BLD-Foundation | 8/10/2020 | 8/11/2020 | 8/11/2020 | A | PASS |
Mike Jordan
|
|
|
Victor *screened Phone #: ###-####
|
BLD-Footing | 8/6/2020 | 8/7/2020 | 8/7/2020 | A | PASS |
Mike Jordan
|
|
|
Brandon or Manny ###-#### *screened* Phone #: ###-####
|
BLD-Footing | 8/3/2020 | 8/4/2020 | 8/4/2020 | A | FAIL |
Mike Jordan
|
|
|
Victor *screened* Phone #: ###-####. Needs to provide updated site plan approved by planning.
|
Telephone call | | | 7/6/2020 | | DONE |
|
|
|
emailed brandon@triconproperties.com about ACHD
|
Issue PAID IN FULL permit | | | 7/6/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/6/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 6/23/2020 | | |
|
|
|
|
Permit Ready to Issue | | | 6/23/2020 | | DONE |
|
|
|
NEED (brandon@triconproperties.com)
ACHD
Met
RP
GC
Revised Certificate of Value
|
Routing PW Drainage | 6/22/2020 | | 6/22/2020 | | PASS |
Brian Murphy
|
|
|
Approved in ePlan by BGM
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/22/2020 | | DONE |
Michael Hanson
|
|
|
|
Plan assigned to (M_H) | 11/29/2019 | | 6/22/2020 | | DONE |
Michael Hanson
|
|
|
1st review completed - 01/07 #502 L3 ePlan - Encore Dealership Building
|
Routing - PLANNING | 2/11/2020 | | 6/22/2020 | | PASS |
Leon Letson
|
|
|
Passed in ePlan by Leon Letson.
|
Routing Off Site - STRUCTURAL | 5/21/2020 | | 6/22/2020 | | PASS |
Michael Hanson
|
|
|
Jan W. @ Stapley engineering
|
Routing PW Drainage | 6/8/2020 | | 6/8/2020 | | FAIL |
Brian Murphy
|
|
|
NEED HYDRO CARBON FILTER FOR AUTO SHOP
|
Routing PW Street Lights | 2/11/2020 | | 5/22/2020 | | PASS |
Tom Marshall
|
|
|
|
Routing Off Site - STRUCTURAL | 4/9/2020 | | 4/9/2020 | | FAIL |
Michael Hanson
|
|
|
Stapley engineering
|
Routing Off Site - STRUCTURAL | 3/31/2020 | | 4/2/2020 | | FAIL |
Michael Hanson
|
|
|
Stapley Engineering
|
Routing PW Drainage | 2/11/2020 | | 3/6/2020 | | FAIL |
Jason C. Taylor
|
|
|
need paver area on plan
|
Routing PW Environmental | 2/11/2020 | | 2/18/2020 | | FAIL |
Rick Christenson
|
|
|
Applicant must submit plumbing plans for the service/detail shop. Suitable and adequate sand and oil abatement equipment must be provided.
|
Routing Off Site - STRUCTURAL | 2/11/2020 | | 2/11/2020 | | FAIL |
Michael Hanson
|
|
|
See structural review document located in agency comments
|
Routing - Design Review | 2/10/2020 | | 2/10/2020 | | PASS |
Josh Wilson
|
|
|
|
Route to Impact Fee Review | 1/7/2020 | 1/10/2020 | 1/8/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 1/7/2020 | | FAIL |
Michael Hanson
|
|
|
|
Routing Off Site - STRUCTURAL | 11/29/2019 | | 1/7/2020 | | FAIL |
Michael Hanson
|
|
|
Stapley Engineering
|
Routing - PLAN CHECK | 11/29/2019 | | 1/7/2020 | | FAIL |
Michael Hanson
|
|
|
See building plan review report for corrections required.
|
Routing - FIRE | 11/29/2019 | 11/29/2019 | 1/6/2020 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - MECHANICAL | 12/31/2019 | | 12/31/2019 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 11/29/2019 | | 12/13/2019 | | FAIL |
Troy James
|
|
|
Emailed correction to engineer and applicant.
|
Routing - PUBLIC WORKS | 11/29/2019 | | 12/6/2019 | | PASS |
Morgan Webb
|
|
|
|
Routing - Design Review | 11/29/2019 | | 12/5/2019 | | FAIL |
Josh Wilson
|
|
|
•Provide a minimum of four Class I trees (due to overhead power restrictions) along Fairview Avenue.
