Permit Information
Permit NumberBLD19-04685
StatusIssued
Name BROWN BUILDING CO LLC
Site Address 4109 N EYRIE WAY
Project NameMaskell/Trebbi Residence
Customer Number 
ePlanReviewYes
Description
***W.U.I. FOOTHILLS LOT ZONE A; CLASS "A" ROOF AND NON-COMBUSTIBLE EXTERIOR MATERIALS REQUIRED*** Permit for the construction of a new 3186 sq. ft., two story (first story 1341 sq. ft., second story 1845 sq. ft.) single family dwelling with 4 bedrooms, 2.5 bathrooms, approximately 644 sq. ft. of covered patio/porch and a 1045 sq. ft. attached garage per the approved plans and any notations. Prescriptive Energy Compliance. A-1 zoning and setbacks per planning. ***RDP*** ***Sprinklers are being provided, as noted on the Site Plan - Cover Sheet drawing***LGM
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
1st review completed  12/16/2020 FAIL
DetailsRob Patrick
Routing - MECHANICAL8/6/2020 8/6/2020 PASS
DetailsTroy James
Resubmitted ACCA report
BLD-Foundation5/14/20205/15/20205/15/2020APART
DetailsTony Young
Phone #: 2086956103 >> Inspection requested via mobile web by Alvaro
BLD-Footing5/13/20205/14/20205/14/2020PPASS
DetailsTony Young
As early as possible Phone #: 2086956103 >> Inspection requested via mobile web by Alvaro,, garage areas
BLD-Foundation4/15/20204/16/20204/16/2020APART
DetailsTony Young
As early as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro
BLD-Footing4/8/20204/8/20204/8/2020PPASS
DetailsTony Young
As late as possible Phone #: 2089656103 >> Inspection requested via mobile web by Alvaro,, lower footings ok
PubWorks Subgrade Approval4/2/20204/2/20204/2/2020 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
Issue PAID IN FULL permit  3/25/2020 DONE
OVERRIDE  3/23/2020  
Plan assigned to (RDP)12/4/201912/4/20193/23/2020 DONE
DetailsRob Patrick
Resubmit Due 03/19: 02/18 2nd Review Passed waiting for Hillside... 1st Review Complete: 12/23 SFD L2 ePlan...02/03 Failed; Corrections Req'd for Hillside. 03/04 Failed: Engineering update is req'd.
Routing PW Grading-Hillside3/23/2020 3/23/2020 PASS
DetailsMelissa Jannusch

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
Routing - PLAN CHECK3/23/2020 3/23/2020 PASS
DetailsRob Patrick
PLANS/APPL TAKEN TO FRONT DESK  3/23/2020 DONE
DetailsRob Patrick
Permit Ready to Issue  3/23/2020 DONE
MET
Routing PW Grading-Hillside3/4/2020 3/4/2020 FAIL
DetailsMelissa Jannusch
see changemarks in ePlan
Routing - PLAN CHECK3/4/2020 3/4/2020 FAIL
DetailsRob Patrick
Engineering corrections req'd
Routing Off Site - STRUCTURAL3/2/2020 3/4/2020 FAIL
DetailsRob Patrick
Stapley Engineering
Plan Reviewer's activity  3/2/2020  
Phoned contractor and let him know 3rd party engineering should be completed today.
Routing - PLAN CHECK2/3/2020 2/3/2020 FAIL
DetailsRob Patrick
Corrections Req'd for Hillside. Complete engineering is req'd.
Routing PW Grading-Hillside1/31/2020 1/31/2020 FAIL
DetailsMelissa Jannusch
see changemarks in ePlan
Telephone call  12/31/2019 DONE
recieved email from Connor construction transferring case to Brown Building before permit issued. See docs
Routing - PLAN CHECK12/4/2019 12/16/2019 FAIL
DetailsRob Patrick
Corrections Req'd
Routing PW Grading-Hillside12/4/2019 12/13/2019 FAIL
DetailsMelissa Jannusch
see changemarks in ePlan
Route to Impact Fee Review12/4/201912/7/201912/6/2019 PASS
DetailsTravis P Black
Initial residential review of new SFD permits requested for now.
Routing - Addressing12/4/2019 12/5/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS12/4/2019 12/5/2019 PASS
DetailsCandy A. Nichols
Routing - FIRE12/4/201912/4/201912/4/2019 PASS
DetailsLee G Meredith
Sprinklers are being provided, as noted on the Site Plan - Cover Sheet drawing. No written review comments.
Routing - Erosion and Sediment12/4/2019 12/4/2019 PASS
DetailsMichael Zawacki
Site prep required.
Plans ACCEPTED BY PLAN TECH  12/4/2019 DONE
Recd Pcfee & Taken To Pln CK  12/4/2019 DONE
Intake Approval  12/4/2019 PASS
Routing - MECHANICAL12/4/2019 12/4/2019 PASS
DetailsTroy James
Routing - PLANNING12/4/2019 12/4/2019 PASS
DetailsLeon Letson
Approved per CFH19-00068
Application received  11/25/2019 DONE