CHANGE STATUS TO (ISS) | | | 8/6/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 8/3/2020 | | |
|
|
|
|
OVERRIDE | | | 8/3/2020 | | |
|
|
|
|
OVERRIDE | | | 8/3/2020 | | |
|
|
|
|
OVERRIDE | | | 8/3/2020 | | |
|
|
|
|
Plan assigned to (JG) | 7/17/2020 | 7/17/2020 | 8/3/2020 | | PASS |
Javier Guzman
|
|
|
08/05 plan mod Ustick 12-Plex ePlan
|
Routing Off Site - STRUCTURAL | 7/23/2020 | | 8/3/2020 | | PASS |
Javier Guzman
|
|
|
Signed off in ePlan by kpff engineers
|
Override - Parcel Holds | | | 8/3/2020 | | |
|
|
|
|
Permit Ready to Issue | | | 8/3/2020 | | DONE |
|
|
|
PLAN MOD
|
BLD-Foundation | 7/27/2020 | 7/27/2020 | 7/27/2020 | P | PEND |
Tell Riley
|
|
|
Sergio - Foundation walls are outside of the modified footing area. */Screened*/ Phone #: ###-####//special inspection report, for post installed anchors, verified by pull test, was in compliance with design engineer--also engineer called me and verified// //plans show hair pins at corners with hold down anchor bolts--engineer called and wants detail deleted from plans--advised to submit with current plan mod under review for footings// //let GC know about my concerns with elevations, we discussed elevtations, wall height seems extremely high, wall currently 2' 8" above footing, plans show a 2' wall on structurals, will need to meet accessiblity requirements at finals// //if walls are poured prior to acceptance of plan modification for footing changes and wall details, cantractor is pouring at own risk// rebar appears to be installed per the current plans, less the hair pins on corners//
|
Routing - PLAN CHECK | 7/23/2020 | | 7/23/2020 | | PASS |
Javier Guzman
|
|
|
|
Plan Modification Accepted | | | 7/17/2020 | | DONE |
|
|
|
S2.0Footings revised to reflect width and depth requirements by Simpson manufacturer for hold downs. Interior partition walls widened to increase factor of saftey.
S3.0 Footing embeomeiut of foundation anchor bolts decreased per Simpson.
S6.0 Note added to make girdertruss design requirements clear fortruss mfg
|
BLD-Footing | 7/15/2020 | 7/15/2020 | 7/15/2020 | P | PART |
Tell Riley
|
|
|
Serigo *screened* Phone #: ###-####//SOUTH WALL FOOTINGS CLOUDED ON PLANS DATED 6/22/2020 THAT ARE NOT APPROVED PLANS, CONTRACTOR POURING AT OWN RISK UNTIL PLAN MODIFICATION IS SUBMITTED AND APPROVED//REBAR IN THIS LOCATION APPEARS TO BE INSTALLED PER THESE PLANS//areas outside modified footings are ok per the APPROVED plans//advised contractor PLAN MODIFICATION MUST BE APPROVED PRIOR TO GOING VERTICAL WITH FRAMING//maintain all clearances on rebar//
|
BLD-Footing | 7/13/2020 | 7/13/2020 | 7/13/2020 | P | NR |
Tell Riley
|
|
|
Call ahead Sergio - Phone #: ###-####//need to submit to plan review for modifications to structural plans for footing sizes, depths and rebar//also appears to be changes with the roof trusses per the new structural drawings onsite//rebar clearances need to be adjusted/cut away from forms and elevated 3" above grade//
|
BLD-Footing | 7/6/2020 | 7/7/2020 | 7/7/2020 | A | FAIL |
Tell Riley
|
|
|
Sergio Phone #: ###-####//CN posted//need small documents//special inspections reqiured//rebar does not meet installation requirements on plans//site does not meet minimum ESC requirements//need all property lines identified and/or marked//
|
Issue PAID IN FULL permit | | | 5/29/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 5/29/2020 | | DONE |
|
|
|
|
Telephone call | | | 5/28/2020 | | DONE |
|
|
|
sent email about expired permit
|
OVERRIDE | | | 5/21/2020 | | |
|
|
|
|
Plan assigned to (JG) | 12/9/2019 | 12/17/2019 | 5/21/2020 | | PASS |
Javier Guzman
|
|
|
05/27 4th rev 506 Ustick 12-plex Bldg 1 ePlan, pend pw sl
|
Routing - PLAN CHECK | 5/21/2020 | | 5/21/2020 | | PASS |
Javier Guzman
|
|
|
|
Routing PW Street Lights | 5/21/2020 | | 5/21/2020 | | PASS |
Tom Marshall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/21/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 5/21/2020 | | DONE |
|
|
|
ALL MET
Robert Campbell
ACHD
metGC Form
metRevised Cert of Value
metRP
|
Routing - PLAN CHECK | 5/11/2020 | | 5/20/2020 | | PASS |
Javier Guzman
|
|
|
|
Routing - FIRE | 5/11/2020 | 5/11/2020 | 5/13/2020 | | PASS |
Greg Ruxton
|
|
|
Attached comments to case.
|
Routing PW Street Lights | 5/11/2020 | | 5/11/2020 | | FAIL |
Tom Marshall
|
|
|
|
Routing - PLAN CHECK | 4/13/2020 | | 4/28/2020 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 4/13/2020 | | 4/24/2020 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by kpff engineer
|
Routing - Design Review | 4/13/2020 | | 4/21/2020 | | PASS |
Josh Wilson
|
|
|
riser room now on west eaxterior wall
|
Routing - FIRE | 4/13/2020 | 4/13/2020 | 4/15/2020 | | FAIL |
Greg Ruxton
|
|
|
Attached comments to case and emailed architiect.
