Permit Information
Permit NumberBLD19-04133
StatusIssued
Name ASIN GENERAL CONTRACTORS
Site Address 5395 N EUGENE ST
Project NameADU Greiner Guest House
Customer NumberMAIN HOUSE BLD19-03963
ePlanReviewYes
Description
**PRESCRIPTIVE ENERGY REQUIREMENT***Per Leon, customer should have recorded deed restriction and final approval from irrigation company as part of their documents in eplan*** Permit for the construction of a new 700 sq. ft., one story accessory dwelling unit with 2 bedrooms, 1.5 bathrooms, approximately 80 sq. ft. of covered patio/porch and a 325 sq. ft. attached garage per the approved plans and any notations. R-1C zoning and setbacks per planning. D_S
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Foundation8/4/20208/4/20208/4/2020PPART
DetailsTony Young
Jose ###-####
BLD-Foundation8/3/20208/4/20208/4/2020ANR
DetailsTony Young
jose
BLD-Footing7/31/20208/3/20208/3/2020APASS
DetailsTony Young
Jose Phone #: ###-####
BLD-Footing7/31/20207/31/20207/31/2020PNR
DetailsTony Young
Jose Phone #: ###-####
BLD-Footing7/30/20207/31/20207/31/2020ANR
DetailsTony Young
Jose Phone #: ###-####
Issue PAID IN FULL permit  7/10/2020 DONE
Inspection Record Card- Bld  7/10/2020 DONE
Extend Review Timeline  6/15/2020 DONE
1st approved 180 day extension per joe. see documents
Telephone call  6/9/2020 DONE
sent email to scott informing permit is 57 days past the expiration date
OVERRIDE  6/3/2020  
Plan assigned to (D_S) Debbie4/28/20204/28/20206/3/2020 DONE
DetailsDebbie Sanine
PLANS/APPL TAKEN TO FRONT DESK  6/3/2020 DONE
DetailsDebbie Sanine
Permit Ready to Issue  6/3/2020 DONE
MET
Routing - PLAN CHECK5/29/2020 5/29/2020 PASS
DetailsDebbie Sanine
Routing - FIRE5/8/20205/8/20205/14/2020 PASS
DetailsLee G Meredith
Access distance exceeds the maximum allowed. Sprinklers are required.

6-2-20 Resubmittal notes on the cover sheet that an NFPA 13D sprinkler system will be provided in the ADU.
1st review completed  5/8/2020 FAIL
DetailsDebbie Sanine
Routing - PLAN CHECK4/28/2020 5/8/2020 FAIL
DetailsDebbie Sanine
Route to Impact Fee Review4/28/20205/1/20204/29/2020 PASS
DetailsShannon Cade
Initial residential review of new SFD permits requested for now.
Routing - MECHANICAL4/28/2020 4/28/2020 PASS
DetailsTroy James
Routing - PLANNING4/28/2020 4/28/2020 PASS
DetailsLeon Letson
Routing - Addressing4/28/2020 4/28/2020 PASS
DetailsDoug Chausow
ADU Address: 5395 N Eugene St
Routing - PUBLIC WORKS4/28/2020 4/28/2020 PASS
DetailsCandy A. Nichols
Plans ACCEPTED BY PLAN TECH  4/28/2020 DONE
Intake Approval  4/28/2020 PASS
Recd Pcfee & Taken To Pln CK  4/28/2020 DONE
Intake Approval  10/25/2019 FAIL
Second Prescreen 0-25-19
Please provide Manual J
Recorded deed (Per Leon Letson)
Intake Approval  10/18/2019 FAIL
Please refer to ePlanReview Standards - https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
1. Move the "Designed by Jo" stamp and all other text and linework to comply with ePlan Standards (it is where the city stamp will be) - See page 6
2. Rename sheets according to ePlan Standards. See page 6
3. Provide ACCA report on HVAC system - see page 2 of the Submittal Checklist (required) - https://www.cityofboise.org/media/7086/402-new-residential-submittal-checklist.
4. Per Leon in planning, customer should have recorded deed restriction and final approval from irrigation company as part of his documents in eplan
5. Show crawlspace and attic access
Application received  10/16/2019 DONE
Application submitted via PDS Online on Oct 16 2019 11:13AM