FIRE-Final Inspection | 8/13/2020 | 8/13/2020 | 8/13/2020 | P | PASS |
Greg Ruxton
|
|
|
Pssed final fire inspection.
Fire Final on Carports. Phone #: ###-#### Inspection requested via web by Bob Goodwin
|
BLD-Final | 7/1/2020 | 7/2/2020 | 7/2/2020 | P | CANC |
Mike Jordan
|
|
|
Final Inspections for carports Phone #: ###-#### >> Inspection requested via web by Kris Linnell Inspection cancelled from web by: Kris Linnell
|
FIRE-Final Inspection | 7/1/2020 | 7/2/2020 | 7/2/2020 | P | CANC |
Troy Cobbley
|
|
|
Final Inspections for carports Phone #: ###-#### >> Inspection requested via web by Kris Linnell Inspection cancelled from web by: Kris Linnell
|
BLD-Footing | 5/27/2020 | 5/28/2020 | 5/28/2020 | A | PASS |
Mike Jordan
|
|
|
Footing Inspection for Carport posts at Buildings 10, 11 and 12. Late as possible in the AM. Concrete is scheduled for 2pm. Phone #: ###-#### Inspection requested via web by Bob Goodwin
|
Print Occupancy Form | | | 1/15/2020 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 1/8/2020 | | DONE |
|
|
|
|
Telephone call | | | 1/8/2020 | | DONE |
|
|
|
Kris brought the permit and sign it// emailed permit to be sign to kmendive@wbtbc.com Eplan needs to be release
|
Print Occupancy Form | | | 1/8/2020 | | DONE |
|
|
|
|
Routing - FIRE | 11/21/2019 | 11/21/2019 | 12/30/2019 | | PASS |
Erika Akin
|
|
|
No comments attached. Carports do not encroach into required FD aerial access on approved site plan. Inspector to field verify.
|
Routing Off Site - STRUCTURAL | 11/21/2019 | | 12/30/2019 | | PASS |
Michael Hanson
|
|
|
AHJ
|
Plan assigned to (M_H) | 11/21/2019 | | 12/30/2019 | | DONE |
Michael Hanson
|
|
|
12/30 #502 L3 ePlan - Rosewood Apts Carports
|
1st review completed | | | 12/30/2019 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/30/2019 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 12/30/2019 | | DONE |
|
|
|
MET
Need GC
Need RP
need Revised Certificate of Value JCA
|
Routing - PLAN CHECK | 11/21/2019 | | 12/30/2019 | | PASS |
Michael Hanson
|
|
|
|
Routing - PLANNING | 11/21/2019 | | 11/25/2019 | | PASS |
Karla Nelson
|
|
|
|
Routing PW Street Lights | 11/21/2019 | | 11/25/2019 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Solid Waste | 11/21/2019 | | 11/22/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing - Addressing | 11/21/2019 | | 11/22/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/21/2019 | | 11/21/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 11/21/2019 | | 11/21/2019 | | PASS |
Michael Zawacki
|
|
|
Please refer to esc18-01769
|
Routing - Design Review | 11/21/2019 | | 11/21/2019 | | PASS |
Josh Wilson
|
|
|
ok per DRH18-00430
|
Routing PW Drainage | 11/21/2019 | | 11/21/2019 | | PASS |
Brian Murphy
|
|
|
|
Intake Approval | | | 11/19/2019 | | PASS |
Julie Romig
|
|
|
|
Intake Approval | | | 11/12/2019 | | FAIL |
Julie Romig
|
|
|
need: 4. Form 310 Statement of Special Inspections with all 10 pages completed by the structural engineer and cover page signed by owner.
Form 310 can be found here: https://www.cityofboise.org/media/3760/final310_special_inspections.pdf
|
Intake Approval | | | 10/25/2019 | | FAIL |
Julie Romig
|
|
|
To complete your application, please provide the following (also see items circled on checklist):
1. Form 304 Registered Design Professional Form for Structural Engineer, signed by owner;
2. Verification of Legal Lot or Parcel form, signed by PDS subdivision staff;
3. Site Specific Fire Flow at Hydrants Letter;
4. Form 310 Statement of Special Inspections completed by the structural engineer and signed by owner;
5. Planning & Zoning letters of approval;
6. Vicinity Map;
7. Code Analysis/Building Data;
8. Scaled site plan drawing at minimum 18" x 24" with dimensions locating carports on the site and dimensions between carports and adjacent buildings;
9. Identify required special inspections on structural plans;
10.Upload drawings as individual sheet files, with file names per the City of Boise naming standards (ie S1.0 General Structural Notes). Drawings have been deleted out of ePlanReview so they can be uploaded.
https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
|
Application received | | | 10/24/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 24 2019 1:40PM
|