Permanent Occupancy | | | 11/20/2019 | | DONE |
|
|
|
|
BLD-Final | 11/5/2019 | 11/6/2019 | 11/6/2019 | A | PASS |
Dave Hannah
|
|
|
office closed until 9am // Ethan Phone #: ###-####
|
FIRE-Final Inspection | 11/5/2019 | 11/5/2019 | 11/5/2019 | P | PASS |
Jim Page
|
|
|
No fire sprinklers, no fire alarms, fire extinguishers are placed with current inspection tags. Final life fire safety inspection is complete.
Ethan Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/29/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 10/15/2019 | 10/15/2019 | 10/22/2019 | | PASS |
Javier Guzman
|
|
|
10/21 L2 Commerical Northwest Occ Eval paper
|
Routing - PLAN CHECK | 10/17/2019 | | 10/22/2019 | | PASS |
Javier Guzman
|
|
|
|
Case Summary (BLD) | | | 10/22/2019 | | DONE |
Javier Guzman
|
|
|
|
1st review completed | | | 10/22/2019 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/22/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/22/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/22/2019 | | DONE |
|
|
|
|
Telephone call | | | 10/22/2019 | | DONE |
|
|
|
left a message for natalie informing her this permit is ready and one of us will go over the required inspections
|
Routing - Addressing | 10/15/2019 | | 10/17/2019 | | PASS |
Doug Chausow
|
|
|
Suite 100
|
Routing - PUBLIC WORKS | 10/15/2019 | | 10/17/2019 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/15/2019 | | DONE |
|
|
|
|
Intake Approval | | | 10/15/2019 | | PASS |
Javier Guzman
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/15/2019 | | DONE |
|
|
|
|
First Notice | | 11/30/2019 | | | |
|
|
|
|
Application received | | 10/15/2019 | | | |
|
|
|
|