Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD19-04225
StatusIssued
Name SEAN CAFFERTY ENTERPRISES
Site Address 405 S CAPITOL BLVD
Project NameYoi Tomo Sushi/Grill Expansion
Customer Number 
ePlanReviewYes
Description
(YOI TOMO SUSHI & GRILL EXPANSION) Permit to expand the existing 1,982 sq ft restaurant into the adjacent 771 sq ft tenant space to create a 2,753 sq ft restaurant. Work to include: demo of existing interior non-bearing walls, cabinetry, and sinks; replacing exterior door with storefront glazing; new interior non-bearing walls; new ceiling soffit and suspended lay-in ceiling system; new electrical including light fixtures in compliance with the 2015 IECC; mechanical; plumbing; and interior finishes in compliance with Ch. 8 of the 2015 IBC. All work to be done per the approved plans, plan review report and any notations. This building is fully Fire Sprinklered with an approved Fire Alarm system due to high rise requirements. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/6/20202/6/20202/6/2020PPASS
DetailsDave Hannah
Dustin Phone #: ###-####
FIRE-Final Inspection2/4/20202/5/20202/5/2020PPASS
DetailsJim Page
Previously noted item for fire alarm correction complete, final life fire safety inspection for area of work complete, signatures provided on permit sign off card.

Justin Phone #: ###-####
BLD-Final1/31/20201/31/20202/3/2020PPART
DetailsDave Hannah
Justin Phone #: ###-#### ok for tco ok for perm after fire gos perm
FIRE-Final Inspection1/31/20201/31/20201/31/2020PPART
DetailsJim Page
Partial final inspection for life fire safety complete, a minor fire alarm modification was required, hotel fire panel is what provides notification to the fire alarms in area of work, fire alarm inspection for the 1 strobe addition will be completed on 05FEB2020. No fire sprinkler modifications, fire extinguishers are placed with current inspection tags. TCO authorized for 14 days per conversation with Joe Bruce, Fire Section Supervisor. After fire alarm inspection is inspected and finaled this permit can be signed off for life fire safety. Chest freezer will be relocated as discussed.

Justin Phone #: ###-####
BLD-Final1/27/20201/28/20201/28/2020PNR
DetailsDave Hannah
Justin - call in advance Phone #: ###-####
FIRE-Final Inspection1/27/20201/28/20201/28/2020AFAIL
DetailsJim Page
Provide fire alarm notification in waiter station area as discussed, any and all modifications to the fire alarm system will require a seperate permit. Relocate chest freezer that is blocking designated exit path from new kitchen opening into kitchen as discussed.

Justin - call in advance Phone #: ###-####
BLD-Framing/Rough-in1/6/20201/7/20201/7/2020APASS
DetailsDave Hannah
Justin Phone #: ###-####
Issue PAID IN FULL permit  12/13/2019 DONE
Issue PAID IN FULL permit  12/13/2019 DONE
Print Occupancy Form  12/13/2019 DONE
Route to Impact Fee Review12/11/201912/14/201912/12/2019 PASS
DetailsShannon Cade
Review requested for Commercial Permit
Plan assigned to (JAR)11/14/201911/14/201912/11/2019 DONE
DetailsJulie Romig
12/10 - L3 Yoi Tomo
Routing - PLAN CHECK11/14/2019 12/11/2019 PASS
DetailsJulie Romig
1st review completed  12/11/2019 DONE
DetailsJulie Romig
PLANS/APPL TAKEN TO FRONT DESK  12/11/2019 DONE
Permit Ready to Issue  12/11/2019 DONE
all met
Need GC
Need Revised Value
Routing - FIRE11/14/201911/14/201912/10/2019 PASS
DetailsErika Akin
Attached comments to case
Routing PW Environmental11/15/2019 11/18/2019 PASS
DetailsRick Christenson
Routing - MECHANICAL11/14/2019 11/18/2019 PASS
DetailsChad Schwendiman
Routing - Addressing11/14/2019 11/15/2019 PASS
DetailsLaura Hunter
Routing - PUBLIC WORKS11/14/2019 11/15/2019 PASS
DetailsMorgan Webb
NO NEW CUSTOMER SERVICE AREA.
Routing - Design Review11/14/2019 11/15/2019 PASS
DetailsJosh Wilson
Routing - PLANNING11/14/2019 11/14/2019 PASS
DetailsDavid Moser
see czc19-00257
Intake Approval  11/13/2019 PASS
Intake Approval  10/30/2019 FAIL
DetailsJavier Guzman
For prescreen review provide and upload the following:
• The adjacent space is an existing M occupancy and with the new dinning assembly expansion change in M use requires a major T.I. 520 checklist (directed by Carl M), provide a completed 520 checklist and any other item requested from the 520 checklist, also checklist is not complete unless all information is filled out, all appropriate boxes are checked, and all plan page numbers are listed.
• Provide how any new interior wall are being braced top of wall
• Provide suspended acoustic ceiling details section
• Provide mechanical and plumbing engineered plans per checklist due to food service or provide a transcript between you and the department head mechanical and plumbing supervisor stating no engineered plans are required.
Application received  10/23/2019 DONE
Application submitted via PDS Online on Oct 23 2019 4:14AM