Permit Information
Permit NumberBLD19-04743
StatusFinaled
Name PETER HARRIS CONSTRUCTION INC
Site Address 2593 N BIRD ST
Project NameLot 11 Block 1 Lodestar
Customer Number 
ePlanReviewYes
Description
**PRESCRIPTIVE ENERGY REQUIREMENT**Permit for the construction of a new 1748 sq. ft., one story single family dwelling with 3 bedrooms, 2 bathrooms, approximately 125 sq. ft. of covered patio/porch and a 462 sq. ft. attached garage per the approved plans and any notations. R-1C zoning and setbacks per planning. D_S ***Sprinklers are not required***LGM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Blower Door Test Results5/29/20205/29/20205/29/2020PDONE
DetailsTell Riley
2.71 ACH 50
BLD-Final5/28/20205/29/20205/29/2020APASS
DetailsTell Riley
We''ve completed the door blast and relocated the carbon monoxide detector.
Thanks, Phone #: ###-#### Inspection requested via web by Peter Harris//corrections made final completed//
DOC - Permit Finaled5/29/20205/29/20205/29/2020PPASS
DetailsTell Riley
corrections made final complete
BLD-Final5/27/20205/28/20205/28/2020ANR
DetailsTell Riley
House will be open. Cleaner will be be the only ones there tomorrow Phone #: ###-#### Inspection requested via web by Peter Harris//need blower door test//move combo smoke/co near master to 3 feet away from return duct//
BLD-Energy code compliance3/25/20203/27/20203/27/2020APASS
DetailsTell Riley
Phone #: ###-#### Inspection requested via web by Peter Harris
BLD-Framing/Rough-in3/24/20203/25/20203/25/2020APASS
DetailsTell Riley
Christina Phone #: ###-####
BLD-Wall Bracing3/4/20203/5/20203/5/2020APASS
DetailsTell Riley
Christina Phone #: ###-####
BLD-Foundation2/13/20202/14/20202/14/2020PPASS
DetailsTell Riley
Brian Phone #: ###-####//wall ok//
BLD-Footing2/12/20202/13/20202/13/2020PPART
DetailsTell Riley
Brian Phone #: ###-####//contractor is diging out frost areas and heating with torches onsite//WIP with frost//pour at own risk if frost is not completly removed//areas outside of shade ground temps ok and no frost//
BLD-Footing2/11/20202/12/20202/12/2020PFAIL
DetailsTell Riley
Brian Phone #: ###-####//1/2 of footings subgrade frozen//
Telephone call  2/4/2020 DONE
Emailed Peter to inform him not all of the fees for this project have been paid. Once the remaining fees have been paid we then can issue the permits.
Issue PAID IN FULL permit  2/4/2020 DONE
Inspection Record Card- Bld  2/4/2020 DONE
OVERRIDE  1/9/2020  
Plan assigned to (D_S) Debbie12/16/201912/16/20191/9/2020 DONE
DetailsDebbie Sanine
Routing - PLANNING1/9/2020 1/9/2020 PASS
DetailsSue Cummings
PLANS/APPL TAKEN TO FRONT DESK  1/9/2020 DONE
DetailsDebbie Sanine
Permit Ready to Issue  1/9/2020 DONE
Routing - PLAN CHECK1/8/2020 1/8/2020 PASS
DetailsJenny Nelson
Per D_S review
Routing - FIRE12/16/201912/16/201912/17/2019 PASS
DetailsLee G Meredith
New SFH

Sprinklers are not required.
1st review completed  12/17/2019 FAIL
DetailsDebbie Sanine
Plan assigned to (BJM)12/5/201912/5/201912/16/2019 DEFR
DetailsBrian McGowan
12/18- SFD L1
Routing - PLAN CHECK12/5/2019 12/16/2019 FAIL
DetailsJenny Nelson
Per D_S review
Route to Impact Fee Review12/5/201912/8/201912/6/2019 PASS
DetailsTravis P Black
Initial residential review of new SFD permits requested for now.
Routing - MECHANICAL12/5/2019 12/6/2019 PASS
DetailsTroy James
Routing - PLANNING12/5/2019 12/5/2019 FAIL
DetailsSue Cummings
Need to see driveway location and width.
Routing - Addressing12/5/2019 12/5/2019 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS12/5/2019 12/5/2019 PASS
DetailsCandy A. Nichols
Plans ACCEPTED BY PLAN TECH  12/5/2019 DONE
Recd Pcfee & Taken To Pln CK  12/5/2019 DONE
Intake Approval  12/5/2019 PASS
Application received  12/4/2019 DONE
Application submitted via PDS Online on Dec 4 2019 11:25AM