BLD-Final | 1/27/2020 | 1/28/2020 | 1/28/2020 | A | NR |
Mike Jordan
|
|
|
Please call Jared 15 minutes prior. Phone #: ###-#### Inspection requested via web by Jared Waggoner. Needs fire/life/safety finals.
|
BLD-Framing/Rough-in | 1/8/2020 | 1/9/2020 | 1/9/2020 | A | PASS |
Jim Storey
|
|
|
Women''s Restroom wall and ceiling framing for cover. Please call Jared 15 minutes prior, ###-####. Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
FIRE-Conference | 1/2/2020 | 1/2/2020 | 1/2/2020 | P | DONE |
Troy Cobbley
|
|
|
Myself and the general contractor went over potential fire alarm strobe placements issues caused by the new walls.
|
BLD-Framing/Rough-in | 12/30/2019 | 12/31/2019 | 12/31/2019 | P | PASS |
Mike Jordan
|
|
|
(2) vestibules for cover. Phone #: ###-#### Inspection requested via web by Jared Waggoner
|
Issue PAID IN FULL permit | | | 12/10/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/10/2019 | | DONE |
|
|
|
|
Telephone call | | | 12/10/2019 | | DONE |
|
|
|
emailed permit to be signed to- mike@russcorp.com
|
Plan assigned to (JG) | 11/21/2019 | 11/21/2019 | 12/4/2019 | | PASS |
Javier Guzman
|
|
|
12/02 L2 DXC Technology ePlan
|
Routing - PLAN CHECK | 11/21/2019 | | 12/4/2019 | | PASS |
Javier Guzman
|
|
|
|
1st review completed | | | 12/4/2019 | | DONE |
Javier Guzman
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/4/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 12/4/2019 | | DONE |
|
|
|
MET
Need
GC Form
Revised Cert of Value
|
Routing - MECHANICAL | 11/21/2019 | | 11/25/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 11/21/2019 | | 11/22/2019 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Addressing | 11/21/2019 | | 11/22/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 11/21/2019 | | 11/21/2019 | | PASS |
Morgan Webb
|
|
|
ONE LAV, THREE WC'S
|
Intake Approval | | | 11/20/2019 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 11/15/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 15 2019 1:42PM
|