BLD-Ceiling Grid Inspection | 7/21/2020 | 7/22/2020 | 7/22/2020 | A | PASS |
Jim Storey
|
|
|
Please call Jerry Jones before arrival ###-#### Phone #: ###-#### Inspection requested via web by Jerry Jones
|
Fees Due Hold | 5/8/2020 | | 5/27/2020 | | DONE |
Christina Prado
|
|
|
|
BLD-Framing/Rough-in | 5/7/2020 | 5/7/2020 | 5/7/2020 | P | PASS |
Jim Storey
|
|
|
Jerry *screened* Phone #: ###-####
|
Fees Due Hold | 4/21/2020 | | 5/7/2020 | | DONE |
Tiffany Carson-Herker
|
|
|
|
BLD-Ceiling Grid Inspection | 5/6/2020 | 5/6/2020 | 5/6/2020 | P | PASS |
Jim Storey
|
|
|
screened // Jerry Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 4/20/2020 | 4/20/2020 | 4/20/2020 | P | PART |
Jim Storey
|
|
|
Jerry **cleared** Phone #: ###-#### fire stopping emt/ duct/ plm south wall and east wall// ceilling supports ok.
|
Fees Due Hold | 2/28/2020 | | 4/20/2020 | | DONE |
Tiffany Carson-Herker
|
|
|
|
BLD-Wall Bracing | 2/27/2020 | 2/28/2020 | 2/28/2020 | A | PASS |
Jim Storey
|
|
|
Please call Jerry Jones (###-####) 10 minutes ahead of arrival @ B26 lobby. Phone #: ###-#### Inspection requested via web by Jerry Jones wall ok
|
Fees Due Hold | 2/14/2020 | | 2/27/2020 | | DONE |
Judith Amador
|
|
|
|
Permit Ready to Issue | | | 2/13/2020 | | DONE |
|
|
|
ALL MET- Need
(both forms are in eplan with dates from last year, we need updated forms with a current date)
GC Form
Revised Cert of Value
|
Issue & PRINT to be Invoiced | | | 2/13/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/13/2020 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 12/31/2019 | 12/31/2019 | 2/12/2020 | | PASS |
Carl D Madsen
|
|
|
Micron L-3
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/12/2020 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 2/5/2020 | | 2/12/2020 | | PASS |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 2/5/2020 | | 2/10/2020 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 2/3/2020 | 2/6/2020 | 2/4/2020 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 12/31/2019 | 12/31/2019 | 1/31/2020 | | PASS |
Mark Stumbaugh
|
|
|
01/22 Micron B26 Labs L3
|
1st review completed | | | 1/31/2020 | | DONE |
|
|
|
|
Routing - MECHANICAL | 1/24/2020 | | 1/24/2020 | | FAIL |
Troy James
|
|
|
Emailed corrections to applicant.
|
Routing - PLAN CHECK | 12/31/2019 | | 1/17/2020 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 12/31/2019 | | 1/6/2020 | | FAIL |
Troy James
|
|
|
Emailed applicant to upload mechanical engineered stamped plans for all mechanical work being performed.
|
Routing PW Environmental | 1/2/2020 | | 1/6/2020 | | PASS |
Rick Christenson
|
|
|
|
Routing - Addressing | 12/31/2019 | | 1/2/2020 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/31/2019 | | 1/2/2020 | | PASS |
Morgan Webb
|
|
|
CAPACITY PURCHASED. NOTIFIED ANGELA.
|
Intake Approval | | | 12/26/2019 | | PASS |
|
|
|
|
Application received | | | 11/19/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 19 2019 9:02AM
|