BLD-Final | 6/3/2020 | 6/4/2020 | 6/4/2020 | A | DONE |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by justin reynolds
|
DOC - Permit Finaled | 6/4/2020 | 6/4/2020 | 6/4/2020 | P | PASS |
Tony Young
|
|
|
|
BLD-Blower Door Test Results | 5/29/2020 | 6/3/2020 | 6/3/2020 | P | DONE |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by justin reynolds/// 4.5
|
BLD-Final | 5/29/2020 | 5/29/2020 | 5/29/2020 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by justin reynolds// needs fire caulking.. guard rail// blower door test result
|
PubWorks Occupancy Approval | 5/28/2020 | 5/28/2020 | 5/28/2020 | | DONE |
Jason C. Taylor
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Jason Taylor ###-####.
|
BLD-Energy code compliance | 3/18/2020 | 3/18/2020 | 3/19/2020 | P | PART |
Dave Hannah
|
|
|
Justin Phone #: ###-#### ok all but for back wall still needs to do shear fix
|
BLD-Wall Bracing | 3/13/2020 | 3/13/2020 | 3/15/2020 | P | PART |
Dave Hannah
|
|
|
shear // Justin Phone #: ###-#### needs letter from engineer on hold downs front window and enstall one in back tv rm
|
BLD-Framing/Rough-in | 3/13/2020 | 3/13/2020 | 3/15/2020 | P | PART |
Dave Hannah
|
|
|
Justin Phone #: ###-#### needs fire blocking tv room ok to insulate
|
BLD-Foundation | 1/2/2020 | 1/6/2020 | 1/6/2020 | A | PART |
Tony Young
|
|
|
curt Phone #: ###-####,, work in progress,, ok
|
BLD-Footing | 12/23/2019 | 12/26/2019 | 12/26/2019 | A | PASS |
Tony Young
|
|
|
Curtis Phone #: ###-####,, rear retaining wall footing,, late am,, early pm ok/// interior footings and retaining wall footing per plan now,, ok to pour
|
BLD-Footing | 12/19/2019 | 12/23/2019 | 12/23/2019 | A | PART |
Tony Young
|
|
|
Curtis Phone #: ###-####,, main footings ok except the east retaining wall footing,, engineering changed,, need to redo per newer engineering
|
PubWorks Subgrade Approval | 12/12/2019 | 12/12/2019 | 12/12/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
OVERRIDE | | | 12/10/2019 | | |
|
|
|
|
Plan assigned to (D_S) Debbie | 11/26/2019 | 11/26/2019 | 12/10/2019 | | DONE |
Debbie Sanine
|
|
|
Bldg rev passed. Pending Hillside, Mech. & Planning approvals
|
Inspection Record Card- Bld | | | 12/10/2019 | | DONE |
|
|
|
|
Telephone call | | | 12/10/2019 | | DONE |
|
|
|
informed Kristine that this is ready and what fees are
|
Issue PAID IN FULL permit | | | 12/10/2019 | | DONE |
|
|
|
|
Routing - PLANNING | 12/9/2019 | | 12/10/2019 | | PASS |
Nicolette Womack
|
|
|
|
Routing - MECHANICAL | 12/2/2019 | | 12/10/2019 | | PASS |
Troy James
|
|
|
|
Case Summary (BLD) | | | 12/10/2019 | | DONE |
Debbie Sanine
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/10/2019 | | DONE |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 12/10/2019 | | DONE |
|
|
|
|
Routing - PUBLIC WORKS | 12/2/2019 | | 12/9/2019 | | PASS |
Candy A. Nichols
|
|
|
|
Routing PW Grading-Hillside | 12/2/2019 | | 12/9/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Plan resubmittals received | | | 12/2/2019 | | DONE |
|
|
|
Two copies of plan sheets A1.0 and SD2.0. taken to Debbie
|
Routing - PLAN CHECK | 12/2/2019 | | 12/2/2019 | | PASS |
Jenny Nelson
|
|
|
Per D_S review
|
1st review completed | | | 11/27/2019 | | FAIL |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | | | 11/27/2019 | | FAIL |
Jenny Nelson
|
|
|
Per review with D_S
|
Plan assigned to (RDP) | 11/1/2019 | 11/1/2019 | 11/26/2019 | | DEFR |
Rob Patrick
|
|
|
11/20 sfd L2 ePlan
|
Plan resubmittals received | | | 11/25/2019 | | DONE |
|
|
|
Two copies each of Truss engineering stamped and taken to plan reviewer.
|
Routing - FIRE | 11/21/2019 | | 11/22/2019 | | PASS |
Lee G Meredith
|
|
|
New SFH paper
Fire area exceeds available fire flow. Fire sprinklers required. Emailed applicant with review comments.
Justin responded to indicate fire sprinklers will be provided.
12-18-19: Ron Johnson approved an alternate flow request from Justin. Sprinklers are not required.
|
Routing - Erosion and Sediment | 11/21/2019 | | 11/21/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. RP listed. Site Preparation inspection required.
|
Routing - MECHANICAL | | | 11/21/2019 | | FAIL |
|
|
|
Emailed corrections to Idaho hvac
|
Routing - PLANNING | 11/15/2019 | | 11/19/2019 | | FAIL |
Nicolette Womack
|
|
|
Email sent to applicant, two set of grading plans submitted, which do not match.
|
Plan resubmittals received | | | 11/18/2019 | | DONE |
|
|
|
Two copies each of Structural Calculations, Site Suitability Letter and Foundation Details SD1.0 stamped and taken to plan reviewer.
|
Routing - PUBLIC WORKS | 11/1/2019 | | 11/15/2019 | | FAIL |
Candy A. Nichols
|
|
|
SEE HILLSIDE FAILED
|
Routing PW Grading-Hillside | 11/4/2019 | | 11/15/2019 | | FAIL |
Melissa Jannusch
|
|
|
E-mail send to applicant
|
Route to Impact Fee Review | 11/1/2019 | 11/4/2019 | 11/4/2019 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | | | 11/4/2019 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 11/1/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/1/2019 | | DONE |
|
|
|
|
Intake Approval | | | 11/1/2019 | | PASS |
|
|
|
|
Application received | | 11/1/2019 | | | |
|
|
|
|