BLD-Final | 8/5/2020 | 8/6/2020 | 8/6/2020 | A | PASS |
Tell Riley
|
|
|
357
|
DOC - Permit Finaled | 8/6/2020 | 8/6/2020 | 8/6/2020 | P | PASS |
Tell Riley
|
|
|
|
BLD-Blower Door Test Results | 8/5/2020 | 8/6/2020 | 8/6/2020 | A | DONE |
Tell Riley
|
|
|
3.3 ACH 50
|
BLD-Final | 8/5/2020 | 8/5/2020 | 8/6/2020 | P | NR |
Tell Riley
|
|
|
Vince -*/Screened*/ Phone #: ###-####
|
BLD-Energy code compliance | 4/22/2020 | 4/22/2020 | 4/22/2020 | P | PASS |
Tell Riley
|
|
|
Vince Phone #: ###-####
|
BLD-Energy code compliance | 4/15/2020 | 4/16/2020 | 4/16/2020 | A | NR |
Tell Riley
|
|
|
Vince Phone #: ###-####//gas line test has failed//no inspection completed//not cover until inspection completed after gas line test has passed//
|
BLD-Framing/Rough-in | 4/10/2020 | 4/10/2020 | 4/10/2020 | P | PASS |
Tell Riley
|
|
|
vince - Screened for COVID 19 symptoms Phone #: ###-####//ok to insulate//see truss engineering for missed bracing, please provide engineering for patio cover//
|
BLD-Wall Bracing | 3/12/2020 | 3/13/2020 | 3/13/2020 | A | PASS |
Jim Storey
|
|
|
Vince Phone #: ###-####
|
BLD-Foundation | 2/12/2020 | 2/13/2020 | 2/13/2020 | P | PART |
Tell Riley
|
|
|
pat- foundation wall inspection Phone #: ###-####//WIP//will need to cover footings and wall for cold weather protection//
|
BLD-Footing | 2/11/2020 | 2/12/2020 | 2/12/2020 | P | PART |
Tell Riley
|
|
|
Pat Phone #: ###-####//Wip//bar installed//string set for easment, building appears to be outside of easment line based on strings set by contractor//no frost observed onsite at time of isnpection//blankets onsite//
|
Issue PAID IN FULL permit | | | 2/10/2020 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/10/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 12/16/2019 | | |
|
|
|
|
Plan assigned to (D_S) Debbie | 12/4/2019 | 12/4/2019 | 12/16/2019 | | DONE |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 12/16/2019 | | 12/16/2019 | | PASS |
Jenny Nelson
|
|
|
Per D_S review
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/16/2019 | | DONE |
Debbie Sanine
|
|
|
|
Permit Ready to Issue | | | 12/16/2019 | | DONE |
|
|
|
met
|
1st review completed | | | 12/5/2019 | | FAIL |
Debbie Sanine
|
|
|
|
Routing - PLAN CHECK | 12/2/2019 | | 12/5/2019 | | FAIL |
Jenny Nelson
|
|
|
Per D_S review
|
Plan assigned to (BJM) | 12/2/2019 | 12/2/2019 | 12/4/2019 | | DEFR |
Brian McGowan
|
|
|
12/13- SFD L1 ePlan
|
Routing - FIRE | 12/2/2019 | 12/2/2019 | 12/4/2019 | | PASS |
Lee G Meredith
|
|
|
per note on 11/29/19 from Gemma this needs to be routed to FIRE per Brian
Sprinklers are not required.
|
Route to Impact Fee Review | 12/2/2019 | 12/5/2019 | 12/3/2019 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 12/2/2019 | | 12/3/2019 | | PASS |
Laura Hunter
|
|
|
|
Routing - PUBLIC WORKS | 12/2/2019 | | 12/2/2019 | | PASS |
Candy A. Nichols
|
|
|
|
Routing - MECHANICAL | 12/2/2019 | | 12/2/2019 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 12/2/2019 | | 12/2/2019 | | PASS |
Sue Cummings
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/2/2019 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/2/2019 | | DONE |
|
|
|
|
Intake Approval | | | 12/2/2019 | | PASS |
|
|
|
|
Meeting | | | 11/29/2019 | | DONE |
|
|
|
Per Brian McGowan - route to FIRE
|
Intake Approval | | | 11/27/2019 | | FAIL |
|
|
|
We are now in the 2015 IRC code year. I Saw on your Cover Sheet that it had 2012 IRC code year listed. Please update the code year on all plans to the 2015 code year.
|
Intake Approval | | | 11/27/2019 | | FAIL |
|
|
|
Still says 2012 IECC.
|
Application received | | | 11/22/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 22 2019 2:27PM
|