Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberBLD19-04595
StatusIssued
Name PRIMARY CONSTRUCTION INC
Site Address 13 S LATAH ST Unit: 103
Project NameBuilding C - Shell
Customer NumberBLD19-04591, 04593-04595
ePlanReview 
Description
**4 PERMITS IN EPLAN UNDER BLD19-04591** (BUILDING C - SHELL) (DRH19-00443) (GRD19-00109 Rough Grading) (BLD19-04951 Wash Bay Demo) Permit to construct a new 1,867 sq ft one-story wood-framed shell building for future occupancy. Three other structures will be located on this parcel: Canopy (BLD19-04591), Bldg A The Stil (BLD19-04593), Bldg B Shell (BLD19-04594). All structures are considered portions of one building for building height, stories, and area per 2015 IBC 503.1.2. If future A2 occupant load exceeds 100 occupants, sprinklers will be required. Future restrooms in Bldgs B and C are to have capacity to serve occupant load of Canopy. Approval is contingent upon adhering to the approved plans on file and attached engineering. This building is NOT Fire Sprinklered. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection8/6/20208/6/20208/6/2020 PASS
DetailsJim Storey
BLD-Foundation3/24/20203/25/20203/25/2020APASS
DetailsJim Storey
Stem wall inspection for Building C. Looking to pour late Wed/early Thur. Phone #: ###-#### Inspection requested via web by Ryan Wilhelm
BLD-Footing3/18/20203/19/20203/19/2020APASS
DetailsJim Storey
Footing inspection for Building C, planning to pour at 2pm. Phone #: ###-#### Inspection requested via web by Ryan Wilhelm
BLD-Footing3/13/20203/16/20203/13/2020ACANC
DetailsJim Storey
Footing/rebar inspection for Building C. Plan to pour PM. Phone #: ###-#### >> Inspection requested via web by Ryan Wilhelm Inspection cancelled from web by: Ryan Wilhelm
Issue PAID IN FULL permit  2/26/2020 DONE
Inspection Record Card- Bld  2/26/2020 DONE
Routing - Design Review11/25/2019 2/24/2020 FAIL
DetailsKatelyn Menuge
Routing - Design Review1/30/2020 2/24/2020 FAIL
DetailsKatelyn Menuge
Routing PW Drainage1/30/2020 2/24/2020 PASS
DetailsBrian Murphy
Routing PW Drainage2/19/2020 2/24/2020 PASS
DetailsBrian Murphy
Permit Ready to Issue  2/24/2020 DONE
4 PERMITS/DO NOT ISSUE W/OUT BLD19-04593, 04594, 04595
NEED
RP
GC
Revised Certificate of Value
Plan assigned to (JAR)11/25/201911/25/20192/22/2020 DONE
DetailsJulie Romig
1st Rev Comp - 2nd Comp - 502 13 S Latah (Building C)
PLANS/APPL TAKEN TO FRONT DESK  2/22/2020 DONE
Routing - PLAN CHECK2/19/2020 2/22/2020 PASS
DetailsJulie Romig
Routing Off Site - STRUCTURAL2/19/2020 2/22/2020 PASS
DetailsJulie Romig
KPFF 3rd Review
Routing - PLANNING1/30/2020 2/20/2020 PASS
DetailsKarla Nelson
Routing - Design Review2/19/2020 2/20/2020 PASS
DetailsKatelyn Menuge
Routing - PLANNING11/25/2019 2/20/2020 PASS
DetailsKarla Nelson
Routing PW Drainage12/3/2019 2/19/2020 PASS
DetailsBrian Murphy
Routing PW Street Lights12/3/2019 2/19/2020 PASS
DetailsTom Marshall
Routing PW Sewer Design12/3/2019 2/19/2020 PASS
DetailsDeAnn Brown
Routing PW Street Lights1/30/2020 2/19/2020 PASS
DetailsTom Marshall
Routing PW Sewer Design1/30/2020 2/19/2020 PASS
DetailsDeAnn Brown
Routing PW Solid Waste1/30/2020 2/19/2020 PASS
DetailsEvan Carpenter
Routing - PLAN CHECK1/30/2020 2/13/2020 FAIL
DetailsJulie Romig
Routing Off Site - STRUCTURAL1/30/2020 2/13/2020 FAIL
DetailsJulie Romig
Routing - PLUMBING1/30/2020 1/30/2020 PASS
DetailsDaryl Spivey
see redline notes
Route to Impact Fee Review1/22/20201/25/20201/23/2020 PASS
DetailsTravis P Black
Review requested for Commercial Permit
Routing - FIRE11/25/201911/25/20191/21/2020 PASS
DetailsGreg Ruxton
Attached comments to BLD19-04591

01/02 520Building C 13 S Latah
1st review completed  1/21/2020 FAIL
DetailsJulie Romig
Routing - PLAN CHECK11/25/2019 1/18/2020 FAIL
DetailsJulie Romig
Routing PW Solid Waste12/3/2019 1/13/2020 FAIL
DetailsEvan Carpenter
See comments under BLD19-04591.
Routing PW Environmental12/3/2019 1/8/2020 PASS
DetailsRick Christenson
Approved grease abatement per BLD19-04591
Routing Off Site - STRUCTURAL11/25/2019 12/23/2019 FAIL
DetailsJulie Romig
kpff
Routing - MECHANICAL11/25/2019 12/4/2019 PASS
DetailsTroy James
No mechanical work shown.
Routing - PUBLIC WORKS11/25/2019 12/3/2019 PASS
DetailsMorgan Webb
NO NEW PLUMBING AT THIS TIME. FUTURE TI FOR RESTAURANT IS EXPECTED. CREDIT FOR DEMO IS AVAILABLE.
Routing - Erosion and Sediment11/25/2019 11/26/2019 PASS
DetailsMichael Zawacki
Routing - Addressing11/25/2019 11/26/2019 PASS
DetailsDoug Chausow
Bldg 103
Routing - PLUMBING11/25/2019 11/25/2019 PASS
DetailsDaryl Spivey
Per plan and ISPC.
Intake Approval  11/21/2019 PASS
DetailsMichael Hanson
Application received  11/19/2019 DONE
Application submitted via PDS Online on Nov 19 2019 12:17PM