BLD-Conference | 4/7/2020 | 4/8/2020 | 4/8/2020 | A | PASS |
Tony Young
|
|
|
?s on carport,, head room about 6' or so on lower section ok per exception in code.. needed for roof drainage
|
BLD-Concrete | 3/18/2020 | 3/18/2020 | 3/18/2020 | P | PART |
Tell Riley
|
|
|
JB Phone #: ###-####//need to maintain clearance on rebar, will need tocut bar for clearances//hole depth and width ok now//
|
BLD-Footing | 3/16/2020 | 3/17/2020 | 3/17/2020 | P | NR |
Tell Riley
|
|
|
BJ Phone #: ###-####//need to meet engineering//
|
Routing Walk-In (Zoning) | | 11/12/2019 | 11/12/2019 | A | PASS |
|
|
|
|
Routing Walk-In (BLD) | 11/12/2019 | 11/12/2019 | 11/12/2019 | A | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 11/12/2019 | | 11/12/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 11/12/2019 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 11/12/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 11/12/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/12/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 11/12/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/12/2019 | | DONE |
|
|
|
|
Application received | | 11/12/2019 | | | |
|
|
|
|