Permanent Occupancy | | | 5/4/2020 | | DONE |
|
|
|
|
BLD-Final | 4/29/2020 | 4/30/2020 | 4/30/2020 | A | PASS |
Mike Jordan
|
|
|
Screened- Dave Phone #: ###-####. Ok for perm occ. Noted that added sinks and water hearter installed with no permits has been removed.
|
BLD-Conference | 4/24/2020 | 4/27/2020 | 4/27/2020 | A | CANC |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 4/22/2020 | 4/24/2020 | 4/24/2020 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Lid was removed from the rug tumbler to allow overhead sprinkler coverage.Dave Phone #: ###-####
|
Issue PAID IN FULL permit | | | 2/12/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/12/2020 | | DONE |
|
|
|
|
Route to Impact Fee Review | 1/21/2020 | 1/24/2020 | 1/21/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 1/8/2020 | 1/10/2020 | 1/21/2020 | | PASS |
Mark Stumbaugh
|
|
|
01/21 - L2 Zerorez
|
Plan assigned to (JAR) | 1/8/2020 | 1/8/2020 | 1/21/2020 | | DONE |
Julie Romig
|
|
|
01/21 - IBC Rev Comp - L2 Zerorez
|
1st review completed | | | 1/21/2020 | | DONE |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/21/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 1/21/2020 | | DONE |
|
|
|
all met
NEED
GC FORM (if tenant is acting as GC, they will need approval from parcel owner)
REVISED VALUE
|
Print Occupancy Form | | | 1/21/2020 | | DONE |
|
|
|
|
Telephone call | | | 1/21/2020 | | DONE |
|
|
|
Called David, permit is ready to be picked up need GC and Rev values
|
Telephone call | | | 1/21/2020 | | DONE |
|
|
|
David Grigsby called to say that he is hoping to act as the GC with permission from Sundance. I told him he must have sundance contact us to give him permission to do so. If Sundance gives him permission, we do not need the 306 and can add the fees per the original value.
|
Routing - PLAN CHECK | 1/10/2020 | | 1/10/2020 | | PASS |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 1/9/2020 | | 1/10/2020 | | PASS |
Troy James
|
|
|
See letter from business owner. No repairs allowed in storage area of service vans. Existing exhaust and make up air openings is sufficient to remove any vehicle exhaust and okay to operate manually.
|
Case Summary (BLD) | | | 1/10/2020 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 1/8/2020 | | 1/9/2020 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 1/8/2020 | | PASS |
|
|
|
|
Routing - Addressing | 1/8/2020 | | 1/8/2020 | | PASS |
Gemma Flores
|
|
|
|
Application received | | | 10/14/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 14 2019 4:27PM
|