BLD-Framing/Rough-in | 7/30/2020 | 7/30/2020 | 7/30/2020 | P | PASS |
Tony Young
|
|
|
Dale - */Screened*/ Phone #: ###-####
|
BLD-Energy code compliance | 7/29/2020 | 7/30/2020 | 7/30/2020 | P | PASS |
Tony Young
|
|
|
Tammy- */Screened*/ Phone #: ###-####
|
BLD-Framing/Rough-in | 7/29/2020 | 7/29/2020 | 7/29/2020 | P | PART |
Tony Young
|
|
|
Tammy- */Screened*/ Phone #: ###-####// needs fire blocking at ceiling line
|
BLD-Framing/Rough-in | 7/27/2020 | 7/28/2020 | 7/28/2020 | P | PASS |
Tony Young
|
|
|
SCREENED // Dale Phone #: ###-####
|
Telephone call | | | 7/7/2020 | | DONE |
|
|
|
Per attached letter from parcel owners, they are taking over as the permit holders.
|
BLD-Wall Bracing | 3/31/2020 | 3/31/2020 | 3/31/2020 | P | PASS |
Mike Jordan
|
|
|
for shear inspection Phone #: ###-#### Inspection requested via web by greg bauer
|
BLD-Conference | 3/11/2020 | 3/12/2020 | 3/12/2020 | A | DONE |
Dave Hannah
|
|
|
Regarding removing existing alley wall framing and replacing with new 2x6" wall with pressure treated sill plate. Phone #: ###-#### Inspection requested via web by greg bauer
|
BLD-Foundation | 2/25/2020 | 2/28/2020 | 2/28/2020 | A | PASS |
Dave Hannah
|
|
|
Phone #: ###-#### Inspection requested via web by greg bauer
|
BLD-Foundation | 2/24/2020 | 2/26/2020 | 2/26/2020 | P | NR |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by greg bauer
|
BLD-Foundation | 2/22/2020 | 2/24/2020 | 2/24/2020 | P | PART |
Tony Young
|
|
|
Phone #: ###-#### Inspection requested via web by greg bauer// footing for garage,/ ADU.. work in progress
|
Issue PAID IN FULL permit | | | 1/10/2020 | | DONE |
|
|
|
|
OVERRIDE | | | 1/9/2020 | | |
|
|
|
|
Telephone call | | | 1/9/2020 | | DONE |
|
|
|
Voicemail box is full. Emailed Greg to inform him the permit is ready, we need an RP and what fees are due.
|
Permit Ready to Issue | | | 1/9/2020 | | DONE |
|
|
|
NEED
RP
|
Plan assigned to (JAB) Josh | 11/26/2019 | 11/26/2019 | 1/8/2020 | | PASS |
Josh Bogle
|
|
|
*12/02 ADU, paper - 1st done
|
Plan resubmittals received | | | 1/8/2020 | | DONE |
|
|
|
Two copies of each Cover sheet, site plan, permit set, elevations, building sections, electrical plan, general notes, typical structural, footings, upper floor framing, roof framing, S5, S5.01 plan and Engineering documents stamped and taken to plan reviewer.
|
Routing - PLAN CHECK | 1/8/2020 | | 1/8/2020 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 1/8/2020 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 1/8/2020 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/8/2020 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Routing - PLAN CHECK | 12/27/2019 | | 12/27/2019 | | FAIL |
Josh Bogle
|
|
|
see e-mails to Greg & Walter
|
Plan resubmittals requested | | | 12/19/2019 | | DONE |
|
|
|
Two copies of Enigineering, two copies of plan sheets 0.0,1.0, 2.0, 3.0, 4.0, 5.0, S0.00, S0.01, S1.00, S1.01, S1.02, S5.00 and S5.01 taken to Josh
|
1st review completed | | | 12/5/2019 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 12/4/2019 | | 12/5/2019 | | FAIL |
Josh Bogle
|
|
|
see e-mail to Greg
|
Routing - MECHANICAL | | | 12/4/2019 | | PASS |
Troy James
|
|
|
Ductless system for heating. Energy star bath fan for mechanical ventilation.
|
Routing - PLANNING | 11/27/2019 | | 12/2/2019 | | FAIL |
David Moser
|
|
|
Rear eave crosses property line and recorded deed restriction and conditions of approval, letter from Idaho Power
|
Routing - PLANNING | 12/2/2019 | | 12/2/2019 | | PASS |
Ted Vanegas
|
|
|
|
Route to Impact Fee Review | 11/26/2019 | 11/29/2019 | 11/27/2019 | | PASS |
Travis P Black
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 11/26/2019 | | 11/27/2019 | | PASS |
Laura Hunter
|
|
|
ADU address is: 2121 W Hazel St. Added fee
|
Routing - PUBLIC WORKS | 11/26/2019 | | 11/27/2019 | | PASS |
Candy A. Nichols
|
|
|
ADU
|
Plans ACCEPTED BY PLAN TECH | | | 11/26/2019 | | DONE |
|
|
|
|
Intake Approval | | | 11/26/2019 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 11/26/2019 | | DONE |
|
|
|
|
Application received | | 11/26/2019 | | | |
|
|
|
|