BLD-Energy code compliance | 4/1/2020 | 4/2/2020 | 4/2/2020 | A | PASS |
Tell Riley
|
|
|
Insulation inspection R-38 closed cell spray in ceiling, bat walls, floor bat done with flooring R-30 Home owner home access site through gate on left of house enter sliding door. room contained away from house members with plastic walls. Phone #: ###-#### Inspection requested via web by Tara Vreeland
|
BLD-Framing/Rough-in | 3/30/2020 | 3/31/2020 | 3/31/2020 | A | PASS |
Brandon Shaw
|
|
|
Client is home. Access project through gate left side of house into back yard and in sliding door. Blocked off from resat of house inside. Phone #: ###-#### Inspection requested via web by Tara Vreeland
|
BLD-Wall Bracing | 3/20/2020 | 3/23/2020 | 3/23/2020 | A | PASS |
Dave Hannah
|
|
|
Sheer inspection, homeowner will be home or we can meet inspector if given a 30 minute notice. ###-#### Tara
Note: note on sill plate about additional plate on top of visible sill plate set back 1/2" I have picture if needed. Phone #: ###-#### Inspection requested via web by Tara Vreeland
|
BLD-Footing | 1/3/2020 | 1/3/2020 | 1/3/2020 | P | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
Routing Walk-In (BLD) | 12/9/2019 | 12/9/2019 | 12/9/2019 | A | DONE |
Josh Bogle
|
|
|
|
Plan assigned to (JAB) Josh | 11/5/2019 | 11/5/2019 | 12/9/2019 | | PASS |
Josh Bogle
|
|
|
11/11 addition, ePlan - 1st done
|
Routing - PLAN CHECK | 12/9/2019 | | 12/9/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 12/9/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 12/9/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/9/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy yes
|
Routing - PLANNING | 12/9/2019 | | 12/9/2019 | | PASS |
Michaella Owens
|
|
|
|
Permit Ready to Issue | | | 12/9/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/9/2019 | | DONE |
|
|
|
|
Plan Reviewer's activity | | | 12/6/2019 | | PASS |
|
|
|
Passed, previous conditions still apply- window and doors must not be vinyl.
|
Plan Reviewer's activity | | | 12/5/2019 | | DONE |
Josh Bogle
|
|
|
accepted resubmittals and routed
|
Routing - PLAN CHECK | 11/26/2019 | | 11/26/2019 | | FAIL |
Josh Bogle
|
|
|
see notes in ePlan, also e-mail to Tara & Paul
|
Plan Reviewer's activity | | | 11/25/2019 | | FAIL |
|
|
|
Needs resubmit after 10 day appeal period (can resubmit on December 2, 2019).
|
Plan Reviewer's activity | | | 11/22/2019 | | DONE |
Josh Bogle
|
|
|
accepted resubmittal
|
Plan Reviewer's activity | | | 11/15/2019 | | DONE |
Josh Bogle
|
|
|
rejected resubmittal
|
Routing - PLAN CHECK | 11/12/2019 | | 11/12/2019 | | PASS |
Josh Bogle
|
|
|
no review pending Planning approval
|
Plan Reviewer's activity | | | 11/8/2019 | | DONE |
Josh Bogle
|
|
|
accepted and routed resubmittal
|
Routing - PLAN CHECK | 11/5/2019 | | 11/7/2019 | | FAIL |
Josh Bogle
|
|
|
plans not readable
|
1st review completed | | | 11/7/2019 | | DONE |
Josh Bogle
|
|
|
|
Plan Reviewer's activity | | | 11/7/2019 | | DONE |
Josh Bogle
|
|
|
reject resubmittal - plan pages not uploaded separately
|
Application received | | | 11/5/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 5 2019 12:34PM
|
Intake Approval | | | 11/5/2019 | | FAIL |
|
|
|
plans need to be uploaded indivdually
|
Plans ACCEPTED BY PLAN TECH | | | 11/5/2019 | | DONE |
|
|
|
|
Intake Approval | | | 11/5/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/5/2019 | | DONE |
|
|
|
|
Routing - PLANNING | 11/5/2019 | | 11/5/2019 | | FAIL |
Sue Cummings
|
|
|
This property is in an Historic District. A Certificate of Appropriateness is required prior to issuance of a building permit
|