BLD-Energy code compliance | 8/4/2020 | 8/4/2020 | 8/5/2020 | P | PART |
Dave Hannah
|
|
|
Joe *screened* Phone #: ###-#### 2nd and third floor mec spaces
|
BLD-Conference | 6/4/2020 | 6/5/2020 | 6/5/2020 | A | PASS |
Dave Hannah
|
|
|
joe *screened* Phone #: ###-####
|
Issue PAID IN FULL permit | | | 4/15/2020 | | DONE |
|
|
|
|
Print Occupancy Form | | | 4/15/2020 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 2/5/2020 | 2/5/2020 | 4/13/2020 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - 2nd Comp - 520 3rd & Myrtle Parking Garage Build-out
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/13/2020 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/13/2020 | | DONE |
|
|
|
ALL MET
Met
Rev Values
RP
GC
|
Routing - PLAN CHECK | 3/26/2020 | | 4/3/2020 | | PASS |
Julie Romig
|
|
|
|
Routing PW Street Lights | 3/26/2020 | | 3/26/2020 | | PASS |
Tom Marshall
|
|
|
|
Routing - MECHANICAL | 3/26/2020 | | 3/26/2020 | | PASS |
Troy James
|
|
|
|
Routing PW Flood Plain | 3/26/2020 | | 3/26/2020 | | PASS |
Jason C. Taylor
|
|
|
A portion of the subject property is within the regulatory floodplain. This project must comply with the Boise Floodplain Ordinance (B.C.C. 11-08). If you have any questions, please call Jason Taylor at ###-####.
Elevation Certificate will be required prior to occupancy. Jason Taylor
|
Route to Impact Fee Review | 3/18/2020 | 3/21/2020 | 3/23/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 2/5/2020 | 2/5/2020 | 3/18/2020 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 3/18/2020 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 2/5/2020 | | 3/18/2020 | | FAIL |
Julie Romig
|
|
|
|
Routing PW Drainage | 2/10/2020 | | 2/20/2020 | | PASS |
Brian Murphy
|
|
|
|
Routing PW Environmental | 2/10/2020 | | 2/18/2020 | | PASS |
Rick Christenson
|
|
|
Approved for retail shell only. Any restaurant/food service tenants will need suitable and adequate grease abatement. Tenants will need to get approval from Pretreatment.
|
Routing - MECHANICAL | 2/5/2020 | | 2/18/2020 | | FAIL |
Troy James
|
|
|
Emailed correction to applicant.
|
Routing - PLUMBING | 2/5/2020 | | 2/11/2020 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 2/5/2020 | | 2/11/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 2/5/2020 | | 2/11/2020 | | PASS |
Candy A. Nichols
|
|
|
|
Routing PW Solid Waste | 2/10/2020 | | 2/10/2020 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Sewer Design | 2/10/2020 | | 2/10/2020 | | PASS |
DeAnn Brown
|
|
|
|
Routing PW Street Lights | 2/10/2020 | | 2/10/2020 | | FAIL |
Tom Marshall
|
|
|
Need a streetlight plan.
|
Routing - PLANNING | 2/5/2020 | | 2/10/2020 | | PASS |
Cody Riddle
|
|
|
|
Routing - Design Review | 2/5/2020 | | 2/10/2020 | | PASS |
Josh Wilson
|
|
|
|
Intake Approval | | | 2/5/2020 | | PASS |
Julie Romig
|
|
|
|
Application received | | | 11/7/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 7 2019 1:38PM
|