BLD-Final | 3/16/2020 | 3/17/2020 | 3/17/2020 | A | PASS |
Mike Jordan
|
|
|
jeff Phone #: ###-####
|
DOC - Permit Finaled | 3/17/2020 | 3/17/2020 | 3/17/2020 | P | PASS |
Mike Jordan
|
|
|
All issues were resolved.
|
BLD-Final | 3/13/2020 | 3/16/2020 | 3/16/2020 | A | NR |
Dave Hannah
|
|
|
Jeff Phone #: ###-#### need to install smoke detectors in bedrooms
|
BLD-Framing/Rough-in | 1/7/2020 | 1/8/2020 | 1/8/2020 | A | PASS |
Mike Jordan
|
|
|
jeff Phone #: ###-####
|
BLD-Wall Bracing | 1/7/2020 | 1/8/2020 | 1/8/2020 | A | PASS |
Mike Jordan
|
|
|
jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 1/6/2020 | 1/7/2020 | 1/7/2020 | A | FAIL |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Completeairseal/fireblock at penetrations in top plates.
|
BLD-Wall Bracing | 1/6/2020 | 1/7/2020 | 1/7/2020 | A | FAIL |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Install blocking at panel edges in corners, 4ft. in either direction nd fasten.
|
BLD-Framing/Rough-in | 12/18/2019 | 12/19/2019 | 12/19/2019 | P | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. New beam in kitchen.
|
BLD-Wall Bracing | 12/16/2019 | 12/17/2019 | 12/17/2019 | A | CANC |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 12/16/2019 | 12/17/2019 | 12/16/2019 | A | CANC |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
BLD-Energy code compliance | 12/11/2019 | 12/12/2019 | 12/12/2019 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
BLD-Framing/Rough-in | 12/10/2019 | 12/11/2019 | 12/11/2019 | A | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
BLD-Wall Bracing | 11/27/2019 | 11/27/2019 | 11/27/2019 | P | PASS |
Mike Jordan
|
|
|
Jeff Phone #: ###-####
|
OVERRIDE | | | 11/15/2019 | | |
|
|
|
|
BLD-Foundation | 11/14/2019 | 11/15/2019 | 11/15/2019 | A | PART |
Mike Jordan
|
|
|
Jeff- foundation wall inspection Phone #: ###-####
|
Routing Walk-In (BLD) | 11/15/2019 | 11/15/2019 | 11/15/2019 | A | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 11/15/2019 | | 11/15/2019 | | PASS |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 11/15/2019 | | DONE |
Josh Bogle
|
|
|
|
Plan Modification Accepted | | | 11/15/2019 | | DONE |
|
|
|
plan mod
|
Permit Ready to Issue | | | 11/15/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 11/15/2019 | | DONE |
|
|
|
|
BLD-Footing | 11/12/2019 | 11/13/2019 | 11/13/2019 | A | PART |
Mike Jordan
|
|
|
Jeff Phone #: ###-####. Addition and detached garage.
|
Issue PAID IN FULL permit | | | 10/31/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 10/30/2019 | | |
|
|
|
|
Routing Walk-In (BLD) | 10/30/2019 | 10/30/2019 | 10/30/2019 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 10/30/2019 | | 10/30/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 10/30/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 10/30/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/30/2019 | | DONE |
Josh Bogle
|
|
|
ESc yes - Energy yes
|
Permit Ready to Issue | | | 10/30/2019 | | DONE |
|
|
|
paid
met just need RP
|
Routing Walk-In (Zoning) | 10/24/2019 | 10/24/2019 | 10/24/2019 | P | PASS |
Jeff Lowe
|
|
|
|
Routing Walk-In (BLD) | 10/24/2019 | 10/24/2019 | 10/24/2019 | P | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 10/24/2019 | | 10/24/2019 | | FAIL |
Josh Bogle
|
|
|
incomplete plans, needs engineering for patio cover
|
1st review completed | | | 10/24/2019 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 10/24/2019 | | | |
|
|
|
|