT REISSUE - PLAN MOD**
|
Routing - PLANNING | 4/22/2020 | | 4/22/2020 | | FAIL |
Sue Cummings
|
|
|
The garage setback is 20 ft. from P.L. and the driveway can only be 33 ft. wide.
|
BLD-Foundation | 4/6/2020 | 4/7/2020 | 4/7/2020 | P | PASS |
Dave Hannah
|
|
|
*Screened* - Pat Phone #: ###-####
|
BLD-Footing | 4/3/2020 | 4/6/2020 | 4/6/2020 | P | PASS |
Dave Hannah
|
|
|
clear // Pat Phone #: ###-####
|
Routing - PLAN CHECK | 4/6/2020 | | 4/6/2020 | | PASS |
Jenny Nelson
|
|
|
|
Routing - PLANNING | 4/6/2020 | | 4/6/2020 | | PASS |
Sue Cummings
|
|
|
|
Routing - MECHANICAL | 4/6/2020 | | 4/6/2020 | | PASS |
Troy James
|
|
|
|
Telephone call | | | 4/6/2020 | | DONE |
|
|
|
Per Troy Mechanical Inspector, Mechanical Review fee is not required.
|
Intake Approval | | | 4/1/2020 | | PASS |
|
|
|
Prescreen approved per JJN telephone call notes.
|
Plan Reviewer's activity | | | 3/25/2020 | | DONE |
Jenny Nelson
|
|
|
Talked to applicant on phone, he was having trouble getting things to upload correctly, I told him I'll accept it and can take care of the drawings that didn't version over correctly. JJN
|
Telephone call | | | 3/11/2020 | | DONE |
|
|
|
spoke with Forest and explain why the prescreen for his plan mod wes sent back
|
Intake Approval | | | 3/11/2020 | | FAIL |
|
|
|
prescreen for the plan mod was fail because applicant did not name the drawings the same, spoke with Forest over the phone and explain this. The new drawings that were submitted on 3/11/2020 were deleted so that he can name them the same and they can version over.
|
Plan Modification Accepted | | | 3/10/2020 | | DONE |
|
|
|
plan mod #1
|
Issue PAID IN FULL permit | | | 1/17/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 1/17/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 12/2/2019 | | |
|
|
|
|
Plan assigned to (J_N) | 10/23/2019 | 10/23/2019 | 12/2/2019 | | DONE |
Jenny Nelson
|
|
|
11/05 sfd L1 ePlan. 1st complete 11/7, need bracing full calcs, headers not adequate
|
Routing - PLAN CHECK | 12/2/2019 | | 12/2/2019 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/2/2019 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 12/2/2019 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 11/20/2019 | | 11/20/2019 | | FAIL |
Jenny Nelson
|
|
|
No bracing calcs
|
1st review completed | | | 11/7/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 10/23/2019 | | 11/7/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - MECHANICAL | 10/23/2019 | | 10/25/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 10/23/2019 | 10/26/2019 | 10/24/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 10/23/2019 | | 10/24/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 10/23/2019 | | 10/23/2019 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/23/2019 | | DONE |
|
|
|
|
Intake Approval | | | 10/23/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/23/2019 | | DONE |
|
|
|
|
Routing - PLANNING | 10/23/2019 | | 10/23/2019 | | PASS |
Sue Cummings
|
|
|
|
Telephone call | | | 10/15/2019 | | DONE |
|
|
|
Spoke with Forest the applicant, the wrong drawings were uploaded when he corrected the file names. He asked me to delete all the plans because two different house plans were uploaded and he wasnt sure which was for which house.
|
Intake Approval | | | 10/15/2019 | | FAIL |
|
|
|
Wrong drawings were uploaded. There were two different house plans in the drawings and the applicant wasnt sure which was which. So all plans were deleted, so they could reupload the correct ones.
|
Intake Approval | | | 10/11/2019 | | FAIL |
|
|
|
1. Plans need to be to the 2015 IRC, 2012 can not be accepted.
2. Manual J
3. Drawing file names must include the first characters of the discipline name followed by the sheet number and name. Example: A2.0_Floor Plan
|
Application received | | | 10/10/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 10 2019 4:02PM
|
Fees Due Hold | 6/18/2020 | | | | |
|
|
|
|