BLD-Final | 4/27/2020 | 4/28/2020 | 4/28/2020 | A | PASS |
Brandon Shaw
|
|
|
Corrections SAT...
|
DOC - Permit Finaled | 4/28/2020 | 4/28/2020 | 4/28/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Final | 4/14/2020 | 4/14/2020 | 4/14/2020 | P | FAIL |
Dave Hannah
|
|
|
Screened- new addition nobody''s live in it-Brad Phone #: ###-#### c/n posted on window
|
BLD-Energy code compliance | 2/6/2020 | 2/7/2020 | 2/7/2020 | P | PASS |
Brandon Shaw
|
|
|
This was rescheal for the PM//brad Phone #: ###-####
|
BLD-Framing/Rough-in | 2/4/2020 | 2/4/2020 | 2/4/2020 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate...
|
BLD-Framing/Rough-in | 2/3/2020 | 2/4/2020 | 2/4/2020 | A | DEFR |
Brandon Shaw
|
|
|
Brad Phone #: ###-####
|
DOC - Permit Finaled | 2/4/2020 | 2/4/2020 | 2/4/2020 | P | PASS |
Brandon Shaw
|
|
|
See BLD19-01239 for re-roof permit...
|
CHANGE STATUS TO (ISS) | | | 2/4/2020 | | DONE |
|
|
|
Per Brandon (480), Doc finaled by mistake. Changed status to issued
|
Routing - MECHANICAL | 1/21/2020 | | 1/21/2020 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Wall Bracing | 1/15/2020 | 1/15/2020 | 1/15/2020 | P | PART |
Brandon Shaw
|
|
|
Ok to cover exterior... Hold downs and straps to be installed before framing rough-in...
|
DOC - Permit Finaled | 1/15/2020 | 1/15/2020 | 1/15/2020 | P | PASS |
Brandon Shaw
|
|
|
|
CHANGE STATUS TO (ISS) | | | 1/15/2020 | | DONE |
|
|
|
doc final accidentlly by Brandon- put back in ISS per Brandon
|
BLD-Framing/Rough-in | 12/26/2019 | 12/27/2019 | 12/27/2019 | A | PART |
Brandon Shaw
|
|
|
Fire wall sheet rock- Erin Phone #: ###-####
|
BLD-Foundation | 11/18/2019 | 11/19/2019 | 11/19/2019 | A | PASS |
Dave Hannah
|
|
|
Aron Phone #: ###-####
|
BLD-Footing | 11/14/2019 | 11/15/2019 | 11/15/2019 | A | PART |
Tell Riley
|
|
|
Aron Phone #: ###-####//WIP--rebar being installed//setbacks per plans//
|
OVERRIDE | | | 11/4/2019 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/4/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/4/2019 | | DONE |
|
|
|
|
Routing Walk-In (BLD) | 11/1/2019 | 11/1/2019 | 11/1/2019 | P | DONE |
Josh Bogle
|
|
|
|
Plan assigned to (JAB) Josh | 10/17/2019 | 10/17/2019 | 11/1/2019 | | PASS |
Josh Bogle
|
|
|
10/24 duplex, paper - 1st done
|
Routing - PLAN CHECK | 11/1/2019 | | 11/1/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 11/1/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 11/1/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/1/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Additional plans submitted | | | 11/1/2019 | | DONE |
|
|
|
Two copies of sheets A0.01, A2.00, A3.01, A3.11 and S1.02 taken to Josh
|
1st review completed | | | 10/28/2019 | | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 10/18/2019 | | 10/28/2019 | | FAIL |
Josh Bogle
|
|
|
missing existing floor plans, some details could use clarification
|
Routing - MECHANICAL | 10/16/2019 | | 10/18/2019 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 10/16/2019 | 10/22/2019 | 10/17/2019 | | PASS |
Eric Bilimoria
|
|
|
|
Routing Walk-In (BLD) | 10/16/2019 | 10/16/2019 | 10/17/2019 | P | PASS |
Josh Bogle
|
|
|
took in for level two routing
|
Routing - Addressing | 10/16/2019 | | 10/17/2019 | | PASS |
Doug Chausow
|
|
|
Turning SFD to Duplex, additional address: 97 E Parkway Dr
|
Routing - PUBLIC WORKS | 10/16/2019 | | 10/17/2019 | | PASS |
Morgan Webb
|
|
|
|
Plan Reviewer's activity | | | 10/17/2019 | | DONE |
Josh Bogle
|
|
|
gave to Permit Tech for 402 routing
|
Routing Walk-In (Zoning) | 10/16/2019 | 10/16/2019 | 10/16/2019 | P | DONE |
Leon Letson
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/16/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/16/2019 | | DONE |
|
|
|
|
Intake Approval | | | 10/16/2019 | | |
|
|
|
|
Application received | | 10/16/2019 | | | |
|
|
|
|