BLD-Final | 1/30/2020 | 1/31/2020 | 1/31/2020 | P | PASS |
Brandon Shaw
|
|
|
Angie Phone #: ###-####
|
DOC - Permit Finaled | 1/31/2020 | 1/31/2020 | 1/31/2020 | P | PASS |
Brandon Shaw
|
|
|
|
FIRE-Final Inspection | 1/30/2020 | 1/31/2020 | 1/31/2020 | A | PASS |
Jim Page
|
|
|
No fire sprinkler modifications, no fire alarm modifications, fire extinguishers are placed with current inspection tags. Final life fire safety inspection for scope of work complete, signatures provided on permit sign off card.
Angie Phone #: ###-####
|
Permanent Occupancy | | | 1/31/2020 | | DONE |
|
|
|
|
Change Expiration Date Only | | | 1/9/2020 | | DONE |
|
|
|
permit was accidentally re-issued on 1/7/2020
|
Issue PAID IN FULL permit | | | 12/30/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 12/30/2019 | | DONE |
|
|
|
|
CHANGE ISSUED DATE | | | 12/30/2019 | | DONE |
|
|
|
permit was accidentally re-issued on 1/7/2020
|
CHANGE STATUS TO (RDY) | | | 12/17/2019 | | DONE |
|
|
|
was issues by mistake.
|
Route to Impact Fee Review | 12/12/2019 | 12/15/2019 | 12/13/2019 | | PASS |
Travis P Black
|
|
|
Review requested for Commercial Permit
|
Plan assigned to (JG) | 12/5/2019 | 12/5/2019 | 12/13/2019 | | PASS |
Javier Guzman
|
|
|
12/18 2nd rev comp, 12/10 L1 Zeppole Bakery TI - Add Sinks ePlan, pend PW Envior
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/13/2019 | | DONE |
|
|
|
|
Meeting | | | 12/13/2019 | | DONE |
|
|
|
this was accidently issued, informed Tisha
|
Permit Ready to Issue | | | 12/13/2019 | | DONE |
|
|
|
all met
NEED
GC
Revised Certificate Value
|
Routing PW Environmental | 12/12/2019 | | 12/13/2019 | | PASS |
Javier Guzman
|
|
|
signed off in ePlan by PW Pre-Treatment Zach Conde
|
1st review completed | | | 12/12/2019 | | FAIL |
Javier Guzman
|
|
|
|
Routing PW Environmental | 12/5/2019 | | 12/12/2019 | | FAIL |
Rick Christenson
|
|
|
No grease abatement shown on plans. Suitable and adequate grease abatement is required.
Contact Zach Conde at zconde@cityofboise.org or ###-#### with any questions.
|
Routing - PLAN CHECK | 12/12/2019 | | 12/12/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLAN CHECK | 12/5/2019 | | 12/10/2019 | | PASS |
Javier Guzman
|
|
|
|
Routing - PLUMBING | 12/5/2019 | | 12/6/2019 | | PASS |
Dan Ediger
|
|
|
Per plans and ISPC
|
Routing - Addressing | 12/5/2019 | | 12/5/2019 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 12/5/2019 | | 12/5/2019 | | PASS |
Morgan Webb
|
|
|
CUSTOMER SERVICE AREA THE SAME
|
Intake Approval | | | 12/4/2019 | | PASS |
Javier Guzman
|
|
|
|
Intake Approval | | | 11/27/2019 | | FAIL |
Joe Bruce
|
|
|
Provide the following items to complete the prescreen process:
1. Fill out and upload checklist form #518 into the documents folder. This form must accompany the submittal with all pages completed and filled out with page references. All items required by checklist must be uploaded. A complete prescreen review cannot be completed without the submission of a checklist.
2. Provide either an application for Central District Health Department for this food establishment or a stamped signed copy by CDHD for the revised food establishment license required for this tenant.
3. Provide an additional application to modify the adjacent tenant space that was previously being utilized by Zeppole Bakery under permit BLD17-00241. If Zeppole Baker intends to remain as a tenant, additional plumbing fixtures might be required for their tenant space.
|
Application received | | | 11/22/2019 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 22 2019 3:36PM
|