BLD-Final | 2/10/2020 | 2/10/2020 | 2/10/2020 | P | DONE |
Tony Young
|
|
|
Kevin Phone #: ###-####
|
DOC - Permit Finaled | 2/10/2020 | 2/10/2020 | 2/10/2020 | P | PASS |
Tony Young
|
|
|
done
|
BLD-Framing/Rough-in | 1/17/2020 | 1/17/2020 | 1/17/2020 | P | PASS |
Tell Riley
|
|
|
Kevin Phone #: ###-####//framing per engineering//ele ok// may need fire separation in garage and 20 min door//will need to relocate dryer vent//talked with Josh about garage separation//will let Kevin Know
|
BLD-Footing | 12/13/2019 | 12/13/2019 | 12/13/2019 | P | PASS |
Brandon Shaw
|
|
|
Kevin Phone #: ###-####
|
Routing Walk-In (Zoning) | 12/13/2019 | 12/13/2019 | 12/13/2019 | A | PASS |
Jeff Lowe
|
|
|
per cva19-00065
|
Routing Walk-In (BLD) | 12/13/2019 | 12/13/2019 | 12/13/2019 | A | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 12/13/2019 | | 12/13/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 12/13/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 12/13/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/13/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 12/13/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/13/2019 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 12/9/2019 | 12/9/2019 | 12/9/2019 | A | FAIL |
Jeff Lowe
|
|
|
10 day appeal period over 12/12 5pm
|
Routing Walk-In (Zoning) | 10/15/2019 | 10/15/2019 | 10/15/2019 | A | FAIL |
Jeff Lowe
|
|
|
variance is required. removing the patio cover and attaching a fully enclosed room creates one structure - the exsting garage is within the setback.
|
Routing Walk-In (BLD) | 10/15/2019 | 10/15/2019 | 10/15/2019 | A | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 10/15/2019 | | 10/15/2019 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 10/15/2019 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 10/15/2019 | | | |
|
|
|
|