BLD-Final | 2/3/2020 | 2/3/2020 | 2/3/2020 | P | PASS |
Tell Riley
|
|
|
call ahead // Russell Phone #: ###-####//corrections made//
|
DOC - Permit Finaled | 2/3/2020 | 2/3/2020 | 2/3/2020 | P | PASS |
Tell Riley
|
|
|
|
BLD-Final | 1/31/2020 | 1/31/2020 | 1/31/2020 | P | NH |
Mike Jordan
|
|
|
Russell- please go later if possible Phone #: ###-####
|
BLD-Final | 1/23/2020 | 1/27/2020 | 1/27/2020 | A | NR |
Tell Riley
|
|
|
Russel Phone #: ###-####2//need to add smoke CO at 1st floor//
|
Plan Reviewer's activity | | | 1/22/2020 | | |
Rob Patrick
|
|
|
Mechanical inspection was inadvertantly added to this. I unchecked that box as it is not needed.
|
BLD-Framing/Rough-in | 11/20/2019 | 11/20/2019 | 11/20/2019 | P | PASS |
Tell Riley
|
|
|
Russel Phone #: ###-####
|
BLD-Framing/Rough-in | 11/18/2019 | 11/19/2019 | 11/19/2019 | A | FAIL |
Dave Hannah
|
|
|
Russ Phone #: ###-#### needs plumbing and elec permits and rough ins signed off
|
Routing Walk-In (BLD) | 10/30/2019 | 10/30/2019 | 10/30/2019 | A | DONE |
Rob Patrick
|
|
|
|
Plan assigned to (RDP) | 10/30/2019 | 10/30/2019 | 10/30/2019 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/30/2019 | | DONE |
Rob Patrick
|
|
|
|
Inspection Record Card- Bld | | | 10/30/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/30/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/30/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/30/2019 | | 10/30/2019 | | PASS |
Rob Patrick
|
|
|
|
1st review completed | | | 10/30/2019 | | DONE |
Rob Patrick
|
|
|
|
Inspection Record Card- Bld | | | 10/30/2019 | | DONE |
Rob Patrick
|
|
|
|
Case Summary (BLD) | | | 10/30/2019 | | DONE |
Rob Patrick
|
|
|
|
Application received | | 10/30/2019 | | | |
|
|
|
|