Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD19-04124
StatusFinaled
Name PARKWAY STATION LLC
Site Address 999 W MAIN ST Unit: STE 1400
Project NameGalena Opportunity Fund
Customer Number 
ePlanReviewNo
Description
(GALENA OPPORTUNITY FUND – 14TH STORY) The fire sprinkler system is used for high rise. To remodel an existing 2,153 square foot tenant space located on the 14th story of an existing high rise building for a new office tenant. Work is to include interior non-bearing walls, interior doors, interior glass windows, millwork, and finishes. The existing 2-hr fire barrier wall that functions as a horizontal exit that was constructed in 1994 is required to be maintained. The common toilet rooms were upgraded to be accessible to the disabled under permit BLD18-02263. The work authorized under that permit is required to be completed and the permit finaled before a permanent Certificate of Occupancy is issued to this tenant. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  5/7/2020 DONE
1st notice
Print Statement  4/13/2020 DONE
Print Statement  4/3/2020 DONE
Second Notice 2/17/20202/13/2020 DONE
This permit finaled on the web by Zach Clegg
First Notice 1/31/20202/7/2020 DONE
mailed 2-10-20
Plan Reviewer's activity  1/24/2020 DONE
Paper drawings taken to records
BLD-Final1/17/20201/21/20201/21/2020PPASS
DetailsDave Hannah
Albert Phone #: ###-####
FIRE-Final Inspection1/17/20201/21/20201/21/2020APASS
DetailsJim Page
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete, signatures provided on permit sign off card.

Albert Phone #: ###-####
Permanent Occupancy  1/21/2020 DONE
BLD-Framing/Rough-in12/3/201912/3/201912/3/2019PPASS
DetailsBrandon Shaw
OK to cover...
Telephone call  11/22/2019 DONE
call out to Zach (###-####) to informed him that 302 & 306 is needed to complete the permit process.
Issue PAID IN FULL permit  11/22/2019 DONE
Plan assigned to (CJW)10/21/201911/11/201911/21/2019 PASS
DetailsCarl Westfall
11/04/19 (L-3 - 15 days) (paper - 14 sheets) Galena Oortunity Fund (Applicant expecting it done by the 22)
Routing - FIRE10/21/201910/21/201911/21/2019 PASS
DetailsErika Akin
Discussed this project with Erika Ekin. Although a fire sprinkler permit and a fire alarm permit will be required, routing to Erika was not required.
1st review completed  11/21/2019 DONE
PLANS/APPL TAKEN TO FRONT DESK  11/21/2019 DONE
Permit Ready to Issue  11/21/2019 DONE
MET
Need
GC FORM
REVISED VALUE
Print Occupancy Form  11/21/2019 DONE
Routing - PLAN CHECK10/28/2019 11/21/2019 PASS
DetailsCarl Westfall
Pending Assignment by CDM10/15/2019 11/21/2019 PASS
DetailsCarl D Madsen
Routing - MECHANICAL10/21/2019 10/28/2019 PASS
DetailsTroy James
Routing - PUBLIC WORKS10/21/2019 10/25/2019 PASS
DetailsMorgan Webb
NO NEW PLUMBING
Routing - Addressing10/21/2019 10/24/2019 PASS
DetailsDoug Chausow
Plans ACCEPTED BY PLAN TECH  10/15/2019 DONE
Recd Pcfee & Taken To Pln CK  10/15/2019 DONE
Intake Approval  10/15/2019 PASS
DetailsCarl Westfall
Application received 10/15/2019