|
Routing PW Drainage | 4/13/2020 | | 4/15/2020 | | PASS |
Jason C. Taylor
|
|
|
|
Routing PW Street Lights | 4/13/2020 | | 4/14/2020 | | FAIL |
Tom Marshall
|
|
|
|
Routing - FIRE | 12/9/2019 | 12/17/2019 | 2/20/2020 | | FAIL |
Greg Ruxton
|
|
|
Attached comments to case and emailed architect.
|
Route to Impact Fee Review | 2/13/2020 | 2/16/2020 | 2/14/2020 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 12/17/2019 | | 2/13/2020 | | FAIL |
Javier Guzman
|
|
|
|
1st review completed | | | 2/13/2020 | | FAIL |
Javier Guzman
|
|
|
|
Routing Off Site - STRUCTURAL | 12/17/2019 | | 1/31/2020 | | FAIL |
Michael Hanson
|
|
|
Per corrections required in ePlan KPFF
|
Routing - MECHANICAL | 1/7/2020 | | 1/7/2020 | | PASS |
Troy James
|
|
|
One manual j report for each level.
|
Routing - PLANNING | 12/17/2019 | | 12/31/2019 | | PASS |
Kevin Holmes
|
|
|
Passed per approved PUD19-00010
|
Routing - PLUMBING | 12/17/2019 | | 12/30/2019 | | PASS |
Dan Ediger
|
|
|
Per plans and ISPC
|
Routing PW Drainage | 12/18/2019 | | 12/23/2019 | | FAIL |
|
|
|
need geotech
|
Routing - Design Review | 12/17/2019 | | 12/23/2019 | | PASS |
Josh Wilson
|
|
|
|
Routing - MECHANICAL | 12/17/2019 | | 12/20/2019 | | FAIL |
Troy James
|
|
|
Notified the applicant to provide ACCA approved Manual j, d and s.
|
Routing PW Street Lights | 12/18/2019 | | 12/20/2019 | | FAIL |
Tom Marshall
|
|
|
See review notes in ePlan. JCT
|
Routing PW Solid Waste | 12/18/2019 | | 12/20/2019 | | PASS |
Evan Carpenter
|
|
|
|
Routing - Addressing | 12/17/2019 | | 12/18/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/17/2019 | | 12/18/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 12/17/2019 | | 12/18/2019 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Site preparation inspection is REQUIRED. Need to list RP prior to permit issuance.
|
Intake Approval | | | 12/9/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 11/29/2019 | | FAIL |
Javier Guzman
|
|
|
For prescreen review provide and upload the following:
• Prescreen resubmittal request not addressed 11/29/2019. Per checklist provide site specific fire flow at hydrants letter from Suez Water or other public water provider
• the uploaded form 310 is incomplete, provide missing information on the cover sheet such as design professional info section and the owner signature or the design professional signature.
• Prescreen resubmittal request not addressed 11/29/2019. Per checklist provide a completed and notarized Drainage System Operation & Maintenance Plan Agreement (appendix J from Public Works Stormwater Manual) form found at https://www.cityofboise.org/departments/public-works/stormwater-and-drainage-control/stormwater-and-drainage-control-documents/
|
Intake Approval | | | 11/4/2019 | | FAIL |
Javier Guzman
|
|
|
For prescreen review provide and upload the following:
• Per checklist provide a signed and approved by PDS Subdivision Staff Verification of Legal Lot or Parcel form
• Per checklist provide site specific fire flow at hydrants letter from Suez Water or other public water provider
• Provide a completed form 310 that is also stamped, signed and dated by an Idaho licensed engineer. Form 310 can be found at https://www.cityofboise.org/media/3760/final310_special_inspections.pdf
• Per checklist provide Erosion & Sediment Control (ESC) Narrative - Narrative must be designed for the specific project and be prepared and signed by a plan designer certified by Boise City.
• Per checklist provide a completed and notarized Drainage System Operation & Maintenance Plan Agreement (appendix J from Public Works Stormwater Manual)
• Per checklist provide a Site Plan Clearly Designating “Fire Department Access Roadways” - Including connecting public streets.
• Per checklist provide a site plan clearly showing new or existing Hydrants
• Per checklist provide Erosion & Sediment Control (ESC) Plans (C2.0 is not an ESC plan)
• FYI, When looking at plan sheet A561 for quick prescreen review noticed the top stair nosing profile was not uniform with other stair profile
• Per ePlan submittal standards the reserve the bottom right corner on the drawing plans for the City electronic stamps. Leave a blank 4” x 2” space located 3” off the right sheet edge to allow for the title block on plan sheet A113, A311, A321 and A561 - see ePlan standards at https://www.cityofboise.org/media/7025/electronic_submittal_standards.pdf
• Per checklist provide and show location of the fire extinguishers. (if you are referring to a triangle shape/symbol at the stairwell place the triangle symbol at the fire extinguisher notes as well) plan sheet G003
• Provide missing electrical engineers stamp on plan sheet E5
|
Application received | | | 11/1/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 1 2019 4:18PM
|
Routing PW Sewer Design | 12/18/2019 | | | | PASS |
|
|
|
Connecting to existing sewer stub
|