Information based on query as of Wednesday, August 14, 2024.
Permit Information
Permit NumberBLD19-04474
StatusIssued
Name EKC INC
Site Address 2223 W FAIRVIEW AVE
Project NameBoise Police-Downtown Station
Customer Number 
ePlanReviewYes
Description
(BOISE POLICE DEPARTMENT – DOWNTOWN STATION) (DRH19-00291) (CVA19-00029) (GREEN BUILDING REMODEL/RENOVATION-2012 IGCC) (5-27-20 PLAN MODIFICATION TO REVISE THE BIKE RAMP SERVING THE BASEMENT AND THE ADJACENT HANDRAIL THAT IS INTENDED TO SERVE THE STAIRWAY PER A CODE MODIFICATION APPROVED BY JASON BLAIS, BUILDING OFFICIAL, AND TO REMOVE THE HOOD FIRE SUPPRESSION SYSTEM ABOVE THE BREAKROOM RANGE. THE REACH DISTANCE OVER THE RAMP WAS APPROVED BY THE BUILDING OFFICIAL TO BE A MAXIMUM OF 16 INCHES FROM THE STAIRWAY TREADS TO THE CENTER OF THE HANDRAIL.) This building will have a fire sprinkler system. Interior nonstructural demolition work was done under permit BLD20-00421. To remodel and enlarge an existing building to function as a police station. This building is expected to comply with the 2015 International Green Construction Code. After the addition, the total building area will be about 5,455 square feet (about 1,384 square feet basement, about 2,837 square feet within the building thermal envelope on the 1st story, and about 1,234 square feet within the unconditioned area below the roof on the 1st story). Basement work includes a new exterior concrete retaining wall, a new covered exterior concrete stairway with an adjacent concrete bike ramp, a wider exterior door at the bottom of the exterior stairway, interior nonbearing walls, a new interior stairway with steel stringers and concrete filled pan treads, interior doors, and a laundry room (dryers will have booster fans). The basement will be used for bicycle maintenance, laundry, storage, and mechanical. Work on the 1st story includes concrete footings, concrete foundations, concrete slabs on grade, steel columns with steel base plates and anchors, a masonry fence to enclose a new covered patio, decorative metal wall panels, steel gates, metal ceilings above the patio, steel beams, a new opening in an existing masonry exterior wall with a new steel header above, exterior masonry wall infills, steel exterior siding, sun shade awnings, repair of the underside of the concrete slab between the basement and the 1st story, steel stud exterior walls at the building addition, steel stud roof parapets, steel roof joists, plywood roof sheathing, rigid insulation on top of the roof deck, a membrane roof covering, gypsum board ceilings, suspended acoustical ceilings, interior nonbearing walls, a single-user toilet room accessible to the disabled, three toilet/shower/locker rooms with two accessible to the disabled, interior “high” and “low” drinking fountains, exterior “high” and “low” drinking fountains, interior doors, exterior doors, exterior windows, concrete patches for slab on grade floors where trenches will be cut to accommodate underslab plumbing, millwork, and finishes. Special Inspection is required for soils, concrete, masonry, steel (including welding and bolting), and anchors post-installed in hardened concrete. Fence work around the secured vehicular parking area includes concrete footings, concrete foundations, tube steel columns, steel wall panels, steel gates with access control, and an automatic vehicle pivot gate with sensors. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Energy code compliance8/5/20208/6/20208/6/2020APART
DetailsDave Hannah
screened // Don Phone #: ###-#### ok to cover walls
BLD-Framing/Rough-in7/13/20207/15/20207/15/2020APASS
DetailsDave Hannah
Joe - * superintendent is out with COVID* *new super is present and all employees tested negative for COVID* *everyone will wear masks* Phone #: ###-####
BLD-Grading Inspection7/13/20207/13/20207/13/2020PDEFR
DetailsJim Storey
Call Joe Dalrymple with any questions. We have some storm pipe that need to be inspected prior to cover. Phone #: ###-#### Inspection requested via web by Brandon McCurdy pw
BLD-Framing/Rough-in6/29/20206/29/20206/29/2020PPART
DetailsDave Hannah
screened // Dale Phone #: ###-#### ok to deck new section of roof
CHANGE STATUS TO (ISS)  6/18/2020 DONE
OVERRIDE  5/27/2020  
Plan assigned to (CJW)5/7/20205/7/20205/27/2020 PASS
DetailsCarl Westfall
plan mod - downtown police (routed to staff)
Plan Reviewer's activity  5/27/2020 PASS
Plan mod review approved
Permit Ready to Issue  5/27/2020 DONE
plan mod approved
Routing - FIRE5/19/20205/19/20205/26/2020 PASS
DetailsErika Akin
Plan Mod to remove fire suppression system over domestic range. Per policy dated 11-26-19, domestic range hood suppression not required in office breakrooms or stations. Letter provided from Boise Police that no grease laden vapors will be occurring and included in small docs. Inspector to field verify compliance with policy.
