BLD-Final | 12/17/2019 | 12/18/2019 | 12/18/2019 | A | PASS |
Tell Riley
|
|
|
Tony - No one on site, no special access required. Call if questions/issues. Phone #: ###-####//work appears to be done per the scope//no one onsite//
|
DOC - Permit Finaled | 12/18/2019 | 12/18/2019 | 12/18/2019 | P | PASS |
Tell Riley
|
|
|
|
Case Summary (BLD) | | | 12/18/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/26/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 11/26/2019 | | DONE |
|
|
|
|
Plan assigned to (JG) | 10/29/2019 | 10/29/2019 | 11/7/2019 | | PASS |
Javier Guzman
|
|
|
11/07 L2 Verizon antenna ePlan
|
Routing - PLAN CHECK | 10/29/2019 | | 11/7/2019 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 11/7/2019 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/7/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 11/7/2019 | | DONE |
|
|
|
harrellm@mrctowers.com
met: GC FORM
met: REVISED VALUE - the revised value send only had MEC value
|
Routing - PLANNING | 10/29/2019 | | 10/29/2019 | | PASS |
Ethan Mansfield
|
|
|
Do not issue permit until Nov 2nd. Appeal period runs until Nov. 1 at 5 PM
|
Intake Approval | | | 10/25/2019 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 10/24/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 24 2019 2:00PM
|
First Notice | 12/18/2019 | 12/18/2019 | | | |
Tell Riley
|
|
|
|