PubWorks Occupancy Approval | 8/13/2020 | 8/13/2020 | 8/13/2020 | | DONE |
Jason C. Taylor
|
|
|
A letter from the applicant’s civil engineer/landscape architect indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department Jason Taylor ###-####.
|
Override - Parcel Holds | | | 8/13/2020 | | |
|
|
|
|
Routing - PLANNING | 8/5/2020 | | 8/5/2020 | | PASS |
Nicolette Womack
|
|
|
Planning allowed the driveway modification included as exhibit to reduce pavement only to access the two car garage.
|
BLD-Conference | 7/30/2020 | 7/31/2020 | 7/31/2020 | A | PART |
Tony Young
|
|
|
Josh Phone #: ###-####// walk through// needs hard surface drive, trades, hillside approval from public works,, fire caulking,, verify underfloor vapor barrior,, address,, landings,, etc
|
BLD-Energy code compliance | 4/3/2020 | 4/6/2020 | 4/6/2020 | A | PASS |
Tell Riley
|
|
|
Derek- ''has been screened**404app** Phone #: ###-####//ok, need to add vapor barrier over exposed insulation, let him know//
|
BLD-Energy code compliance | 4/2/2020 | 4/3/2020 | 4/3/2020 | A | NR |
Tony Young
|
|
|
Derek- ''has been screened**404app** Phone #: ###-####
|
BLD-Framing/Rough-in | 3/27/2020 | 3/30/2020 | 3/30/2020 | A | PASS |
Dave Hannah
|
|
|
call ahead // Derik Phone #: ###-####
|
BLD-Energy code compliance | 3/20/2020 | 3/25/2020 | 3/25/2020 | P | CANC |
Tell Riley
|
|
|
Air seal - Derek Phone #: ###-####
|
BLD-Framing/Rough-in | 3/20/2020 | 3/25/2020 | 3/25/2020 | P | NR |
Tell Riley
|
|
|
Derek Phone #: ###-####//need mechanical passed first, no framing inspection completed, will need to reschedule after mechanical passes//
|
BLD-Other | 3/25/2020 | 3/25/2020 | 3/25/2020 | P | PART |
Tell Riley
|
|
|
sofit // Derek Phone #: ###-####//5/8 gyp ok per plans with vents per plans//CN issued for fascia, talked with plan review, will need approval from fire dept for combustible fascia//
|
BLD-Wall Bracing | 3/13/2020 | 3/16/2020 | 3/16/2020 | A | PASS |
Brandon Shaw
|
|
|
Derek Phone #: ###-####
|
BLD-Foundation | 2/7/2020 | 2/10/2020 | 2/10/2020 | A | PASS |
Tony Young
|
|
|
Dave Phone #: ###-####
|
BLD-Footing | 2/3/2020 | 2/6/2020 | 2/6/2020 | A | PASS |
Tony Young
|
|
|
Dave; Phone #: ###-####
|
BLD-Footing | 2/5/2020 | 2/5/2020 | 2/5/2020 | P | PASS |
Tony Young
|
|
|
Dave; Phone #: ###-####,, house footings ok now
|
BLD-Footing | 1/31/2020 | 2/3/2020 | 2/3/2020 | A | NR |
Tony Young
|
|
|
pour at 12 // Dave Phone #: ###-####,, needs soils approval,, ground is frozen
|
PubWorks Subgrade Approval | 2/3/2020 | 2/3/2020 | 2/3/2020 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 1/13/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 1/10/2020 | | |
|
|
|
|
Plan assigned to (J_N) | 11/15/2019 | 11/15/2019 | 1/10/2020 | | DONE |
Jenny Nelson
|
|
|
12/04 sfd L2 Paper. 1st complete 12/10, wui details, site plan, clarify water heater, energy code. Failed planning and mech
|
Inspection Record Card- Bld | | | 1/10/2020 | | DONE |
|
|
|
|
Telephone call | | | 1/10/2020 | | DONE |
|
|
|
Called and left a message for Josh letting him know that his permit is ready for pick up, what the fees are, and that he will need an RP.
|
Routing - PLAN CHECK | 1/10/2020 | | 1/10/2020 | | PASS |
Jenny Nelson
|
|
|
|
Case Summary (BLD) | | | 1/10/2020 | | DONE |
Jenny Nelson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/10/2020 | | DONE |
Jenny Nelson
|
|
|
|
Permit Ready to Issue | | | 1/10/2020 | | DONE |
|
|
|
met
|
Routing - PLANNING | 1/3/2020 | | 1/9/2020 | | PASS |
Nicolette Womack
|
|
|
|
Plan resubmittals received | | | 1/8/2020 | | DONE |
|
|
|
resubmittal: 2 sets of the following: A5, D1, C2.0, C1.0, ESC1.0
|
Routing - PLAN CHECK | 1/3/2020 | | 1/3/2020 | | FAIL |
Jenny Nelson
|
|
|
Still need site and grading plans, need to know siding material.
|
Route to Impact Fee Review | 12/31/2019 | 1/3/2020 | 1/2/2020 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plan resubmittals received | | | 12/31/2019 | | DONE |
|
|
|
Submittal of 2 copies of the following: CS, N, E1, A1, A1.1, A2, A3, A4, A5, A6, A7, A8, A9, A10, A11, D1, D2, D3, D4, D5, D6, D7, D8,, S0, S0.1, S1, S1.1, S1.2, S2, S2.1
|
Routing - FIRE | 11/15/2019 | 11/15/2019 | 12/10/2019 | | PASS |
Lee G Meredith
|
|
|
New SFH paper
Sprinklers are not required. No written review comments. provided.
|
1st review completed | | | 12/10/2019 | | DONE |
Jenny Nelson
|
|
|
|
Routing - PLAN CHECK | 11/15/2019 | | 12/10/2019 | | FAIL |
Jenny Nelson
|
|
|
|
Routing - Erosion and Sediment | 12/6/2019 | | 12/9/2019 | | PASS |
Andy J. Long
|
|
|
Home builder needs to list certfied Responsible Person. ESC plan approved. Site preparation inspection is REQUIRED.
|
Routing - MECHANICAL | 12/9/2019 | | 12/9/2019 | | PASS |
Troy James
|
|
|
|
Routing - MECHANICAL | 11/15/2019 | | 12/6/2019 | | FAIL |
Troy James
|
|
|
Emailed corrections to idaho hvac
|
Routing - PLANNING | 12/3/2019 | | 12/5/2019 | | FAIL |
Nicolette Womack
|
|
|
Grading Plan does not match house plans.
|
Routing - PUBLIC WORKS | 11/15/2019 | | 12/3/2019 | | PASS |
Candy A. Nichols
|
|
|
|
Routing PW Grading-Hillside | 11/18/2019 | | 12/3/2019 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Route to Impact Fee Review | 11/15/2019 | 11/18/2019 | 11/18/2019 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 11/15/2019 | | DONE |
|
|
|
|
Intake Approval | | | 11/15/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/15/2019 | | DONE |
|
|
|
|
Routing - Addressing | 11/15/2019 | | 11/15/2019 | | PASS |
Laura Hunter
|
|
|
|
BLD-Final | 8/13/2020 | 8/14/2020 | | A | |
Tony Young
|
|
|
screened // Joshua Phone #: ###-####
|
Application received | | 11/15/2019 | | | |
|
|
|
|