Routing - PLUMBING5/19/2020 5/20/2020 PASS
DetailsDaryl Spivey
Changed shower from version 1 to version 2. See redline remarks on P2.2
Routing - PLAN CHECK5/13/2020 5/19/2020 PASS
DetailsCarl Westfall
Revised drawings were received by Email. Drawings routed.
Routing - PLAN CHECK5/11/2020 5/13/2020 PASS
DetailsCarl Westfall
Workflow received May 11. Plan intake review approved May 13 but some revised sheets required.
Plan Modification Accepted  5/7/2020 DONE
Modification No.1: Revision to the west exterior stair accessing the basement, revision includes modificat
to the utility bike ramp width and adjustment to the stair handrail.
Modification No. 2: Revision to the breakroom range hood, removing the fire supression system.
Modifications have been previously discussed with Carl Westfall and Jason Blais.
Issue & PRINT to be Invoiced  3/5/2020 DONE
email permits to be signed to cheralee@ekcconstruction.com
Print Occupancy Form  3/5/2020 DONE
Telephone call  3/5/2020 DONE
email permits to be signed to cheralee@ekcconstruction.com EPLAN needs to be release
OVERRIDE  3/4/2020  
Plan assigned to (CJW)11/18/201912/11/20193/4/2020 PASS
DetailsCarl Westfall
(1st done) 12/04/19 (L-3 - 15 days) (eplan - 110 sheets) Boise Police Downtown Station
PLANS/APPL TAKEN TO FRONT DESK  3/4/2020 DONE
Permit Ready to Issue  3/4/2020 DONE
MET
Need
ACHD

MET-
RP
Revised Cert of Value (this will be a JV, let Tisha know when fees are added)
met -GC Form
Routing Off Site - STRUCTURAL2/24/2020 2/28/2020 PASS
DetailsCarl Westfall
Chris Merril (Stapley)
Routing PW Street Lights2/24/2020 2/25/2020 PASS
DetailsTom Marshall
Routing - PLAN CHECK2/20/2020 2/24/2020 PASS
DetailsCarl Westfall
Plan resubmittals received  2/20/2020 DONE
Routing Off Site - STRUCTURAL2/5/2020 2/12/2020 FAIL
DetailsCarl Westfall
Chris Merril (Stapley)
Plan resubmittals requested  2/12/2020 DONE
Routing - PLAN CHECK2/5/2020 2/10/2020 PASS
DetailsCarl Westfall
Uploaded drawings for the Architect that resolved the last remaining item.
Routing PW Street Lights2/6/2020 2/7/2020 FAIL
DetailsTom Marshall
Plan resubmittals received  2/5/2020 DONE
Route to Impact Fee Review1/9/20201/12/20201/10/2020 PASS
DetailsTravis P Black
Review requested for Commercial Permit
Plan resubmittals requested  1/9/2020 DONE
The Plans Examiner responsible for routing this project was sick from December 31 for 8 days. Due to his sickness, this is the 1st it could be routed back to the applicant. He also needed to wait until Fire completed their task in ePlanReview.
1st review completed  12/31/2019 DONE
Routing - FIRE11/18/201911/18/201912/30/2019 PASS
DetailsErika Akin
Attached comments to case
Plan resubmittals requested  12/18/2019 DONE
IBC plan review report Emailed to the applicant and the Architect
Routing - PLAN CHECK11/18/2019 12/18/2019 FAIL
DetailsCarl Westfall
Revised drawings required
Routing - PLANNING11/18/2019 12/18/2019 PASS
DetailsNicolette Womack
Routing Off Site - STRUCTURAL11/18/2019 12/4/2019 FAIL
DetailsCarl Westfall
Chris Merril (Stapley)
Routing - Design Review11/18/2019 11/22/2019 PASS
DetailsJosh Wilson
Routing - MECHANICAL11/18/2019 11/21/2019 PASS
DetailsTroy James
The building is designed to meet the IGCC
Routing PW Drainage11/19/2019 11/21/2019 PASS
DetailsBrian Murphy
Routing - PUBLIC WORKS11/18/2019 11/19/2019 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment11/18/2019 11/18/2019 PASS
DetailsMichael Zawacki
RP needed
Routing - PLUMBING11/18/2019 11/18/2019 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Routing - Addressing11/18/2019 11/18/2019 PASS
DetailsDoug Chausow
Intake Approval  11/14/2019 PASS
DetailsMichael Hanson
Application received  11/8/2019 DONE
Application submitted via PDS Online on Nov 8 2019 11:09PM