BLD-Final | 3/5/2020 | 3/6/2020 | 3/6/2020 | A | PASS |
Jim Storey
|
|
|
If the inspector has any questions regarding the systems installation or has any concerns, they can call our Regional Install Manager:Levi Henry- ###-#### Or they can call us at our office, Blue Raven Solar in the inspections Department at: ###-#### The homeowner will be present for the inspection, and has taken off time for this inspection. If they do not answer the door, please give them a call and leave them a message and give them a few minutes to get everything ready. Homeowner name and number: Edward Krogness: 2062950461 Phone #: ###-#### Inspection requested via web by BRS Permitting
|
DOC - Permit Finaled | 3/6/2020 | 3/6/2020 | 3/6/2020 | P | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 12/16/2019 | 12/17/2019 | 12/17/2019 | A | PASS |
Jim Storey
|
|
|
Please contact Brian Prussia with any questions or concerns Phone #: ###-#### Inspection requested via web by BRS Permitting // . No work needed to the existing roof structure per engineer’s roof evaluation.
|
Issue PAID IN FULL permit | | | 11/27/2019 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 11/21/2019 | 11/21/2019 | 11/26/2019 | | PASS |
Josh Bogle
|
|
|
11/27 PV, ePlan
|
Routing - PLAN CHECK | 11/21/2019 | | 11/26/2019 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 11/26/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/26/2019 | | DONE |
Josh Bogle
|
|
|
ESC no - Energy no
|
Permit Ready to Issue | | | 11/26/2019 | | DONE |
|
|
|
|
Application received | | | 11/21/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 21 2019 2:13PM
|
Plans ACCEPTED BY PLAN TECH | | | 11/21/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/21/2019 | | DONE |
|
|
|
|
Intake Approval | | | 11/21/2019 | | PASS |
|
|
|
|
Routing - PLANNING | 11/21/2019 | | 11/21/2019 | | PASS |
Sue Cummings
|
|
|
|