BLD-Final | 4/27/2020 | 4/29/2020 | 4/29/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
DOC - Permit Finaled | 4/29/2020 | 4/29/2020 | 4/29/2020 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 4/24/2020 | 4/28/2020 | 4/27/2020 | A | CANC |
Jim Storey
|
|
|
Phone #: ###-#### >> Inspection requested via web by James Jackson Inspection cancelled from web by: James Jackson
|
BLD-Energy code compliance | 2/12/2020 | 2/13/2020 | 2/13/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
BLD-Framing/Rough-in | 2/10/2020 | 2/11/2020 | 2/11/2020 | A | PASS |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by James Jackson
|
Routing - MECHANICAL | 2/7/2020 | | 2/7/2020 | | PASS |
Troy James
|
|
|
Resubmitted manual j report
|
BLD-Footing | 12/3/2019 | 12/3/2019 | 12/3/2019 | P | PASS |
Jim Storey
|
|
|
Giber Phone #: ###-####
|
Issue PAID IN FULL permit | | | 11/25/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/25/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 11/6/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 11/6/2019 | | DONE |
|
|
|
met
|
Plan assigned to (J_N) | 10/17/2019 | 10/17/2019 | 11/5/2019 | | DONE |
Jenny Nelson
|
|
|
10/30 sfd L1 ePlan. 1st complete 10/24, fire rated eave, clarify struc calcs, failed planning.
|
Routing - PLAN CHECK | 11/5/2019 | | 11/5/2019 | | PASS |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/5/2019 | | DONE |
Jenny Nelson
|
|
|
|
Telephone call | | | 11/5/2019 | | DONE |
|
|
|
Batch stamped not finished because Impact fees are being looked at by Travis because the Demo was not noted on the building permit at the begining of the process so fees for impact might need to be adjusted.
|
Routing - Design Review | 11/4/2019 | | 11/4/2019 | | PASS |
Katelyn Menuge
|
|
|
Redlined requirements
|
1st review completed | | | 10/24/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 10/17/2019 | | 10/24/2019 | | FAIL |
Jenny Nelson
|
|
|
fire rated eave, clarify structural calcs
|
Routing - Addressing | 10/17/2019 | | 10/22/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - MECHANICAL | 10/17/2019 | | 10/21/2019 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 10/17/2019 | 10/20/2019 | 10/18/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 10/17/2019 | | 10/18/2019 | | DONE |
Sue Cummings
|
|
|
Sent to Katelyn M.
|
Routing - PUBLIC WORKS | 10/17/2019 | | 10/18/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Design Review | 10/18/2019 | | 10/18/2019 | | FAIL |
Katelyn Menuge
|
|
|
See Changemarks
|
Application received | | | 10/17/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 17 2019 10:35AM
|
Plans ACCEPTED BY PLAN TECH | | | 10/17/2019 | | DONE |
|
|
|
|
Intake Approval | | | 10/17/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/17/2019 | | DONE |
|
|
|
|