•Provide a minimum of three Class II trees along Sunrise Manor Way.
•Provide a Class II tree in each planter serving a single row of parking.
•Provide two Class II trees in each planting serving a double row of parking.
•Provide four Class II trees along the west property line adjacent to the automobile sales lot.
|
Routing PW Environmental | 12/3/2019 | | 12/5/2019 | | FAIL |
Rick Christenson
|
|
|
Applicant must submit plumbing plans for the service/detail shop. Suitable and adequate sand and oil abatement equipment must be provided.
|
Routing PW Sewer Design | 12/3/2019 | | 12/4/2019 | | PASS |
DeAnn Brown
|
|
|
Connecting to existing sewer service.
|
Routing PW Solid Waste | 12/3/2019 | | 12/4/2019 | | PASS |
Evan Carpenter
|
|
|
Approved for commercial cart service.
|
Routing - Addressing | 11/29/2019 | | 12/4/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - Erosion and Sediment | 11/29/2019 | | 12/3/2019 | | PASS |
Michael Zawacki
|
|
|
RP needed.
Site prep inspection required.
|
Routing PW Drainage | 12/3/2019 | | 12/3/2019 | | FAIL |
Jason C. Taylor
|
|
|
See changemarks in ePlan.
|
Routing PW Street Lights | 12/3/2019 | | 12/3/2019 | | FAIL |
Tom Marshall
|
|
|
|
Routing - PLUMBING | 11/29/2019 | | 12/2/2019 | | PASS |
Daryl Spivey
|
|
|
Provide DCVA on water service as required and per plan and ISPC.
|
Routing - PLANNING | 11/29/2019 | | 12/2/2019 | | FAIL |
Leon Letson
|
|
|
Items required per PUD16-00039. Applicant has been notified.
|
Intake Approval | | | 11/27/2019 | | PASS |
Brian McGowan
|
|
|
Prescreen approved by BJM
|
Plan Reviewer's activity | | | 11/26/2019 | | |
Brian McGowan
|
|
|
Changes were made to the exterior since the original approval. Josh Wilson said it was ok to send it through Prescreen, he will review it in process. Several of the Civil Sheets do not show this alteration. They were previously approved and are said to not have any significant change to the drainage design.
|
Intake Approval | | | 11/12/2019 | | FAIL |
Brian McGowan
|
|
|
Please provide or address the following for your Prescreen to be approved;
1. A Soils Report was provided but it is not stamped and signed by the Engineer.
2. The ESC Plan is not stamped and signed by the engineer.
3. Fire Hydrants are not called out on Sheet A00 as noted in the Submittal Checklist.
4. Please list the currently adopted Codes for the City of Boise on the Title Sheet and verify that the provided drawings and documents are designed to these Codes. (A20 is specifying 2012 IBC)
5. Sheet A00 does not provide a Landscape Plan, does not show a Trash Enclosure, as noted in the Submittal Checklist.
6. No ESC Plan was provided as noted in the Submittal Checklist, but an ESC Narrative was provided.
7. The Building outline on Sheet C10, Sheet C1 does not match the proposed building profile. C10, C1 already has a City Approval Stamp.
8. A21 does not show portable Fire extinguisher locations.
9. No defered Items are listed on A00 as noted in the Submittal Checklist.
Several Drawings have the City of Boise Approval Stamp already on them. If these are from a previous permit that has been issued please provide that BLD # so further research can be done.
There has been a Code change since these drawings were stamped. They may need to be resubmitted and reviewed to the current Code depending on the situation.
|
Intake Approval | | | 11/7/2019 | | FAIL |
Brian McGowan
|
|
|
Please address or provide the following for your Prescreen to be approved;
1. The Submittal Checklist must be filled out and the required documents provided.
2. Planning Approvals, Structural calculations, Grading Plans, Erosion....etc. documents are required.
|
Application received | | | 11/6/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 6 2019 7:25PM
|